I hereby give notice that an extraordinary Annual Plan Direction Setting
meeting of the
Members: * All Councillors are deemed members of the Finance and
Corporate Business Committee for Annual Plan purposes
APOLOGIES
At the close of the agenda no apologies had been received.
EXTRAORDINARY BUSINESS
Section 46A(7) of the Local
Government Official Information and Meetings Act 1987 (as amended)
states:"An item that is not on the
agenda for a meeting may be dealt with at that meeting if-
- The local authority by
resolution so decides; and
- The presiding member explains
at the meeting at a time when it is open to the public,-
- The reason why the item is not on the
agenda; and
- The reason why the discussion of the item
cannot be delayed until a subsequent meeting."
Section 46A(7A) of the Local
Government Official Information and Meetings Act 1987 (as amended)
states:
"Where an item is not on the
agenda for a meeting,-
- That item may be discussed at
that meeting if-
- That item is a minor matter relating to the
general business of the local authority; and
- The presiding member explains at the
beginning of the meeting, at a time when it is open to the public, that
the item will be discussed at the meeting; but
- no resolution, decision, or
recommendation may be made in respect of that item except to refer that
item to a subsequent meeting of the local authority for further
discussion."
THE CHIEF EXECUTIVE'S OVERVIEW OF DIRECTION SETTING FOR
THE DRAFT 2006-2016 LONG-TERM COUNCIL COMMUNITY PLAN
| L Manaia |
|
| Committee Manager |
3 November 2005 |
The Chief Executive provides an overview of the strategic and funding
contexts for the development of the Long Term Council Community Plan (LTCCP)
2006 2016.
This item was not available at the time the agenda went to print and will be
circulated under separate cover.
SUMMARISED 10 YEAR PROJECTIONS OF SOME KEY PARAMETERS AFFECTING
AUCKLAND CITY
| S R Vaughan |
|
| Strategy Manager Public Policy |
25 October 2005 |
Summarising projections as well as underlying assumptions over the period of
the Long Term Council Community Plan (LTCCP), and providing estimates of the
likely variability of the projections.
Recommending that council note and consider in their deliberations as part
of the development of the LTCCP, projections of key variables affecting Auckland
City, in particular:
- continued population growth
- increasing ethnic diversity
- significant movement of people into and out of the city.
- expected good economic performance relative to New Zealand as a whole
- low uptake of digital technology
- continued attention required to environmental quality
- risks to the health of the population.
| [ATTACHMENT 4] |
Pages 1 - 17 |
OVERVIEW OF THE FUTURE AUCKLAND COMMUNITY OUTCOMES
| Simon Harvey |
|
| Strategic Policy Analyst |
26 October 2005 |
Reporting that twenty-one community outcomes have been identified which
summarise the findings of the research and consultation process. Four of the
outcome statements relate to the leadership outcome area. The remaining
seventeen relate to the four well-being areas.
The community outcomes, and how they have been identified, will be described
in the Long Term Council Community Plan (LTCCP), together with a description of
how council's activities will contribute to those outcomes. The LTCCP will also
outline how council will work with local, regional, public and private
organisations, Maori and central government to further community outcomes.
Recommending that the 21 community outcomes be noted including the top three
priority outcome areas identified in the research:
- Auckland is safe
- Auckland has real transport choices
- Auckland is interesting and enjoyable.
| [ATTACHMENT 5] |
Pages 1 - 26 |
UPDATE: PROGRESS TOWARDS A STRATEGIC DIRECTION FOR AUCKLAND CITY
| N de Blaauw |
|
| Strategic Policy Analyst |
11 November 2005 |
Advising that it is time for council to renew the strategic direction for
Auckland city. The process has commenced, with a councillor workshop preceded
by individual councillor interviews. The two major cluster issues identified by
councillors were - managing and benefiting from growth; and enabling better
mobility for people and goods.
A pyramid methodology developed and trialled by council's senior management
for scoping the preferred destination was used at the councillor workshop, which
identified themes and the direction in which the city should be heading.
Recommending that council confirm the initial statement of the strategic
destination of Auckland city in preparation of the draft Long Term Council
Community Plan and that a programme for consultation be planned and reported to
the March 2006 Combined Committees. Further, that council agree to undertake a
review of the outstanding strategic plan milestones.
| [ATTACHMENT 6] |
Pages 1 - 8 |
LEADING IN URBAN SUSTAINABILITY
| L Manaia |
|
| Committee Manager |
3 November 2005 |
| This report was not available
at the time the agenda went to print and will be circulated under
separate cover. |
LONG TERM COUNCIL COMMUNITY PLAN
| Robert Nelson |
|
| LTCCP Champion |
26 October 2005 |
Reporting that Auckland City is required by the Local Government Act to
prepare and adopt a Long Term Council Community Plan (LTCCP) by 30 June 2006.
The report outlines the LTCCP requirements, process and milestones.
Recommending that the report by Robert Nelson dated 26 October 2005 outlining
the Long Term Council Community Plan requirements, process and milestones be
received.
| [ATTACHMENT 8] |
Pages 1 - 4 |
OPERATIONAL EXPENDITURE 2006/2007 TO 2008/2009
| Colin Field |
|
| Manager Financial Planning |
30 October 2005 |
Updating projections for the 2006/2007, 2007/2008 and 2008/2009 financial
years and outlining the impacts on rates.
