Queen Street upgrade

Project summary | Mobility parking | Consultation | Budget and funding | Trees | | Artworks | Urban design | Heritage | Auckland's CBD Into the future strategy | CBD retail strategy | Facts | History of Queen Street | Reducing the speed limit


Budget and funding

 The project budget has significantly increased from the original estimated budget, largely due to rising construction costs and changes to the project design following consultation.

Queen Street upgrade budget history.

Date

Total cost

Components

Description

2003

$23.4 million

 

The original project budget for the whole of Queen Street (Customs Street to Karangahape Road), was based on preliminary concepts and funded from the general rate. It excluded major service diversions and escalation in construction costs.

2004

$26.1 million

$2.7 million

An additional $2.7 million from the CBD targeted rate was added to include pedestrian canopies and upgrading the entrance to Myers Park.

March 2005

$27.3 million

$27.3 million

The project cost estimate was updated in March 2005 when the revised concept design was completed. The increase was based on a Quantity Surveyor estimate for anticipated costs, including escalated construction costs.

June 2005 $30 million $3 million The total cost included a $3 million sum required to cover the costs of canopies and the Myers Park entrance. Funding to this level was included in the council's 2005/2006 annual plan.

December 2005

$30.6 million

 

The detailed design was finalised for the section between Customs Street and Mayoral Drive. The proposed Mayoral Drive to Karangahape Road block was excluded from the scope of the project in order to meet the budget. The extra $600,000 was funded from the targeted rate.

June 2006

$40.1 million

$36.6 million

 

 

 

 

 


$3.5 million
 

An additional $5 million was added to the $30.6 budget for the Customs Street to Mayoral Drive block ($3.5 million associated with Queen Street trees issue and $1.5 million associated with an urban design capex review).

A further $1 million was allocated to support a greater level of resource and communications and marketing.

This additional funding came from the targeted rate.

Funding was reinstated in the annual plan (via the targeted rate) to complete the southern section from Mayoral Drive to Karangahape Road.

July 2007

$42.5

 

The estimate for the southern section of Queen Street (from Mayoral Drive to Karangahape Road) was increased to $5.9 million due to higher quality urban design outcomes required.

 

 