District Plan Hauraki Gulf Islands Section - Proposed 2006
(Notified version 2006)
Street index |
Planning maps |
Text |
Appendices |
Annexures |
Section 32 material |
Plan modifications |
Help |
Notified - Home |
Decision - Home
Hearing reports index
Report on submissions to the Auckland City District Plan: Hauraki Gulf Islands
Section - Proposed 2006
| Topic: |
Network Utility Services |
| Report to: |
The Hearing Panel |
| Author: |
Bruce Young |
| Date: |
8 May 2008 |
| Group file: |
314/274008
|
1.0 Introduction
This report considers submissions and further submissions ('submissions') that
were received by the council in relation to Network Utility Services of the Auckland
City District Plan: Hauraki Gulf Islands Section - Proposed 2006 ('the Plan'). The
Plan was publicly notified on 18 September 2006. The closing date for lodging submissions
was 11 December 2006. The submissions were publicly notified for further submission
on 29 April 2007. The closing date for lodging further submissions was 28 May 2007.
This report has been prepared under section 42A of the Resource Management Act
1991 ('the RMA'), to assist the hearings panel to consider the submissions on Network
Utility Services. This report discusses the submissions (grouped by subject matter
or individually) and includes recommendations from the planner who prepared this
report. The recommendations identify whether each submission should be accepted
or rejected (in full or in part) and what amendments (if any) should be made to
the Plan to address matters raised in submissions. Further submissions are dealt
with in conjunction with the submissions to which they relate.
The recommendations contained in this report are not decisions of the council.
The council will issue its decisions following consideration of the submissions,
further submissions, any supporting evidence presented at the hearing, and this
report. The council's decisions will be released after all the hearings to the Plan
have been completed.
2.0 Statutory framework
This section of the report briefly sets out the statutory framework within which
the council must consider the submissions. In preparing this report the submissions
and, in particular, the decisions requested in the submissions, have been considered
in light of the relevant statutory matters. These were summarised by the Environment
Court in Eldamos Investments Limited v Gisborne District Council W
047/05
where the court set out the following measures for evaluating objectives, policies,
rules and other methods in district plans:
- The objectives of the Plan are to be evaluated by the extent to which they:
- Are the most appropriate way to achieve the purpose of the RMA (s32(3)(a));
and
- Assist the council to carry out its functions in order to achieve the purpose
of the RMA (s72); and
- Are in accordance with the provisions of part 2 of the RMA (s74(1).
- The policies, rules, or other methods in the Plan are to be evaluated by the
extent to which they:
- Are the most appropriate way to achieve the objectives of the Plan (s32(3)(b));
and
- Assist the council to carry out its functions in order to achieve the purpose
of the RMA (s72); and
- Are in accordance with the provisions of part 2 of the RMA (s74(1)); and
- (If a rule) achieve the objectives and policies of the Plan (s76(1)(b)).
The purpose of the RMA is "to promote the sustainable management of natural and
physical resources", and "sustainable management" is defined in section 5(2) as
meaning:
"... managing the use, development, and protection of natural and physical resources
in a way, or at a rate, which enables people and communities to provide for their
social, economic, and cultural wellbeing and for their health and safety while—
(a) Sustaining the potential of natural and physical resources (excluding minerals)
to meet the reasonably foreseeable needs of future generations; and
(b) Safeguarding the life-supporting capacity of air, water, soil, and ecosystems;
and
(c) Avoiding, remedying, or mitigating any adverse effects of activities on the
environment."
Along with section 5, part 2 of the RMA includes sections 6 (matters of national
importance), 7 (other matters) and 8 (Treaty of Waitangi), which set out a range
of matters that the council needs to recognise and provide for in achieving the
purpose of the RMA. Those matters are also relevant when considering submissions.
The Plan must assist the council to carry out its functions under section 31
of the RMA. These functions are:
"(a) The establishment, implementation, and review of objectives, policies, and
methods to achieve integrated management of the effects of the use, development,
or protection of land and associated natural and physical resources of the district:
(b) the control of any actual or potential effects of the use, development, or
protection of land, including for the purpose of—
(i) the avoidance or mitigation of natural hazards; and
(ii) the prevention or mitigation of any adverse effects of the storage, use,
disposal, or transportation of hazardous substances; and
(iia) the prevention or mitigation of any adverse effects of the development,
subdivision, or use of contaminated land:
(iii) the maintenance of indigenous biological diversity:
(c) ...
(d) The control of the emission of noise and the mitigation of the effects of
noise:
(e) The control of any actual or potential effects of activities in relation
to the surface of water in rivers and lakes."
In addition to the matters listed above from the Eldamos decision:
- The Plan must "give effect to" any national policy statement and any New Zealand
coastal policy statement (s75(3)(a) and (b)).
- The Plan must be "give effect to" the regional policy statement (made operative
after 10 August 2005) (s75(3)(c)).
- The Plan must be "not inconsistent with" any regional plan (s75(4)).
- The council must ensure that that the Plan does not conflict with sections
7 and 8 of the Hauraki Gulf Marine Park Act 2000 ("the HGMPA"). Section
10 of the HGMPA requires that sections 7 and 8 of that Act be treated as a New
Zealand coastal policy statement under the RMA.
3.0 Background
This section of the report sets out background information about the topic under
consideration. It identifies how the Plan deals with Network Utility Services.
Part 5 is a new chapter for network utility services in recognition of their
unique nature and function. The current operative plan rely on the specific land
unit rules in which the utility services are to be located.
Network utility services include electricity, telecommunications, roading and
wastewater.
New definitions are added for telecommunication network, electricity network,
roading network and wastewater network.
Key changes from the operative plan include:
- Separate objectives and policies
- Activity table-lists and identifies the consent status of various types of
activities associated with network utilities
- Development controls for utility services located in land units and road
- Assessment criteria for discretionary activities and restricted discretionary
activities
- New concepts of underground, aboveground and overhead. Definitions are included
in the plan
- Reference to other documents e.g Hauraki Gulf Islands Development Code, Code
of Practice for working in the road
- Reference to the National Environment (NES) Standards for telecommunication
facilities in the road reserve. The NES is currently in the process of being drafted
into regulation.
4.0 Analysis of submissions
4.1 Introduction
This section of the report discusses the decisions requested in submissions about
part 5 and recommends how the panel could respond to the matters raised and decisions
requested in submissions. The submissions are addressed under subject headings.
While the relevant statutory matters (identified in section 2 of this report) will
not necessarily be referred to directly, the discussion and recommendations have
given appropriate consideration to these and any other relevant matters.
A list of the submissions which raise issues about part 5 together with the related
further submissions is contained in appendix 1. Appendix 2 contains
copies of the submissions and further submissions. Any amendments to the Plan recommended
in response to submissions are identified in this section of the report and are
further detailed in appendix 3.
The list of submissions contained in appendix 1 may include some submissions
and further submissions which were received 'late', ie they were received after
the closing date for lodging submissions (11 December 2006) or further submissions
(28 May 2007). All late submissions were considered by the hearing panel at the
start of the hearing process and the panel has already waived the failure to comply
with the time limit for any late submissions or further submissions listed in appendix
1. This has been done in accordance with sections 37 and 37A of the RMA.
4.2 Submissions about Part 5
Submissions dealt with in this section:
1076/1,
1084/2,
1139/5,
1166/19,
2293/1,
3061/41
4.2.1 Decisions requested
Submission
1076/1
requests:
Retain proposed reference/inclusion of telecommunication sites as network
utility services throughout the Plan.
Submission
1084/2 requests:
Amend the plan to provide for navigational aids, air traffic control facilities
and flight information services as permitted activities in appropriate land units
and settlement areas.
Submission
1139/5
requests:
The removal of part 5 Utilities and reintroduction of community mandated controls
in line with the strategic importance of Lot 1 DP67008 Wilma Road, Ostend.
Submission
1166/19
requests:
Facilitate the development of community and household scale infrastructure
esp. for water supply and electricity.
Submission
2293/1
requests:
Seeks amendment by modifying at the appropriate places esp rules, activity
table for the construction, operation and maintenance of roads (in part 5) to ensure
sound environmental outcomes. These outcomes will affect culvert pipes and public
open space. Most places where roadworks intersect with streams and wetlands there
is no effective fish bypass.
Submission
2294/2
requests:
Change the Activity table rule at clause 5.5.1 Construction ... of road network
to "Restricted Discretionary"
Submission
3061/41 requests:
Remove Part 5.0 Network utilities from the Plan along with consequential removal
of Part 10c.5.6 and 10c.5.6.1 and replacement with community mandated policies and
rules and such wider changes to the Plan consequent thereon.
4.2.2 Planner's analysis and recommendations
4.2.2.1 Submission
1076/1
Part 5 refers to various telecommunication services located underground, aboveground
and overhead and provides for their use in the activity table in clause 5.5.1. It
also refers to specific telecommunication equipment such as antennas, cell phone
masts etc. Part 14 also outlines the definition of 'telecommunication network' and
specifically lists various equipment. No changes are specifically sought to
the plan by the submission and accordingly it is recommended that submission
1076/1
be accepted.
4.2.2.2 Submission
1084/2
Section 166 of the RMA states:
Meaning of ..."network utility operator"...-In this Act-...means a person
who-
(g) Is an airport authority as defined by the Airport Authorities Act
1966 for the purposes of operating an airport as defined by that Act; or
(h) Is a provider of any approach control service within the meaning
of the Civil Aviation Act 1990;...