Recommending that the committee note the shortfall of $700,000 in 2006/2007
and that new services are not included in these budget projections.
| [ATTACHMENT 9] |
Pages 1 - 10 |
CAPITAL EXPENDITURE FUNDING FOR THE 2006-2016 LTCCP
| Philip Neutze |
|
| Financial Strategy Manager |
3 November 2005 |
Nine new capital expenditure ("capex") projects totalling approximately $90
million were approved by Combined Committees on 23 June. Officers do not
recommend council decide on funding for these projects ahead of formulating the
integrated funding package for the Long Term Council Community Plan (LTCCP).
Integrated funding recommendations will be provided to the 15 December Annual
Plan Direction Setting meeting including scenarios illustrating the impacts of
progressing at different speeds and/or to different levels of achievement with
the strategic vision.
Under current policy setting, council's funding sources for capital
expenditure are fully committed for the next ten years. Other capital funding
alternatives will need to be considered.
Recommending that council notes:
- the 'master list' contained in Appendix I summarising potential new capex projects across council at various stages of investigation that have some
alignment with the strategic vision being developed by council.
- that officers will report back to council at the 15 December Annual
Planning Direction Setting meeting with:
- a first cut of alternative costed scenarios illustrating
the impacts on ratepayers of progressing at different speeds and/or to different
levels of achievement with the strategic vision.; and
- integrated funding recommendations for the $90 million new capex projects approved by council in June 2005 as well as the costed scenarios.
| [ATTACHMENT 10] |
Pages 1 - 17 |
FOUR LEVERS
| Robert Nelson |
|
| LTCCP Champion |
26 October 2005 |
Reporting that council is required to adopt a balanced budget for each of the
10 years in the Long Term Council Community Plan (LTCCP) which means a base
operating surplus of $15.5 million per annum. This report advises that four
levers are available to council that can be applied to produce a balanced
budget:
- What we do
- Service levels
- Generating additional revenue
- Being efficient and effective
Recommending that the initiatives are grouped under the four levers by the
General Manager Finance during the LTCCP budget process, and report to the March
2006 meeting of Combined Committees identifying achievements under each of the
levers.
| [ATTACHMENT 11] |
Pages 1 - 8 |
RATING REPORTS
12
12.1. OVERVIEW OF RATING POLICY ISSUES
| Catherine Temple / Grant McInman |
|
| Revenue Strategy Manager, Treasury /
Group Manager, Data Services |
2 November 2005 |
Providing an overview of the key rating issues for the Long Term Council
Community Plan for 2006-2016.
Recommending that the:
- general rate for 2006/2007 increase by at least the expected rate
of inflation
- next step of the general rate differential strategy be applied in
2006/2007
- $95 uniform annual general charge in the general rate be retained
for 2006/2007
- refuse collection targeted rate be increased
- Central Business District (CBD) targeted rate on CBD
non-residential ratepayers be increased to match the decrease in that group's
general rate
- four targeted rates for transport, open spaces and volcanic cones,
community development and housing, and heritage and urban design be increased
for 2006/2007 by the expected rate of inflation
- due dates for Auckland City's rate instalments in 2006/2007 be
brought forward by one month and that rate instalments be moved to a four
instalment pattern.
| [ATTACHMENT 12.1] |
Pages 1 - 24 |
12.2. NOTICE OF MOTION : RATES PARAMETERS
| Doug Armstrong |
|
| Councillor |
21 October 2005 |
Advising that it is important to provide guidelines to officers on overriding
considerations; the most important of which is the capacity to increase rates in
the 2006/2007 year.
Recommending that officers be instructed to prepare papers on the basis that
rate increases for the 2006/2007 year be kept within the rate of inflation.
| [ATTACHMENT 12.2] |
Pages 1 - 2 |
DEVELOPMENT CONTRIBUTIONS POLICY FOR 2006: UPDATE ON
EXPECTED CHANGES
| G Marr / M Dendale |
|
| Project Manager / Manager Financial
Contributions |
27 October 2005 |
Proposing that the development contributions policy is extended through the
introduction of a new activity to recover growth costs, such as transport; a
review of the charges for activities already included in the policy (community
amenities, parks community and reserves, and stormwater as these charges are
expected to increase); and the extension to the policy to recover the growth
costs relating to the proposed new library building for Waiheke Island. The
expected changes to the policy continue the incremental improvement of Auckland
city's approach to funding growth.
Recommending that the committee notes that work is underway to extend the
development contributions policy to recover more of the growth costs for the
activities included in the existing policy, and to include charges for a new
transport activity. Further, to note that work is underway to extend the
development contributions policy to include recovery of the growth component of
the proposed library building for Waiheke Island.
| [ATTACHMENT 13] |
Pages 1 - 10 |
2006-2016 LONG TERM COUNCIL COMMUNITY PLAN (LTCCP) POLITICAL
PROCESS
| Lee Manaia |
|
| Committee Manager |
17 October 2005 |
Reporting on the proposed consultation, submission and hearings processes for
the 2006-2016 long-term council community plan.
Recommending that the time-line and processes be adopted, the information
booths continue at shopping centres and local markets and that stakeholder
forums be held as set out in the report. Furthermore, that the hearings process
under Option A of the report be adopted.
| [ATTACHMENT 14] |
Pages 1 - 12 |