Auckland's CBD Into the Future
Introduction |
Street and open space upgrades |
The CBD Board |
Research |
Quarter plans |
Funding |
The guiding documents |
Residents advisory group |
Action plan
>>Back to
Funding and budget
Projects in progress or planned from July 2008 to June 2014
Project
|
Budget
|
Planned Dates
|
|
Planning and Policy
|
|
Quarter planning and implementation (Victoria and
Aotea) |
$500,000 |
2009-2013 |
|
Invest Auckland CBD |
$200,000 |
2008-2011 |
|
CBD destination marketing implementation |
$1,400,000 |
2008-20014 |
|
Retail Strategy implementation |
$350,000 |
2009-2012 |
|
Central Area Plan changes |
$300,000 |
2009-2011 |
|
Participation programme |
$46,000 |
2009-2014 |
|
CBD action plan review |
$300,000 |
2010-2011 |
|
|
$3,096,000 |
|
|
Street and open space upgrades
|
|
Fort Street area |
$22,996,000 |
2009-2013 |
|
Aotea Square redevelopment (including Civic
underground carpark repairs) |
$80,000,000 |
2009-2011 |
|
St Patrick's Square upgrade |
$8,997,000 |
2008-2010 |
|
Upper Khartoum Place upgrade |
$1,010,126 |
2009-10 |
|
Lorne Street upgrade Stage 2 |
$10,887,000 |
2009-2011 |
|
Elliot Street and Darby Streets |
$9,479,000 |
2009-2012 |
|
O'Connell Street |
4,367,000 |
2010-2013 |
|
Swanson Street stage 2 |
$960,000 |
2008-2009 |
|
Exchange Lane |
$547,000 |
2008-2014 |
|
Kitchener Street (south) |
$799,000 |
2008-2009 |
|
Durahm Street lighting |
$72,077 |
2008-2009 |
|
Vulcan Lane lighting |
$80,000 |
2008-2009 |
|
Lorne Street lighting |
$176,339 |
2008-2009 |
|
|
$140,370,542 |
|
|
Capital works
|
|
Art gallery redevelopment (council contribution) |
$58,100,000 |
|
|
Q Theatre (council contribution) |
$9,600,000 |
2011 |
|
|
$67,700,000 |
|
|
Transport
|
|
Central Connector (council contribution) |
$9,000,000 |
2008-2010 |
|
|
$9,000,000 |
|
|
Events
|
|
Events Diwali Festival, Lantern Festival, AK09,
etc |
$8,000,000 |
2008-2014 |
|
Events to activate the streets |
$300,000 |
2009-2014 |
|
Living Room |
$600,000 |
2009-2014 |
|
|
$8,900,000 |
|
|
Waterfront
|
|
Land acquisitions |
$22,562,400 |
2010-2019 |
|
Te Wero Bridge |
$41,444,000 |
|
Fanshawe Street underpass/overpass |
$0 |
|
Marine Events Centre |
$30,454,000 |
|
Teal Park |
$0 |
|
Harbour Bridge park |
$2,936,538 |
|
Wynyard Quarter development |
$94,053,389 |
|
Queens Wharf redevelopment |
$84,344,000 |
|
Westhaven infrastructure |
$19,087,497 |
|
Other |
$34,140,000 |
|
Total |
$329,021,824 |
|
|
|
|
|
|
TOTAL |
$787,154,908 |
|
Another key project in the CBD includes the $350 million
Britomart above ground project, New Zealand's largest heritage redevelopment.
The project, to be carried out by Bluewater, entails the renovation of 18
heritage buildings and the development of eight new buildings in the Britomart
precinct. This is not included in the overall council funding figures.
Published July 2009
|