It is considered that providing for navigational aids, air traffic control facilities
and flight information services is appropriate for facilitating flight movements
to and from the gulf islands. The RMA provides for an airport authority to provide
for these facilities. What is unclear in the submission is the location of facilities
and in what appropriate land unit and settlement areas that they could be located.
Given the nature and function of navigational aids, air traffic control facilities
and flight information services, providing for these facilities as a permitted activity
in certain land units (with the exception of landforms 1,2,4 and 7 which would require
a non-complying activity consent application) and settlement areas is considered
appropriate. However it would be useful for the submitter to outline the scale of
the equipment and what land units in the islands could be appropriate for placing
the equipment. It is recommended that the submission be rejected subject to the
submitter outlining the nature and scale of navigation equipment and where these
could be placed in the gulf islands at the hearing.
4.2.2.3 Submissions
1139/5,
It is unclear in submission
1139/5
how to Part 5 relates to land at Lot 1 DP 67008.
Part 5 has been developed in recognition of the unique nature and function of
network utility services and how they enable the community to provide for their
social and economic well being. The chapter also ensures that the establishment
of network utility services do not detract from the visual amenity of the environment
or heritage values of the gulf islands. Where it is proposed to establish services
within sensitive landscapes, scheduled items and additional limitations, resource
consent would be required.
As stated in the S32 report, a separate chapter is justified for managing network
utility services. The pre notification consultation and formal submission and further
submission periods provided extensive opportunity for the community of the HGI to
be involved in plan development. The large number of submissions and further submissions
indicates good community involvement in the process. Therefore it is recommended
that submission
1139/5
be rejected.
In addition to the above, the submitter may wish to clarify the extent of the
relationship between Part 5 and Lot 1 DP 67008 at the hearing.
4.2.2.4 Submission
1166/19
Electricity reticulation is provided on Waiheke island by Vector Limited.
Power to Great Barrier (and other islands) is provided by generators. Water supply
is generally through rainwater collection (water tanks) or bore water. The
submission being considered in this section of the report is too general to be the
basis of any recommended changes to the Plan. In addition, the proposed provisions
in the land units in the plan enable the development of community and household
scale infrastructure e.g solar power panels, water tanks. In particular, the definition
of residential accessory building will enable the provision of solar panels, water
tanks and individual wind turbines. Therefore it is recommended that submission
1166/19
be rejected.
These submissions seeks the construction, operation and maintenance of roads
(in part 5) to ensure sound environmental outcomes.
Specifically, the submissions seek amendments to the activity table in clause
5.5.1 by classifying the construction and maintenance of roads as a restricted discretionary
activity and to add a new assessment criteria relating to the construction of fish
bypass.
This submission is not supported. The Auckland Regional Plan: Air, Land and Water
is the primary document for the management of beds, rivers, lakes, streams in the
Auckland region in terms of section 13 of the RMA:
13. Restriction on certain uses of beds of any lake or river,-
(1) No person may, in relation to the bed of any lake or river,-
(a) Use, erect, reconstruct, place, alter, extend, remove, or demolish
any structure or part of any structure in, on, under or over the bed; or
(b) Excavate, drill, tunnel, or otherwise disturb the bed; or
(c) Introduce or plant any plant or any part of plant (whether exotic
or indigenous) in, on , or under the bed; or
(d) Deposit any substance in, on or under the bed; or
(e) Reclaim or drain the bed-
Unless expressly allowed by a rule in the regional plan and in any relevant
proposed regional plan or a resource consent...
The Auckland Regional Plan: Air, Land and Water sets thresholds for permitted,
controlled, restricted discretionary, discretionary and non-complying activities.
One of the general conditions placed on all activities is listed in clause 7.5.2A(a)
of the plan:
The passage of fish and other aquatic organisms both up and down stream shall
be maintained, where it already occurs on existing structures, and provision shall
be made for the passage of fish and other aquatic organisms on new or reconstructed
structures;
In determining the standard relating to fish passage, the regional plan refers
to the ARC Technical Publication 131: Fish Passage-Review and Guidelines for the
Auckland Region.
It is considered that the above statutory document and associated guidelines
are the appropriate mechanisms when assessing the construction, operation and maintainance
of roads. In addition, it is considered that given the context of roads where they
have been:
- Located on land which has been vested or dedicated as road; and
- The road is identified as formed on the planning maps
The effects of constructing, operation and maintaining the existing road network
are considered minor and that this activity be retained as a permitted activity
in clause 5.5.1.
For the above reasons, it is recommended that submission
2293/1and
2294/2
be rejected.
4.2.2.6 Submission
3061/41
Submission
3061/41 seek the removal of Part 5, removal of Part 10c.5.6 and 10c.5.6.1 and
re-introduction of community mandated policies and rules and wider changes to the
plan and consequential changes.
Part 5 has been developed in recognition of the unique nature and function of
network utility services and how they enable the community to provide for their
social and economic well being. The chapter also ensures that the establishment
of network utility services do not detract from the visual amenity of the environment
or heritage values of the gulf islands. Where it is proposed to establish services
within sensitive landscapes, scheduled items and additional limitations, resource
consent would be required.
As stated in the S32 report, a separate chapter is justified for managing network
utility services. The pre notification consultation and formal submission and further
submission periods provided extensive opportunity for the community of the HGI to
be involved in plan development. The large number of submissions and further submissions
indicates good community involvement in the process.
The removal of clause 10c.5.6 and 10c.5.6.1 is not supported. These sections
of the plan relate to earthworks. Specifically, clauses 10c.5.6.1(3) and 10c.5.6.1(7)
relates to trenching for utility services and the use, maintenance and upgrading
of existing formed public roads respectively.
There will be instances where earthworks for utility services are essential,
for example, undergrounding cables and maintaining roads. Conditions have been developed
to ensure that there are minimal effects and to minimise potential for erosion and
sedimentation that can have adverse effects on water bodies, wetlands and coastal
systems. Clause 10c.5.6.2 of the plan sets out the permitted activity standards
for earthworks. Good practice and guidelines are also referred to in appendix 16-Erosion
and sediment control guidelines for earthworks of the plan. It is considered
that these requirements in the plan are sufficient to ensure good environmental
outcomes.
Therefore it is recommended that submission
3061/41 be rejected.
| Planner's recommendations about submissions
1076/1,
1084/2,
1139/5,
1166/19,
2293/1
&
3061/41
That submissions
1076/1,
1084/2 ,
1139/5,
1166/19,
2293/1,
2294/2,
3061/41 be rejected.
That submission
1076/1 be accepted with no changes to the text.
|
4.3 Submissions about clause 5.1
Submissions dealt with in this section:
519/4,
941/6,
1250/10,
1250/11,
1250/12,
1250/13
4.3.1 Decisions requested
Submission
519/4
requests:
Amend clause 5.1 paragraph 3, third sentence, to read (additions are shown
underlined) "It is also recognised that some utility operators have specific
legislative rights under legislation that expressly provides for utility services."
Submission
941/6 requests:
That the wording below be adopted by the council in the (clause 5.1):
- "Network utility services provide an important part of the overall
physical resources for the islands. They are also a means of providing for the
economic and social wellbeing for the island communities.
- It is also recognised that utility operators have specific legislative
rights under legislation that expressly provides for utility services.
- The council recognises the importance of utility services:
Submission
1250/10
requests:
Remove general reference to wastewater from clause 5.1.
Submission
1250/11
requests:
Include a new section in clause 5.1 for the ongoing maintenance only, of the
Owhanake Wastewater Treatment Plant.
Submission
1250/12
requests:
State in clause 5.1 that wastewater on Waiheke will continue to be treated
and disposed of through on site systems.
Submission
1250/13
requests:
State in clause 5.1 that grey water recycling systems will be required for
all new development.
4.3.2 Planner's analysis and recommendations
4.3.2.1 Submission
519/4
It is accepted that some utility operators have specific legislation to enable
provision of utility services particularly within the road reserve. This legislation
includes Electricity Act, Telecommunications Act and Local Government Act. Recently
the government has confirmed that new standards will apply to telecommunication
facilities within the road reserve (i.e National Environmental standards).
Therefore it is recommended that submission
519/4
be accepted.
4.3.2.2 Submission
941/6
The submission supports the following wording in clause 5.1 of the plan:
- "Network utility services provide an important part of the overall physical
resources for the islands. They are also a means of providing for the economic
and social wellbeing for the island communities.
- It is also recognised that utility operators have specific legislative
rights under legislation that expressly provides for utility services.
- The council recognises the importance of utility services:
It is recommended that submission
941/6 be accepted.
4.3.2.3 Submission
1250/10
The reference to wastewater in clause 5.1 is in recognition of existing infrastructure
(Owhanake wastewater treatment plant-clause 4.8 of the plan) on the islands and
in particular Waiheke island. It is appropriate to recognise this type of infrastructure
given its existence. Therefore it is recommended that submission
1250/10
be rejected.
4.3.2.4 Submission
1250/11
The reference to Owhanake Wastewater Treatment Plant and its ongoing maintenance
is addressed in the Notice of requirement (Designation 1-14) and can be more appropriately
managed through conditions on the designation. In addition clause 4.8 of the plan
also recognises the treatment plant be provided for by way of designation. It is
not appropriate to address this in the introduction to Part 5. Therefore it is recommended
that submission
1250/11
be rejected.
