Orakei Basin improvements
Orakei Basin improvements
Introduction
| Current works
| Current management approach
| History and ecology
Current works
Construction of a combined cycle/walkway parallel
to the existing railway lines, linking Purewa Road to Orakei Road is complete. This was opened for use in
early December 2010.
Work to construct stage two of the walkway, linking Purwera Road and Lucerne Road via Lucerne and Macpherson Reserves began in December
2010 and is due for completion in mid-May 2011.
Upgrades to the existing Macpherson track are scheduled to finish in late
June 2011. During May and early June acccess between Purewa Road and the new
section of walkway to Lucerne Road will be via the roadway to the end of
Meadowbank Road.
Complete revegetation and planting works for stage one and
some areas of stage two are due for completion in July 2011.
Completed:
Updated May 2011