Dominion Road 2016
Introduction and background
| What does the
project involve
| Timing | Funding
| How will you be affected? |
Maps of Dominion Road | Next steps
Timing
The scale of the works, the impact on the 290 properties
directly affected, and the costs associated with the project present practical
reasons for staging the improvements over a 12-year period. This means people
will see gradual improvements rather than a sudden transformation.
Improvements are scheduled to take place
between 2012 and 2016 to coincide with the forecasted traffic growth that
justifies their construction. The construction work has been scheduled to begin
after the Rugby World Cup in 2011.
The projected programme of physical works is outlined
below.
|
When |
What will you see? |
What will it offer? |
|
Stage 1
2012 |
Upgraded bus stops and
associated streetscape improvements, mid-block improvements, and wider
bus lanes to the southern end of the Valley Road shops
|
These measures offer
immediate passenger benefits as well as an opportunity to improve
shelter, ticketing and information facilities at bus stops. The time it
takes for passengers to get on the bus will be reduced.
|
|
Stage 2
2013 to 2014
|
Upgraded bus stops and associated streetscape
improvements, mid-block improvements, and wider bus lanes from the
southern end of the Valley Road shops to the southern end of Dominion
Road
|
Bus lanes on Dominion
Road will be brought up to Australasian standards, meaning that buses
can more easily pass the growing numbers of cyclists and traffic queues.
|
|
Stage 3
2014 to 2015
|
The Valley Road
deviation and streetscape improvements within the shopping centre
|
The deviation (the
final design is yet to be confirmed) is expected to offer greatly
improved waiting areas for passengers (particularly for those travelling
to Auckland's CBD) and good pedestrian connections to the surrounding
shopping area. It will also opportunities for streetscape improvements
to benefit the retail centre.
|
|
Stage 4
2015 to 2016
|
The Balmoral Road
deviation and streetscape improvements within the shopping centre |
Similar to the Valley
Road intersection, growing congestion at the intersection of Balmoral
and Dominion roads may justify a deviation off Dominion Road. Because of
the much higher existing capacity of the Balmoral
Road intersection,
this deviation won't be required until towards the end of the work
period.
|