The introduction to Part 5 only refers to wastewater in a general sense and not
specifically with policy matters pertaining to on-site systems or requiring grey
water recycling systems for all new developments. Furthermore, such systems may
not be suitable for some sites and/or circumstances. In this regard, it would be
more appropriate to address such matters on a case by case basis and through clause
4.8-Wastewater on policy matters. Therefore it is recommended that submissions
1250/12
and 1250/13
be rejected.
| Planner's recommendations about submissions
519/4,
941/6,
1250/10,
1250/11,
1250/12
and
1250/13
That submissions
519/4,
1250/10,
1250/11,
1250/12
and
1250/13 be rejected.
That submission
519/4
be accepted and that clause 5.1, paragraph 3, third sentence be amended to read
(additions are shown underlined):
It is also recognised that some utility operators have specific
legislative rights under legislation that expressly provides for utility services.
That submission
941/6 be accepted with no changes to the text.
|
4.4 Submissions about clause 5.2
4.4.1 Decisions requested
Submission
941/7 requests that issues in clause 5.2 (1)-(3) be adopted.
Submission
941/8 requests:
The issues clause 5.2 be amended by including further issues as follows, or
words of similar effect:
"The most appropriate resource management techniques to provide for the wide
range of public works and network utilities in the District Plan.
How to provide for the efficient development, operation and maintenance of
public works and network utilities.
How to co-ordinate the provision of public works and network utilities with
the demands for new or intensified development".
4.4.2 Planner's analysis and recommendations
4.4.2.1 Submission
941/7
Submission
941/7 is accepted.
4.4.2.2 Submission
941/8
It is considered that the issues outlined in clause 5.2 encapsulate the issues
with respect to providing and managing the effects of network utility services.
The first issue raised in the submission is not considered an issue with respect
to providing for network utilities. It is a decision making process on which is
the best method within the RMA techniques for managing utility services within the
district. Furthermore, as an issue, a desired outcome should be stipulated and it
is difficult to envisage monitoring the "appropriate resource management technique."
The second issue raised by the submission is provided for within clause 5.2(1)
and is encapsulated within objective 5.3.1 of the plan. In addition, this is further
reinforced by the policies aligned with the objective.
The third issue as outlined in the submission can be covered through a range
of other techniques and processes outside of the RMA which can effectively address
these matters such as memorandum of understanding agreements, documents such as
code of practice for working in the road and co-operation between council and utility
operators.
Overall, it is considered that the issues in 5.2 are appropriate. Therefore,
it is recommended that submission
941/8 be rejected.
| Planner's recommendations about submissions
941/7 and
941/8
That submission
941/8 be rejected.
That submission
941/7 be accepted with no changes to the text.
|
4.5 Submissions about clause 5.3.1
4.5.1 Decisions requested
Submission
941/9 requests:
Objective 5.3.1 (or words to similar effect) be adopted.
Submission
941/12 requests:
Policies 5.3.1 (1)-(8) (or words to similar effect) be adopted.
Submission
941/13 requests:
Policy 5.3.1(5) be amended as follows (or words to similar effect):
"5. By encouraging the co-ordination and co-location of works between network
utility operators to minimise environmental impacts and community disruption
, where practicable ."
Submission
941/14 requests:
The explanation for clause 5.3.1 be adopted.
Submission
1116/1 requests:
Amend clause 5.3.1(6) as follows (additions underlined and deletions in strikethrough):
"By requiring encouraging network utility operators to
comply be
consistent with the Code of Practice for Working in the Road."
Submission
2929/1
requests:
Seeks that policy 5.3.1 (8) be amended to prohibit further overhead lines
being put in place in new subdivisions.
4.5.2 Planner's analysis and recommendations
Submissions
941/9,
941/12 and
941/14 are accepted.
4.5.2.2 Submission
941/13
Submission
941/13 amends policy 5.3.1(5) by adding the words "where practicable"
at the end of the policy sentence. This amendment is not supported. Firstly, the
words add ambiguity to the policy and do not add any value to the general direction
the policy is trying to achieve. Furthermore, the policy recognises the difficulty
of the RMA in trying to achieve the direction sought (i.e co-ordination and co-location
of works), hence the word "encouraging" is used in the policy.
Other methods outside of the RMA are better in achieving the objective.
For the above reasons, the submission is rejected.
4.5.2.3 Submission
1116/1
Submission
1116/1 seeks the following amendment:
"By requiring encouraging network utility operators to
comply be
consistent with the Code of Practice for Working in the Road."
This amendment is not supported. The Code of Practice was developed to
provide consistency in the application of standards for working in the road throughout
the Auckland region, whether that work is being carried out by councils, utilities
or others.
Part 1.2.1 of the Code states "All work shall comply with the requirements of
this code ........." and "The RCA and Principal Providers have the prime responsibility
for ensuring code compliance at all times".
Further, the road opening notice declaration by the Principal Provider or the
Principal Providers agent is an agreement "to comply in full with the requirements
of the Code ......".
The submitter (Vodafone NZ Ltd) are a signatory to the Code by virtue of their
membership in the Auckland Utilities Operators Group (AUOG) and also the Partnership
Agreement was signed on their behalf on 7 December 2006.
Any dispute would generally follow what is provided for in various utility acts-discussion/mediation/District
Court/Environment Court.
For the above reasons, it is considered that submission
1116/1 is rejected.
4.5.2.4 Submission
2929/1
Policy 5.3.1(8) states:
"By providing for overhead lines in the appropriate landform land units."
The submission seeks to prohibit further overhead lines being put in place in
new subdivisions. The Hauraki Gulf islands Development Code requires undergrounding
of new lines (electricity and telecommunication) where new subdivision occurs. The
HGI development code is referenced in clause 5.3.1(7) of the plan. In particular
clause 8.4.3.3 of the code as a means of compliance states, "...all services
shall be underground except for approved surface chambers or above ground plant
which shall be of minimum possible size."
In addition, Objective 12.3.8 for subdivision states:
To design subdivisions so that network utility services are installed in a
manner that minimises any adverse effects on the environment, including visual amenity,
noise, earthworks, dust, spill lighting, electro magnetic field emissions and radio
frequency fields (RF).
Policies
1. By requiring at the time of subdivision that electricity and telecommunication
services are placed underground.
2. By preventing the installation of utility services which may be sought
in conjunction with subdivision where the effect on landscape and amenity values
cannot be adequately remedied or mitigated.
Therefore, the matter of undergrounding services at the time of subdivision is
also addressed in Part 12 of the plan.
In general, the council will require undergrounding of lines in new subdivisions.
However there are situations where undergrounding may not be appropriate such
as where heritage, geological or archaeological features would be compromised by
undergrounding. This is addressed in the above policy 2. This would be considered
on a case by case basis.
Policy 5.3.1(8) also caters for situations in rural areas (landforms 3 and 5)
and formed legal road adjoining rural areas (landform 1-7) where providing for underground
lines is expensive due to distance from existing services, where topographical constraints
may exist and the nature of existing development or landscape considerations are
evident.
Any new overhead lines outside of the above matters will require resource consent
application so that environmental effects of new overhead lines can be assessed.
Policy 5.3.1(8) is appropriately worded to take into account the above circumstances
and is recommended that the wording not be changed.
For the above reasons, it is considered that submission
2929/1
is rejected.
4.6 Submissions about clause 5.3.2
4.6.1 Decisions requested
Submission
663/2 requests:
Ban all "up" lighting and remove all "up" lighting in order to eliminate all
light scatter to the night sky.
Submission
941/10 requests:
Amend Objective 5.3.2 as follows (or words to similar effect):
"To ensure ... are appropriately avoided, remedied or mitigated
where practicable ."
Submission
941/15 requests:
Policy 5.3.2 (1) be amended to read (or words to similar effect):
"By ensuring that utility services meet appropriate environmental standards
so that adverse effects are avoided, remedied or mitigated, where practicable."
Submission
941/16 requests:
Policy 5.3.2(2) (or words to similar effect) be adopted.
Submission
1117/1 requests:
Amend clause 5.3.2(1) as follows (additions underlined and deletions in strikethrough):
"By ensuring That utility services meet appropriate environmental standards
so that in order to reduce any significant adverse effects do not occur."
Submission
1117/2 requests:
Amend the explanation to clause 5.3.2 as follows (additions underlined and
deletions in strikethrough):
"The standards have been established to ensure that there is minimal adverse
effect on the environment and provide guidance for The standard must
be met during the establishment, operation and maintenance of utility services.
Should the standards not be met, resource consent will be required to exceed the
standards."
4.6.2 Planner's analysis and recommendations
4.6.2.1 Submission
663/2
Submission
663/2 seeks
to ban all "up" lighting and remove all "up" lighting in order to eliminate all
light scatter to the night sky.
Clause 5.3.2 of the plan addresses the objective of ensuring adverse effects
associated with utilities are avoided, remedied or mitigated and includes spill
lighting. Spill lighting is controlled by the council's bylaws. Standards are adopted
by the bylaw which limits the amount of illumination of lighting which can have
adverse effects on properties.
In general the submitter requests that all lighting be downward lighting so that
any impacts on the nights sky are minimised. It is acknowledged that greater emphasis
can be placed on reducing the adverse effects from lighting on the night sky through
appropriate policy and assessment criteria. This is addressed in Part 4 of the plan
whereby it has been recommended that:
"By adding a new policy numbered 4.10.1.5 after policy 4.10.1.4:
By avoiding, remedying or mitigating the adverse effects of lighting on the
night sky."
