Introduction

We're getting on with upgrading a majority of the walking tracks that run throughout the Auckland Domain from January 2008 through to mid February 2009.

The improvements will result in a network of tracks that are accessible and more enjoyable in all weather conditions.


What will be involved

Auckland City Council contractors will be upgrading one to two tracks at a time. Improvement work includes the resurfacing and upgrading of steps and surface drainage. Some tracks may require more work than others.


Programme of works

Track Planned upgrade date
Domain Walk Part 1 Mid-February 2009
Bush Walk Mid-February 2009
Bledisloe Walk Mid-February 2009
Domain Walk Part 2 Mid-February 2009
Lower Domain Drive to Carpark Track Completed in 2008
Glade Path Completed in 2008
Nikau Walk Completed in 2008
Lovers Walk/Glade Walk link Completed in 2008
Lovers Walk Completed in 2008
Lovers Walk/Centennial Walk link (lower and upper) Completed in 2008

You can view the site plan showing the locations of the walkways in PDF format:
Domain walkways upgrade siteplan (420kb PDF)

PDF icon To view PDFs download Acrobat Reader from the Adobe website. Further help on how to view PDFs.


Closures during the upgrade

In some cases the tracks be closed while works are in progress. Contractors will be required to close some of the tracks while work is taking place. Other tracks will remain open but caution should be taken.

Signs will indicate whether or not a track is closed during its upgrade or if caution is necessary.

To ensure you encounter minimal disruption while improvements are taking place, keep in mind the schedule above and try to plan alternate routes just in case.