Consultation and next steps

The council consulted with key stakeholders and the public between April and July 2009.

236 submissions were received of which 56 % were supporting the proposed changes, 23 % were against.

After considering all the submissions the August 2009 Transport Committee resolved:

 (A) That the proposed clearway extensions and no stopping restrictions along the Manukau Road section of the CBD to Airport route be implemented.

 (B) That the proposed right turn restrictions at Rangiatea Rd, Gardner Rd and Onslow Ave. be reviewed in line with the related opposing submissions.

Next steps

  • A review of the right turn bans has concluded that they will not be included in the proposed changes which will be implemented.
  • The procurement process has started to select a consultant to prepare final design plans for the proposed improvements.
  • The procurement for a contractor to undertake the physical works is expected to be completed by October 2009
  • Construction is expected to finish by February 2010.

 

 