It is considered that the amendment to Part 4 is the appropriate place for mitigating
spill lighting.
For the above reasons, it is considered that submission
663/2 be
accepted in part and a new policy is added in Part 4 of the plan.
4.6.2.2 Submission
941/10
Submission
941/10 seeks the words "appropriately" and "where practicable" be added in the
objective. This amendment is not supported. Section 5(2)(c)of the RMA states
"...their health and safety while-... avoiding, remedying or mitigating any adverse
effects of activities on the environment." The section of the RMA does not qualify
this with the words "appropriately" and "where practicable."
The submission is concerned that there should be an appropriate balance between
providing for utilities and ensuring any adverse effects on development and the
community are appropriately avoided, remedied or mitigated.
By adding the words "appropriately" and "where practicable" creates
ambiguity and does not add any value to the objective as objectives need to be measureable.
Such words will often add confusion and uncertainty when assessing proposals and
consent applications (i.e what is considered appropriate and where practicable?).
It is also good planning practice to keep objectives simple, clear and concise.
Adding the words does not achieve this.
In addition, while objective 5.3.1 of the plan does provide for the provision
of utility services, objective 5.3.2 is to ensure that any adverse effects generated
by network utility services are avoided, remedied and mitigated.
For the above reasons, it is considered that submission
941/10 be rejected.
Both submissions seek rewording to clause 5.3.2(1) of the plan.
Submission
941/15 seeks that the words "...are avoided, remedied or mitigated where
practicable" are substituted in place of "... do not occur." It is considered
that the words "...are avoided, remedied or mitigated" is supported as it
is consistent with the wording in section 5(2)(c) of the RMA. However, the words
"where practicable" is not supported for the reasons as set out in the analysis
of submission
941/10.
Submission
1117/1 seeks similar wording but that the policy be amended to read:
That utility services meet appropriate environmental standards in order to
reduce any significant adverse effects
This amendment is not supported as the standards developed are appropriate to
ensure that the any adverse environmental effects are avoided, remedied or mitigated
as per the RMA. The submission only seeks to "reduce any significant adverse effects"
which is not consistent with the wording of section 5(2)(c) of the RMA.
For the reasons above, it is considered that submission
941/15 be accepted in part and submission
1117/1 be rejected and that clause 5.3.2(1) be amended to read:
By ensuring that utility services meet appropriate environmental standards
so that adverse effects are avoided, remedied or mitigated.
4.6.2.4 Submission
941/16
Submission
941/16 is accepted.
4.6.2.5 Submission
1117/2
Submission
1117/2 seeks that the explanation be amended to explain the policy. The submission
is supported in part with the following wording as the amendment explains and clarifies
the policy better than it currently reads:
The standards have been established to ensure that adverse effects on the
environment are avoided, remedied or mitigated during the establishment, operation
and maintenance of utility services. Should the standards not be met, resource consent
will be required to exceed the standards.
Submission
1117/2 is accepted in part.
| Planner's recommendations about submissions
663/2,
941/10,
941/15,
941/16,
1117/1 and
1117/2
That submissions
663/2,
941/10,
1117/1 be rejected.
That submissions
941/16 be accepted with no changes to the text.
That submission
941/15 and be accepted in part and that clause 5.3.2(1) be amended to read:
By ensuring that utility services meet appropriate environmental standards
so that adverse effects do not occur are avoided, remedied or mitigated.
That submission
1117/2 be accepted in part and that the explanation to clause 5.3.2 be amended
to read:
The standards have been established to ensure that there is minimal adverse
effect on the environment adverse effects on the environment are avoided,
remedied or mitigated during The standards must be met during
the establishment,
operation and maintenance of utility services. Should the standards not be met,
resource consent will be required to exceed the standards.
|
4.7 Submissions about clause 5.3.3
4.7.1 Decisions requested
Submission
941/11 requests:
Amend Objective 5.3.3 as follows (or words to similar effect):
"To ensure that the establishment of network utility services do not unnecessarily
detract from the visual amenity of the environment or any heritage values
, where practicable ."
Submission
941/17 requests:
Policy 5.3.3(1) be amended to read (or words to similar effect):
"By encouraging underground services for new subdivision and development,
where practicable".
Submission
941/18 requests:
Policy 5.3.3(3) be amended to read (or words to similar effect):
"By encouraging utility operators to underground existing overhead utilities
where the opportunity exists for co-ordinated works with council road works, and
considering any relevant constraints."
Submission
941/19 requests:
Policy 5.3.3(6) be amended to read (or words to similar effect):
"By controlling large scale above ground and overhead utility services on
significant ridgelines and in land units with high landscape value to ensure that
they do not detract from the visual amenity of the surrounding environment, where
practicable."
Submission
941/20 requests:
Policy 5.3.3(7) be amended as follows (or words to similar effect):
"By assessing the cumulative visual impact of multiple antennae on the environment."
Submission
941/21 requests:
Policy 5.3.3(8) be amended as follows (or words to similar effect):
"By encouraging utility operators to design utility services that are visually
sympathetic to the environment, where practicable".
Submission
941/22 requests:
Policy 5.3.3(9) be amended as follows (or words to similar effect):
"By requiring the removal of redundant or obsolete services, particularly
within the road, where appropriate and practicable".
Submission
941/23 requests:
Policy 5.3.3(10) be amended as follows (or words to similar effect):
"By encouraging utility operators to provide a long term plan for undergrounding
existing overhead utilities in the future, where appropriate and practical".
Submission
941/24 requests:
The 2nd, 7th and 10th paragraphs of the explanation for clause 5.3.3 be amended
to read (or words to similar effect):
"Where new subdivision or development occurs undergrounding of services is
encouraged.
The council will also require the removal of redundant or obsolete services
in the road, where appropriate and practicable.
Generally, there needs to be a balance between providing utility services
and ensuring that they do not detract from the environment in which they are located,
where practicable. The above policies recognise the unique nature of utility services
while ensuring that they can be established, operated and maintained so that minor
adverse effects on the environment can be avoided, remedied or mitigated".
Submission
1111/1 requests:
Amend the eighth paragraph of the explanation of clause 5.3.3 as follows (additions
underlined, and deletions in strikethrough) :
"The cumulative effect of aboveground and utility services in any one location
can have an adverse effect on an area. There is a need. The provisions of the
District Plan seeks to avoid a minimise the proliferation of separate
structures and this requires a co-operative approach where feasible and practicable
so that visual impacts effects are avoided or minimised appropriately
managed . This is particularly relevant in the fast changing communications
industry where sites for cellular phone towers, antennas and wireless internet services
can be difficult to find."
Submission
1243/41 requests:
Amend clause 5.3.3(1) to reflect that not all types of development require
the undergrounding of services.
Submission
2928/1
requests:
Delete policy 5.3.3 (10) and add a policy that mandates long term plans for
undergrounding, and requires further reticulation to be under grounded.
4.7.2 Planner's analysis and recommendations
4.7.2.1 Submission
941/11
The submission is concerned that there should be an appropriate balance between
providing for utilities and ensuring any adverse effects on development and the
community are appropriately avoided, remedied or mitigated.
Furthermore, adding the words "unnecessarily" and "where practicable"
creates ambiguity and does not add any value to the objective as objectives
need to be measureable. Such words will often add confusion and uncertainty when
assessing proposals and consent applications (i.e what is considered appropriate
and where practicable?). It is also good planning practice to keep objectives simple,
clear and concise. Adding the words do not achieve this.
For the above reasons, it is considered that submission
941/11 be rejected.
Submission
941/17 seeks the addition of the words "encouraging" for "requiring"
and the addition of the words "where practicable." The submission considers
that the proposed policies are unduly onerous for utility operators and do not accurately
reflect the explanation which follows these policies under clause 5.3.3.
In response to the relief sought, it is considered appropriate to separate the
relief into the following headings
1. "Where practicable"
In addressing submission
941/17, it is considered that the words "where practicable" creates ambiguity
and does not add any value to the policy. Policies need to be written in such a
way to give direction and strength to methods and those making decisions on consents.
Such words will often add confusion and uncertainty when assessing proposals and
consent applications (i.e what is considered "where practicable"?). It is also good
planning practice to keep objectives simple, clear and concise. Adding the words
does not achieve this.
2. "encouraging" for "requiring"
The use of the word "encouraging" in substitution for "requiring" is not supported.
In general, the council will require undergrounding of all services. The use of
the word "encouraging" does not enable the council to achieve the outcome of underground
services. There are some exceptions where providing for overhead services
are allowed as explained below.
It is considered that the need for utility services often relates to development
and/or subdivision. It is considered that development and subdivision could be mutually
exclusive or inclusive and that separating both situations into separate policies
is appropriate when addressing the effects on landscape and amenity values. The
policy should be written in a way that gives direction to remedy and mitigate landscape
and visual amenity effects which can potentially occur through the implementation
of utility services.
Part 12-subdivision provides for utility services through objectives and policies,
rules and assessment criteria at the time of subdivision. While policy 1 of objective
12.3.8 requires utility services to be placed underground, policy 2 of objective
12.3.8 recognises that adverse effects can occur through the undergrounding of such
services: This is outlined as follows:
Objective 12.3.8
To design subdivisions so that network utility services are installed in a
manner that minimises any adverse effects on the environment, including visual amenity,
noise, earthworks, dust, spill lighting, electro magnetic field emissions and radio
frequency fields (RF).
Policies
- 1. By requiring at the time of subdivision that electricity and telecommunication
services are placed underground.
