Newmarket Park remediation
Introduction | Background
| Project update | Project documents
and plans
Introduction
Auckland Council has carried out remediation and stabilisation works at
Newmarket Park, Parnell.
The remediation and stabilisation works were completed on 24 May 2011 and a new contract is now in place for final site tidy-up with completion expected
in April 2012.
Background
Newmarket Park is a closed landfill with a southern slope that was
historically prone to
slips. The remediation works were carried out to address ongoing public
health and safety and environmental risks.
The remediation works involved:
- removal of the existing vegetation on the southern slope
- excavation and rebuilding of the slope
- revegetation with native plants and
trees.
Detailed ecological mitigation and landscaping plans for the site were consulted
on during 2009 and these plans were implemented.
 |
Newmarket Park showing location of southern slope.
Sourced from Land Information New Zealand data. Crown Copyright Reserved |
|
 |
 |
| Newmarket Park showing southern slope
during works and following completion. |
|
Project update
|
Timeline for 2011/12 |
|
Completed to date |
December 2011 |
January 2012 |
February - April 2012 |
- Stabilisation and landscaping of the southern slope completed.
- Walking paths on southern slope completed.
- Reinstatement of car park footpaths completed.
- Local board - public planting day 10 August
- Play equipment and some new park furniture installed. Playground open
for public use.
- Spreading of topsoil and grass seeding adjacent to new playground area.
- Tender process completed and contract awarded for southern slope
landscaping maintenance contractor through to 2014.
|
- Tender process completed and letter of award issued for new civil works
contractor to finish all site tidy-up works.
- Planting maintenance programme to continue, which includes irrigation,
weeding and replacement planting (if required).
|
- Staged removal of stockpiled earth scheduled to resume 16 January with
site preparation expected week of 9 January.
- Removal of fencing around new grass adjacent to playground, subject to
its condition.
|
- Final site tidy-up, including removal of all remaining earth, minor
works on southern slope, addressing of ponded areas and reinstatement of
all footpaths on upper park, installation of remaining park furniture.
|
Following the completion of bulk earthworks in May 2011, the
southern slope has been landscaped with more than 10,000 native trees
and plants to create habitat for wildlife and provide a high-quality
environment for park users to enjoy.
The planting includes groves of large feature trees, including kauri and
tanekaha, tree ferns, and canopy trees such as rimu, totara, kahikatea,
kohekohe, puriri, tawa and taraire.
Improved walking paths have been built
through the reforested southern slope to link the lower access track with the main park area.
The council is continuing to take action to reduce potential impacts on
wildlife and to improve native forest areas nearby. This action includes animal
pest control, weed removal and enrichment planting at Ayr Street Reserve, and
the already completed transfer of native lizards from Newmarket Park to Ayr
Street Reserve.
Prior to major earthworks in early and mid 2010, in accordance with Environmental Management Best Practice guidelines, considerable effort was made by
restoration ecologists to relocate (transplant) native lizards from Newmarket Park's
southern slope to nearby Ayr Street Reserve. This project included the relocation of Copper Skink (Nationally Protected Species) and Ornate Skink (Nationally Protected Threatened species) populations.
Log refuge piles have since been created amongst the plantings on the Newmarket Park
southern slope to provide long-term habitat for these native skink species upon their return.
For further information, please contact us.
Project documents and plans
Landscape drawings and plant lists
(2231kb) PDF
Landscape Management Plan (3028kb) PDF
Historical failure types (95kb) PDF
Sections showing
previous slip scenarios on southern slope.
Remedial works site plan
and staging (900kb) PDF
Plan showing proposed works area.
Construction process (158kb) PDF
Typical sections of southern slope showing construction process to mitigate future
slope failure.
Consultation presentation document (2143kb)
PDF
Full details of the site, history of the park, project objectives and options, and
more.
Updated January 2012