Church Street works

Auckland City Pavement Rehabilitation Works / Church Street (Mount Joy), Onehunga.

This pavement rehabilitation work consist of two stages:

Stage 1 involves driveway, kerb, channel and catchpit renewals work. Works will be undertaken during the days. Two-lanes two-way traffic will be in operation at all times.

Stage 2 involves milling of the section of Church Street between Mount Joy Place and the rail-crossing and reinstatement with structural asphalt layers and new surfacing. Works will be undertaken during the nights and will involve the road closure of Church Street between Alfred Street and Captain Springs Road.

Works for Stage 1 are due to be carried out during the week starting 21 January 2008. Works for Stage 2 are due to  be carried out during the week starting 02 March 2008.

We apologise for any inconvenience during this work and thank you for your cooperation.