- 2. By preventing the installation of utility services which may be sought
in conjunction with subdivision where the effect on landscape and amenity values
cannot be adequately remedied or mitigated.
It is considered logical that addressing the provision of utilities at subdivision
and its effects on the environment is adequately provided for in part 12 of the
plan and should be referred to as a policy.
The Plan recognises the relationship between subdivision and the effect on landscape
character from associated land use activities. Accordingly, electricity and telecommunication
services are invariably required to service any activity on a site. Such services
can take the form of tall power/telecommunication poles with overhead cabling, which
can adversely affect the landscape character and amenity value of an area. Conversely,
undergrounding of utility services can adversely affect significant environmental
features such as indigenous bush or heritage features (e.g middens). Applicants
will therefore need to consider the provision of utility services as part of any
subdivision.
The polices and assessment criteria in clause 12.11.11 (Network utility services)
consider the design of subdivision within all land units and settlement areas and
how each can be serviced by network utilities without adversely affecting the natural
landscape and amenity qualities of the environment. Matters to consider include
shared services (easements) and the extent to which services can be placed underground.
In addition the HGI Development Code requires that all services be placed underground.
Policy 2 of objective 12.3.8 addresses the situation where undergrounding may
not be the most appropriate method of providing utility services especially where
it affects landscape and amenity values.
For the above reasons it is considered that submission
941/17 be rejected.
3. Submission
1243/41
Similarly, in addressing submission
1243/41, new development may not require undergrounding of services in all cases.
Council will generally require the undergrounding of services for new development
where the effects on landscape values can be adequately remedied or mitigated. If
however there are situations where undergrounding may cause adverse effects (e.g
sites of ecological significance, heritage values) then overhead and aboveground
provision of utilities may be appropriate.
For the above reasons, it is considered that submission
1243/41 be accepted in part.
Therefore, policy 5.3.3(1) should be reworded as follows:
1. By requiring underground services for new subdivision and development where
the adverse effects on landscape or heritage values can be adequately avoided, remedied
or mitigated.
4.7.2.3 Submission
941/18
Submission
941/18 seeks addition of the words "and considering any relevant constraints"
to the end of the policy. This is not supported. The policy in its context encourages
the utility operators and the council to co-ordinate works within the road reserve
and wherever possible underground existing overhead utilities.
The principles of coordination of works is covered in Part 2 of the Code of Practice
for Working in the Road, Auckland Region. The purpose is to reduce disruption to
all users and occupants, particularly with consideration to (a) traffic sensitive
roads and (b) retail and business areas.
There is an obligation for all Road Controlling Authorities (RCA's) and Service
Providers to notify each other of their individual forward strategic programmes
(at least 1 to 2 years in advance). This is particularly relevant in circumstances
where the RCA is carrying out major road or footpath resurfacing and reconstruction
as it provides the Service Providers the opportunity to underground existing overhead
services and/or upgrade, install or maintain existing underground services with
greatly reduced reinstatement costs.
Provided that the RCA has advised the Service Providers of its intentions to
carry out such upgrades, the Code provides for an exclusion period of 5 years from
the date of completion. The Code also recognises the need for flexibility of timing
by all parties.
Therefore, it is considered that adding words to the policy does not add value
to the policy. The words "encourage" recognises that council cannot compel utility
operators to underground existing overhead services. The detail issues as to what
constraints and considerations are taken into account when works are undertaken
in the road reserve are worked through at the time of implementation and this is
worked out in detail through the Code of Practice for Working in the Road. Generally
both parties come to a mutual agreement as timing, costs and any other factors that
may have an impact on the project work.
For the above reasons, it is considered that submission
941/18 be rejected.
4.7.2.4 Submission
941/19
Submission
941/19 seeks the addition of the wording "where practicable" to the end of the
policy. This submission is not supported. Firstly, as explained elsewhere in this
report, the words "where practicable" creates ambiguity and does not add any value
to the policy as policies need to be written in such a way to give direction and
strength to methods and those making decisions on consents. Such words will often
add confusion and uncertainty when assessing proposals and consent applications
(i.e what is considered "where practicable"?). It is also good planning practice
to keep objectives simple, clear and concise. Adding the words does not achieve
this.
In addition, the council will control large scale above ground and overhead utilities
in areas of high landscape value to ensure that do not detract from the visual amenity
of the surrounding environment. Adding the words "where practicable" in the policy
is not seen as necessary as both the activity table and development controls of
the plan have a range of rules which manages this. Furthermore, where utility operators
wish to apply for resource consent, then the merits of each case can treated on
a case by case basis and the practicalities can be assessed at that time.
For the above reasons, it is considered that submission
941/19 be rejected.
4.7.2.5 Submission
941/20
Submission
941/20 seeks the amendment of policy 5.3.3(7) by the following:
By assessing the cumulative impact of overhead utilities multiple antennae
on the environment
This submission is supported in part. Clause 5.8.1(m) of the plan states the
following:
Whether any cumulative adverse visual effects arising from a number of utility
services being located in a particular area or of the same (or similar) services
being repeated in areas of significant amenity can be avoided, remedied or mitigated.
This is particularly relevant for overhead electricity and telecommunication lines
and masts and antennas.
It is considered that the assessment of cumulative effect is not just limited
to overhead lines as stated in clause 5.8.1(m). The clause clearly states that both
electricity and telecommunication overhead lines, masts and antennas are also of
a concern that warrants assessment. The submission seeks the substitution of multiple
antennae in lieu of overhead utilities. This is not supported. However, it is considered
that both types of utilities should be considered as part of the policy. Therefore
it is recommended that policy 5.3.3(7) be amended to read:
By assessing the cumulative impact of overhead utilities and antennas
on the environment
For the above reasons, it is considered that submission
941/20 be accepted in part.
4.7.2.6 Submission
941/21
Submission
941/21 seeks the addition of the wording "where practicable" to the end of policy
5.3.3(8). This submission is not supported. Firstly, as explained elsewhere in this
report, the words "where practicable" creates ambiguity and does not add any value
to the policy as policies need to be written in such a way to give direction and
strength to methods and those making decisions on consents. Such words will often
add confusion and uncertainty when assessing proposals and consent applications
(i.e what is considered "where practicable"?). It is also good planning practice
to keep objectives simple, clear and concise. Adding the words does not achieve
this.
Adding the words "where practicable" in the policy is not seen as necessary as
both the activity table and development controls of the plan have a range of rules
which manages this. Furthermore, where utility operators wish to apply for resource
consent, then the merits of each case can treated on a case by case basis and the
practicalities can be assessed at that time.
In addition, the council wishes to encourage utility operators to design utility
services that are visually sympathetic to the environment. This is addressed through
clause 5.8.1(a-d) of the plan. The council also acknowledges that in recent years,
utility companies (telecommunications in particular) have endeavoured to design
equipment that is visually sympathetic with the environment. It is also recognised
that some utility services such as overhead lines cannot be visually sympathetically
designed, but can be located in such a way that mitigates their visual impact or
by undergrounding.
For the above reasons, it is considered that submission
941/21 be rejected.
4.7.2.7 Submission
941/22
Submission
941/22 seeks the addition of the wording "where appropriate and practicable"
to the end of policy 5.3.3(9). This submission is supported in part. As explained
elsewhere in this report, the words "where appropriate and practicable" creates
ambiguity and does not add any value to the policy as policies need to be written
in such a way to give direction and strength to methods and those making decisions
on consents. Such words will often add confusion and uncertainty when assessing
proposals and consent applications (i.e what is considered "where appropriate and
practicable"?). It is also good planning practice to keep objectives simple, clear
and concise. Adding the words does not achieve this.
However, the Code of practice for working in the road is not specific on the
matter of requiring utility operators to remove redundant or obsolete services.
This issue has been the subject of discussion when the code was developed and it
was generally agreed that where an area has been opened and services are identified
as obsolete then they should be removed at that time. In addition, some redundant
services may be able to be reused by other service providers (Code part 5.3.2).
To this extent, submission
941/22 is accepted in part by amending policy 5.3.3(9) to read:
(strikethroughs indicate deletions and underline indicate additions)
By requiring encouraging the removal of redundant obsolete services
or and reuse of obsolete redundant services, particularly in the road.
Submission
941/23 seeks the addition of the wording "where appropriate and practical" to
the end of policy 5.3.3(10). This submission is not supported. Firstly, as explained
elsewhere in this report, the words "where appropriate and practical" creates ambiguity
and does not add any value to the policy as policies need to be written in such
a way to give direction and strength to methods and those making decisions on consents.
Such words will often add confusion and uncertainty when assessing proposals and
consent applications (i.e what is considered "where appropriate and practical"?).
It is also good planning practice to keep objectives simple, clear and concise.
Adding the words does not achieve this.
Furthermore as part the process of undergrounding existing overhead lines, the
submitter's priority for undergrounding existing overhead lines is given to areas
where revitalisation is required (i.e where overhead lines that are reaching the
end of their useful life). The council does not compulsorily require existing overhead
lines to be undergrounded, rather it "encourages" the relevant utility company to
take any opportunity to do so when upgrades of footpaths/roads are undertaken. This
is a collaborative process between the utility operators and the council.
For the above reasons, it is considered that submission
941/23 be rejected.
Submission
2928/1
seeks to delete policy 5.3.3(10) and add a policy that mandates long term plans
for undergrounding, and requires further reticulation to be undergrounded. This
submission is not supported.
