Skip navigation

Central Connector

Introduction | Works update | Central Connector route | Grafton Bridge | Central Connector design plans | Streetscape improvements  | Changes to key intersections | Stay informed


Works update

Anzac Avenue

Anzac Avenue's dedicated bus lanes are working well, and the pedestrian environment has been greatly improved, with new crossings and traffic islands ensuring their safety.

Lower Symonds Street

The area near The University of Auckland is now completed, creating a better environment for students and other users of the area.

A new pedestrian crossing outside the university's Recreation Centre means people can easily cross Symonds Street, additional street lighting makes the area safer at night, and the addition of new footpaths, trees and landscaping makes the area inviting and attractive.

The project team wants to remind people to keep to designated paths so the new landscaping has a chance to establish itself.

Upper Symonds Street

Progress is good in this area, with the outbound side of Upper Symonds Street nearing completion, and work underway on the inbound side, outside The Langham Hotel. Work on this section of Symonds Street is scheduled to be complete in September.

Park Road

Work on Park Road outside the shops and Medical School continues, and is scheduled to be complete next month. Work by Metrowater and Telecom was completed in conjunction with council's work in this area, to minimise disruption in the future.

DART rail connections

Work by ONTARCK at Khyber Pass Road is progressing well on the middle section of the rail overbridge and work is nearly finished on the eastern side of Park Road. ONTRACK will soon shift traffic so they can begin on the second phase of construction. All overbridges are being rebuilt to provide adequate clearances for electric trains in the future, and at Khyber Pass and Park Roads, the cutting beneath the bridges is being widened to allow room for a second track.

Hours of work

Work is carried out between 7am and 7pm, Monday to Friday and 8am to 5 pm Saturday. There will also be some work overnight.

Details of work

The work in the Anzac Avenue, Park Road and Symonds Street areas involves improving pedestrian crossings and widening the roads for bus lanes.

In addition, Auckland City Council is working closely with Metrowater to replace about 2.2km of water main pipes on Park Road.

Metrowater is planning sewer separation works in the Grafton area to reduce the amount of wastewater that overflows into the harbour after heavy rain.

During construction on Park Road, two of the four lanes remain open. There is no parking on Park Road for the duration of work in this area.

Work on Grafton Bridge

The work involves strengthening the bridge columns with steel bar reinforcements, strengthening the bridge beams with carbon fibre and installing new reinforcements to resist horizontal earthquake movement. There will also be some restoration work including repairing cracks in the concrete, removing algal growth and replacing joints and bridge bearings. Work on the heritage icon, is necessary to bring it up to modern environmental and transport standards. Recent structural investigations found earthquake resistance was not considered in the bridge's original design and that heavy transport, including buses, cannot currently use the bridge.

Construction timeline
August 2009 - Work ends on Park Road
September 2009 - Work starts on Upper Symonds Street
October 2009 - Work ends on Grafton Bridge
October - Central Connector becomes operational

Central Connector map highlighting the key stages in which work will be carried out.

 

Updated July 2009

Copyright © 2009 Auckland City Council. All rights reserved.