Road closures
From City Scene, published on 6 July 2008
The eastbound lane of Swanson Street (between Albert Street
and Mills Lane), central city, between 7.30am and noon on Tuesday 8, Friday 11
and Tuesday, 15 July.
These closures are to enable work onsite at 26 Albert
Street (Stamford Plaza).
Barricades, detours and marshals will direct pedestrians
and traffic safely around the work zone. Residents and emergency vehicles will
still be given access.
For more information, phone Arthur Jones
of Fletcher Construction on 579 9979 or 027 457 2539.
Olsen Avenue (between
Littlejohn Street and Hayr Road), Mt Roskill, from 9am on Monday, 7 July to 6pm
on Sunday, 20 July. The road closure is part of the SH20 extension project. A
traffic management plan will be in place, including detours. Melrose Road
traffic will be directed through the site.
For more information, phone 0800 687 675.
Carlton Gore Road (between Boyle Crescent and Park Road ), Newmarket, from Monday, 7 July to Sunday, 20 July, between 7am and 7pm from
Monday to Friday, and between 7am and 5.30pm from Saturday to Sunday. (Rain
dates: Sunday, 20 July to Sunday, 3 August.)
These closures are for stormwater and sewer separation
work.
Motorists are advised to follow the signposted detours. For
more information, phone Nettie Bird of
Fulton Hogan Ltd. on 302 5327.