As stated above, the council cannot compulsorily require undergrounding of existing
overhead lines. Hence the word used in this policy is "encouraging" rather
than "require". A policy that mandates long term plans for undergrounding is therefore
not supported, rather long term undergrounding should be seen as collaborative process
between the council and relevant utility operator.
Further provision of underground services is addressed as means of compliance
by the HGI Development code that all services be underground at the time of subdivision
and development. Furthermore, the subdivision section of the plan also requires
that to minimise visual effects, telecommunication and electricity services be placed
underground at the time of subdivision. Only in exceptional circumstances (or where
allowed in the district plan) should such services be placed overhead and this should
be assessed as part of the subdivision consent application.
For the above reasons, it is considered that submission
2928/1
be rejected.
1. Submission
941/24
Submission
941/24 seeks amendments to the 2nd, 7th and 10th paragraphs of the explanation
for clause 5.3.3:
2nd paragraph-"Where new subdivision or development occurs undergrounding
of services is required encouraged ."
7th paragraph-"The council will also require the removal of redundant or obsolete
services in the road, where appropriate and practicable ."
10th paragraph- "Generally, there needs to be a balance between providing
utility services and ensuring that they do not detract from the environment in which
they are located, where practicable . The above policies recognise the unique
nature of utility services while ensuring that they can be established, operated
and maintained in a manner that has minor adverse effects on the environment
so that minor adverse effects on the environment can be avoided, remedied or mitigated".
Amendments to the 2nd paragraph of the explanation seek the deletion of the word
"required" and its replacement with the word "encouraged". This amendment is not
supported. As discussed in the analysis of submissions
941/17 and
1243/41, objectives and policies within parts 5 and 12 of the plan emphasise
the general requirement by council to provide services underground. However, it
is recognised by the council that there will be circumstances where undergrounding
is not the appropriate method in providing utility services and where it may cause
adverse effects (e.g sites of ecological significance, heritage values).
Amendments to the first sentence of the 7th paragraph of the explanation seek
the addition of the words "where appropriate and practicable". This is not
supported. In keeping with submission
941/22, the council does not compulsorily require utility operators to remove
redundant services or obsolete services. As part of the code of practice of working
in the road, where an area has been opened and services are identifiable as obsolete,
then they should be removed at the time. In addition some redundant services may
be able to be reused by other service providers (code part 5.3.2).
The first sentence of the 7th paragraph be accepted in part and recommended that
the sentence be amended to read:
"The council will also require encourage the removal of redundant or
obsolete services and reuse of redundant services in the road.
Amendments to the 10th paragraph are accepted in part. The explanation is a result
of the assessment of the objectives and policies for network utility services. In
the assessment, it is considered that the objectives and policies which relate to
the provision of network utility services will assist the territorial authority
to carry out its functions of control of actual and potential effect of the use,
development or protection of land in order to achieve the purpose of the Act.
On one hand the needs of the community on the islands are met by the provision
of a level of network utility services which enables them to provide for their social,
economic and cultural wellbeing and for their health and safety. On the other hand
the natural environment which make the islands unique and contributes to amenity
values will be protected. Therefore it is considered that the plan's objectives
and policies achieve a balance between the above objectives and that the words "where
practicable" are superfluous and not required.
The second amendment of the submission seeks the last sentence be amended as
stated above. This is accepted in part as section 5(c) of the RMA states "Avoiding,
remedying, or mitigating any adverse effects of activities on the environment."
Therefore, it is recommended that the last sentence be amended to read:
Generally, there needs to be a balance between providing utility services
and ensuring that they do not detract from the environment in which they are located.
The above policies recognise the unique nature of utility services while ensuring
that they can be established, operated and maintained in a manner that has minor
adverse effects on the environment so that minor
adverse effects on the environment can be avoided, remedied or mitigated".
The amended sentence also deletes the word "minor" as this is not used in section
5(c) of the RMA.
2. Submission
1111/1
Submission
1111/1 seeks the amendments to the 8th paragraph of the explanation:
Submission
1111/1 amendments are accepted in part. It is recommended that the 8th paragraph
be amended to read:
(additions underlined, and deletions in strikethrough) :
"The cumulative effect of aboveground and utility services in any one location
can have an adverse effect on an area. There is a need to avoid the proliferation
of separate structures and this requires a co-operative approach so that visual
impacts effects are appropriately managed . This is particularly
relevant in the fast changing communications industry where sites for cellular phone
towers, antennas and wireless internet services can be difficult to find."
It is considered that the district plan is the appropriate document to manage
the visual effects of utility structures. As stated in the first sentence of the
explanation, utility service equipment by its very nature is utilitarian and can
be visually intrusive, especially in sensitive environments. In some instances,
some utility services can be installed to avoid further proliferation in a particular
area where the cumulative visual effect can be significant. However, the council
also recognises that other utility services cannot be installed that completely
avoids visual effects. In these cases the council would like to minimise these effects
. Both avoiding and minimising the visual effect of utility structures is considered
appropriate.
It is not recommended to use the words "where feasible and practicable" as this
implies a wide variety of scenarios where it may not be feasible and practicable
to install utility equipment in a manner which can avoid or minimise visual effects.
Rather, it is technical limitations that restrict where utility equipment can be
installed although such limitations can usually be overcome at increased cost to
the utility operator.
| Planner's recommendations about submissions
941/17,
941/18,
941/19,
941/20,
941/21,
941/22,
941/23,
941/24,
1111/1,
1243/41,
2928/1
That submissions
941/11,
941/17,
941/18,
941/19,
941/21,
941/23,
941/24 (2nd paragraph),
2928/1
be rejected.
That submission
941/20 be accepted in part and that policy 5.3.3(7) be amended to read:
By assessing the cumulative impact of overhead utilities and antennas
on the environment
That submission
941/22 be accepted in part and that policy 5.3.3(9) be amended to read:
By requiring encouraging the removal of redundant obsolete services
or and reuse of obsolete redundant services, particularly in the road.
That submission
941/24 be accepted in part and that, 7th and 10th paragraphs of the explanation
to objective 5.3.3 be amended to read:
7th paragraph: "The council will also require encourage the
removal of redundant or obsolete services and reuse of redundant services
in the road.
10th paragraph:
Generally, there needs to be a balance between providing utility services
and ensuring that they do not detract from the environment in which they are
located. The above policies recognise the unique nature of utility services
while ensuring that they can be established, operated and maintained in a
manner
that has minor adverse effects on the environment so that
minor adverse effects on the environment can be avoided,
remedied or mitigated".
That submission
1111/1 be accepted in part and that the 8th paragraph of the explanation
to objective 5.3.3 be amended to read:
"The cumulative effect of aboveground and utility services in any one
location can have an adverse effect on an area. There is a need to avoid
the proliferation of separate structures and this requires a co-operative
approach so that visual impacts effects are avoided or minimised
appropriately
managed . This is particularly relevant in the fast changing communications
industry where sites for cellular phone towers, antennas and wireless internet
services can be difficult to find."
That submission
1243/41 be accepted in part and that policy 5.3.3(1) be amended to read:
1. By requiring underground services for new subdivision and development
where the adverse effects on landscape or heritage values can be adequately
avoided, remedied or mitigated.
|
4.8 Submissions about clause 5.4
4.8.1 Decisions requested
Submissions
306/4,
372/4,
564/4,
578/4,
581/4,
635/4,
640/4,
645/4,
654/4,
676/4,
704/4,
708/4,
728/4,
743/4,
870/4,
882/4,
907/4,
934/4,
956/4,
1024/4,
1141/4,
1237/4,
1322/4,
1778/4,
1779/4,
1780/4,
1781/4,
1782/4,
1783/4,
1784/4, 1785/4,
1786/4,
1787/4,
1788/4,
1789/4,
1790/4,
1791/4,
1792/4,
2282/4,
2636/4,
2674/4,
2685/4,
2781/4,
2835/4,
2993/4,
3061/158,
3207/4,
3226/4,
3240/4,
3251/4,
3273/4,
3275/4,
3287/4,
3303/4,
3312/4,
3319/4,
3334/4,
3342/4,
3348/4,
3364/4,
3369/4,
3535/4,
3576/4,
3821/4,
3837/4
request:
That in clause 5.4 "wastewater" means only blackwater adequate to pump without
the addition of other waters.
Submission
635/4
has been withdrawn.
Submission
941/25 requests:
The second paragraph of the (clause 5.4) be amended to read (or words to similar
effect):
"While the Plan acknowledges the need for , and essential nature of,
utility services, the Plan also seeks to ensure that any adverse effects on
the environment are avoided, remedied or mitigated. In particular, the visual amenity
of the islands is unique and the council wishes to ensure that any effects on these
qualities are avoided or minimised".
4.8.2 Planner's analysis and recommendations
The submissions seek that in clause 5.4, "wastewater" means only blackwater adequate
to pump without the addition of other waters. This is not supported.
It would be impractical to refer to "wastewater" meaning only "blackwater" in
the context of clause 5.4. The context of "wastewater" in clause 5.4 is to recognise
the existing wastewater system at Owhanake currently serves the commercial properties
in Oneroa. Blackwater is water from the toilet and greywater is water from sinks,
baths and washing machines. Owhanake takes all wastewater (both blackwater and greywater)
from commercial properties in Oneroa Village.
As there is only one pipe, both blackwater and greywater are mixed before entering
the Owhanake wastewater treatment plant and being treated. If the definition of
wastewater referred to "blackwater," the effect would be that two reticulation systems
would be required to transport the respective "waters" to Owhanake. Therefore
to say that wastewater only refers to blackwater in the Oneroa context would be
incorrect.
For the above reasons, it is considered that submissions
306/4,
372/4,
564/4,
578/4,
581/4,
635/4,
640/4,
645/4,
654/4,
676/4,
704/4,
708/4,
728/4,
743/4,
870/4,
882/4,
907/4,
934/4,
956/4,
1024/4,
1141/4,
1237/4,
1322/4,
1778/4,
1779/4,
1780/4,
1781/4,
1782/4,
1783/4,
1784/4, 1785/4,
1786/4,
1787/4,
1788/4,
1789/4,
1790/4,
1791/4,
1792/4,
2282/4,
2636/4,
2674/4,
2685/4,
2781/4,
2835/4,
2993/4,
3061/158,
3207/4,
3226/4,
3240/4,
3251/4,
3273/4,
3275/4,
3287/4,
3303/4,
3312/4,
3319/4,
3334/4,
3342/4,
3348/4,
3364/4,
3369/4,
3535/4,
3576/4,
3821/4,
3837/4
be rejected.
4.8.2.2 Submission
941/25
Submission
941/25 seeks the inclusion of the words " and essential nature of", in the second
paragraph of clause 5.4 to read:
"While the Plan acknowledges the need for , and essential nature of,
utility services, the Plan also seeks to ensure that any adverse effects on
the environment are avoided, remedied or mitigated. In particular, the visual amenity
of the islands is unique and the council wishes to ensure that any effects on these
qualities are avoided or minimised".
This submission is supported. In essence, this is a continuation of the first
paragraph where the plan acknowledges the essential nature of utilities and its
role in sustaining the economic and social wellbeing of the community.
| Planner's recommendations about submissions
306/4,
372/4,
564/4,
578/4,
581/4,
635/4,
640/4,
645/4,
654/4,
676/4,
704/4,
708/4,
728/4,
743/4,
870/4,
882/4,
907/4,
934/4,
941/25,
956/4,
1024/4,
1141/4,
1237/4,
1322/4,
1778/4,
1779/4,
1780/4,
1781/4,
1782/4,
1783/4,
1784/4,
1785/4,
1786/4,
1787/4,
1788/4,
1789/4,
1790/4,
1791/4,
1792/4,
2282/4,
2636/4,
2674/4,
2685/4,
2781/4,
2835/4,
2993/4,
3061/158,
3207/4,
3226/4,
3240/4,
3251/4,
3273/4,
3275/4,
3287/4,
3303/4,
3312/4,
3319/4,
3334/4,
3342/4,
3348/4,
3364/4,
3369/4,
3535/4,
3576/4,
3821/4,
3837/4
That submissions
306/4,
372/4,
564/4,
578/4,
581/4,
635/4,
640/4,
645/4,
654/4,
676/4,
704/4,
708/4,
728/4,
743/4,
870/4,
882/4,
907/4,
934/4,
956/4,
1024/4,
1141/4,
1237/4,
1322/4,
1778/4,
1779/4,
1780/4,
1781/4,
1782/4,
1783/4,
1784/4,
1785/4,
1786/4,
1787/4,
1788/4,
1789/4,
1790/4,
1791/4,
1792/4,
2282/4,
2636/4,
2674/4,
2685/4,
2781/4,
2835/4,
2993/4,
3061/158,
3207/4,
3226/4,
3240/4,
3251/4,
3273/4,
3275/4,
3287/4,
3303/4,
3312/4,
3319/4,
3334/4,
3342/4,
3348/4,
3364/4,
3369/4,
3535/4,
3576/4,
3821/4,
3837/4
be rejected.
That submission
941/25 be accepted and that the 2nd paragraph of clause 5.4 be amended to
read:
"While the Plan acknowledges the need for , and essential nature of,
utility services, the Plan also seeks to ensure that any adverse effects
on the environment are avoided, remedied or mitigated. In particular, the visual
amenity of the islands is unique and the council wishes to ensure that any effects
on these qualities are avoided or minimised".
|
4.9 Submissions about clause 5.5 (including 5.5.2)
4.9.1 Decisions requested
Submission
941/27 seeks that clause 5.5.2 be adopted.
Submission
1147/2
seeks the removal of clauses 5.5.2 to 5.5.4 from part 5-utilities.
4.9.2 Planner's analysis and recommendations
The plan does not contain clauses 5.5.3-5.5.4 as expressed in the submission's
relief.
The RMA expressly provides for the council to consider an application without
the need for public notification or the need to obtain written approvals of or serve
notice on affected persons. Section 94D of the RMA states that a plan must expressly
provide for such matters as a rule in the plan (i.e clause 5.5.2). The council considers
that such a rule is appropriate for the three activities identified in clause 5.5.1
of the plan.
For the above reasons it is recommended that submission
941/27 be accepted.
For the above reasons it is recommended that submission
1147/2
be rejected.
| Planner's recommendations about submission
941/27,
1147/2
That submission
941/27 be accepted with no changes to the text.
That submission
1147/2
be rejected.
|
4.10 Submissions about clause 5.5 1
4.10.1 Decisions requested
Submission
33/1 requests:
That the following be provided for as permitted activities throughout the
islands:
Aboveground network utilities (not otherwise specifically provided for) outside
of legal road that can meet the relevant development controls contained within clause
5.6
Submission
33/2 requests:
Amend the 11th, 12th and 20th rows of the activity table in clause
5.5.1 to replace "cell site" and/or "cell phone" antennas and masts with the more
generic description of "radio-communication and telecommunication antennas" (or
relief of similar effect).
Submission
33/5 requests:
Amend row 17 of the activity table in clause 5.5.1 to include overhead
lines adjacent to formed legal roads in rural 1 as a permitted activity.
Submission
33/6 requests:
Amend row 10 and 19 of the activity table in clause 5.5.1 as necessary
such that antennas attached to buildings are permitted activities, and there is
no limit on the number of antennas attached to a building.
Submission
33/7 requests:
Amend row 21 of the activity table (clause 5.5.1) to make activities
not meeting one or more of the development standards a restricted discretionary
activity, with the council's discretion restricted to matters relevant to the standard
infringed.
Submission
33/8 requests:
Amend the activity status for row 23 of the activity table (clause
5.5.1) to make above ground network utilities outside of legal roads discretionary
activities.
Submission
519/5
requests:
Amend the wording of clause 5.5, to read (additions shown in underline) "Any
aboveground telecommunication, electricity or wastewater network utility that has
an area not exceeding of 2m2 in plan view and does not exceed 1.6m in height (excluding
plinth) provided that this rule excludes masts, vents and antennas" or words
of like effect.
Submission
519/6
requests:
Amend the wording of clause 5.5 to read (additions shown in underline) "Maintenance
and operation of existing network utility services and upgrading of underground
infrastructure ".
Submission
537/1 requests:
Amend clause 5.5.1, third row to read as follows:
"Underground telecommunication, electricity, water and wastewater and
network utilities".
Submissions
306/5,
372/5,
564/5,
578/5,
581/5,
635/5,
640/5,
645/5,
654/5,
676/5,
704/5,
708/5,
728/5,
743/5,
870/5,
882/5,
907/5,
934/5,
956/5,
1024/5,
1141/5,
1237/5,
1322/5,
1778/5,
1779/5,
1780/5,
1781/5,
1782/5,
1783/5,
1784/5, 1785/5,
1786/5,
1787/5,
1788/5,
1789/5,
1790/5,
1791/5,
1792/5,
2282/5,
2636/5,
2674/5,
2685/5,
2781/5,
2835/5,
2993/5,
3061/159,
3207/5,
3226/5,
3240/5,
3251/5,
3273/5,
3275/5,
3287/5,
3303/5,
3312/5,
3319/5,
3334/5,
3342/5,
3348/5,
3364/5,
3369/5,
3535/5,
3576/5,
3821/5,
3837/5
request:
That in clause 5.5.1 "wastewater" means only blackwater adequate to pump without
the addition of other waters
Submission
635/5
has been withdrawn.
Submission
941/26 requests:
(a) The activity table in clause 5.5.1 be adopted as notified, subject to
the relief sought in paragraphs (b) - (g) below.
(b) The fourth activity be amended to read (or words to similar effect):
"Bundling of existing overhead telecommunication and electricity lines provided
that the new line does not exceed 50mm in diameter".
(c) The ninth activity be amended to read (or words to similar effect):
"Any aboveground telecommunication, electricity or wastewater network utility
that has an area not exceeding of 6m² in plan view and does not exceed 1.75m in
height (excluding plinth) provided that this rule excludes masts and antennas".
(d) The fourteenth activity be adopted as notified.
(e) The seventeenth activity be a permitted activity in respect of landform
1 - 7 and also in respect of all rural land units (rural 1, 2 and 3).
(f) The twenty-first activity be amended so that it is a restricted discretionary
activity.
(g) The twenty-third activity be amended so that it is a discretionary activity.
Submission
1110/1 requests:
Supports row 13 of table 5.5.1.
Submission
1112/1 requests:
Amend row 9 in activity table 5.5.1 as follows (additions underlined and deletions
in strikethrough):
"Any aboveground telecommunication, electricity or wastewater network utility
located within the legal road reserve that has an area not exceeding of 2m2
in plan view and does not exceed 1.6 1.8m in height (exe inc luding plinth)
provided that this rule excludes masts and antennas."
Submission
1112/2 requests:
Insert a new row in activity table 5.5.1 which makes the following a permitted
activity:
"Any aboveground telecommunication, electricity or wastewater network utility
which complies with the relevant development controls for the zone it is located."
Submission
1112/3 requests:
Amend row 18 in activity table 5.5.1 as follows (additions underlined and
deletions in strikethrough):
"Any aboveground telecommunication, electricity or wastewater network utility
located within the legal road reserve that has an area exceeding 2m2 in plan
view and exceeds 1.6 1.8m in height ( exe inc luding plinth) provided that
this rule excludes masts and antennas.
Submission
1113/1 requests:
Amend row 10 of activity table 5.5.1 as follows (additions underlined and
deletions in strikethrough):
"Up to five antennas attached to building. "
Submission
1113/2 requests:
Amend row 19 of activity table 5.5.1 as follows (additions underlined and
deletions in strikethrough):
"Three Six or more antennas attached to a building."
Submission
1114/1 requests:
Amend row 12 in activity table 5.5.1 as follows (additions underlined and
deletions in strikethrough):
"Cell phone masts and attached antennas in commercial 5 and landform 3, 5
and 6; and rural 1."
Submission
1114/2 requests:
Delete row 20 in activity table 5.5.1.
Submission
1179/1
requests:
Opposes wastewater reticulation apparently provided for as a 'permitted activity'
in clause 5.5.1.
Submission
1596/8
requests:
Include "Bus stops/shelters" as a Permitted or Restricted Discretionary Activity
in clause 5.5.1 Activity Table Network Utility Services. Council's discretion could
be restricted to ensuring traffic safety and constructed form.
Submission
2106/5 requests:
Amend clause 5.5.1 Activity table, by amending row 10 to read as follows (insertions
marked with underlining):
'Up to two antennas attached to a building (excluding existing pole structures)'
Submission
2106/6 requests:
Amend clause 5.5.1 Activity table, by amending row 19 to read as follows (insertions
marked with underlining):
'Three or more antennas attached to a building (excluding existing pole
structures)'
Or alternative wording to like effect.
Submission
2928/2
requests:
Upgrading of network utility services to be a discretionary activity, with
manifest reluctance to underground a notified application.
Submission
2929/2
requests:
Seeks that the upgrading of overhead lines be a discretionary activity with
a presumption of undergrounding.
Submission
2935/1
requests:
Provide Objectives, Policies, Rules and Assessment Criteria in clause 5.5.1
that recognise and provide for dedicated cycleways along the main roads between
the villages and to the wharf at Matiatia and Kennedy Point.
Submission
3406/1
requests:
The community must have the right to dialogue and decide over an issue as
important as reticulation. It must not be a permitted activity which officers or
planners on the Isthmus can decide for us. They can guide us, present us with well
researched alternatives, but not decide for us (with specific reference to clause
5.5.1).
Submission
3621/1
requests:
Remove unformed legal road (as shown on maps 34 to 61) from land unit restrictions.
Submission
3701/2
requests:
The formulation of Objectives, Rules and Policies that prevent any roading
on peninsulars and promontories around Waiheke Island.
4.10.2 Planner's analysis and recommendations
4.10.2.1 Submission
33/1,
1112/1,
Submission
33/1
The relevant provisions in activity table 5.5.1 are:
Row 9 - "Any aboveground telecommunication, electricity or wastewater
network utility that has an area not exceeding 2m2 in plan view and does not exceed
1.6m in height (excluding plinth) provided that this rule excludes masts and antennas"
- Permitted activity.
Row 18 - "Any aboveground telecommunication, electricity or wastewater
network utility that has an area exceeding 2m2 in plan view and exceeds 1.6m in
height (excluding plinth) provided that this rule excludes masts and antennas"
- Restricted Discretionary activity.
This submission supports in principle the use of rules with specific dimensions
for utility structures in road reserve, but opposes the proposed activity rules
with respect to utilities outside legal road.
Submission
33/1 is accepted in part. The dimensions stated in rows 9 and 18 in the activity
table are of a reasonable limit to allow the majority of telecommunication cabinets
as a permitted activity. The submitter is concerned that the rules would essentially
make all other structures and buildings associated with the telecommunication network
outside of the legal road require restricted discretionary activities in many land
units.
The submission does not specifically state what other structures and buildings
the submitter currently installs which may not meet the permitted activity control.
Land units which allow buildings as a permitted activities are:
- Landform 3 (alluvial flats)
- Landform 5 (productive land)
- Island residential 1 (traditional residential -except coastal amenity area)
- Commercial 3 (local shops)
- Commercial 6 (Quarry)
- Commercial 7 (Wharf)
Great Barrier Island Settlement areas are divided into sub areas. The following
sub areas allow buildings as permitted activities:
- Residential amenity area
- Visitor accommodation area
- Claris light industry area
- Mulberry Grove School, and Okiwi School and Domain areas
All other land units and sub areas within settlement areas require a restricted
discretionary or non-complying resource consent application for buildings/structures.
These land units exhibit high landscape or visual amenity value thereby requiring
a greater degree of control.
The government has recently confirmed National Environment Standards (NES) for
telecommunication cabinets in the road reserve:
Telecommunication cabinets in road reserves shall be permitted activities
subject to the following restrictions:
Limitations on cabinet size and location
(Above ground level) |
Adjacent area type |
| Maximum height: 1.8m
Maximum footprint of any single cabinet: 1.4m2
Maximum footprint occupied by all cabinets:1.8m2
Maximum number of network utility cabinets exceeding 900mm in height in
any location: one [1]
Minimum separation distance from any existing utility cabinet exceeding
900mm in height: 30m
(except where specific provision by way of dedicated areas has been
made for utilities infrastructure within the road reserve)
|
Residential |
| Maximum height: 2m
Maximum footprint: 2.0m2
Minimum separation distance from any existing utility cabinet exceeding
900mm in height: 30m
(except where specific provision by way of dedicated areas has been
made for utilities infrastructure within the road reserve)
|
Non-residential |
[1] Cabinets in new subdivisions are often
located in areas allocated for utilities, for example dedicated areas of road reserve
are provided. In these cases it would be considered a reasonable condition of a
Road Opening Notice that the cabinets be located within those areas.
[1] Areas identified as historic, historic
heritage, cultural sites or open space
While the standards are limited to telecommunication cabinets it is considered
that these size thresholds would be appropriate for managing aboveground cabinets
of all types within private property. If the above thresholds can be met in the
appropriate land unit identified above then permitted activity status can be afforded
these activities.
If the above standards located on the identified land units cannot be met then
a resource consent application to exceed the threshold or a designation should be
sought. These methods will allow a greater degree of assessment and control of the
visual effects of utility structures given the utilitarian nature of utility equipment
and the visual effects of such services.
Masts and antennas are exempted because of the generally slim line nature of
equipment and also the activity table expressly provides for them by specific rules.
As currently worded, the relief sought in the submission would contradict Row
22 of the activity table. Therefore any relief recommended would be specifically
related to aboveground structures exceeding area of 2m2 and height of 1.6m excluding
masts and antennas.
It is considered
For the above reasons, it is recommended that submission
33/1 be accepted in part and that the following rules be provided for as permitted
activities throughout the islands:
Aboveground telecommunication, electricity or wastewater network utility in
Island Residential 1 (traditional residential-except coastal amenity area) and Settlement
Area sub area-(Residential amenity area) that meets the following:
- Maximum height: 1.8m
- Maximum footprint of any single cabinet or structure: 1.4m2
- Maximum footprint occupied by all cabinet or structure: 1.8m2
Provided that this rule excludes masts and antennas
and
Aboveground telecommunication, electricity or wastewater network utility in
Landform 3 (alluvial flats), Landform 5 (productive land), Commercial 3 (local shops),
Commercial 6 (Quarry), Commercial 7 (Wharf), Settlement Area sub area-(Visitor accommodation
area, Claris light industry area, Mulberry Grove School and Okiwi School and Domain
areas) that meets the following:
- Maximum height: 2m
- Maximum footprint of any single cabinet or structure: 2.0m2
Provided that this rule excludes masts and antennas
Submission
1112/1
The submission seeks that aboveground utilities be located within the legal road
reserve, have an area not exceeding 2m2 in plan view and 1.8m in height (including
plinth) as a permitted activity - Row 9 of activity table . A minor grammatical
change is also sought and supported.
The government has recently introduced National Environmental Standards (NES)
for telecommunication facilities in the road reserve.
While these standards apply to telecommunications, they do not apply to electricity
and wastewater facilities.
It is recommended that the reference to telecommunication be deleted in Row 9
of the activity table to reflect the standards introduced.
In effect, the NES permits telecommunication facilities to be located in the
road reserve as of right (subject to restrictions). These restrictions are generally
based on size limits and location.
The aspect of the submission for utility services to be located within the legal
road reserve is also supported as the new National Environmental Standards (NES)
for telecommunication facilities provides size thresholds. These size thresholds
should also apply to electricity and wastewater network services. The council would
still need to control visual amenity effects from these utility services within
the road reserve if the size thresholds were to be exceeded.
There are some instances where legal road reserve traverses sensitive land units
and significant heritage areas in an unformed state. All matters of development
in this respect require a resource consent for assessment. The activity table has
also been drafted so that various utilities are permitted in 'formed legal road'
where the environment has been modified and that any environmental effect of various
additional utility services can be considered minor. However, any proposal or modification
of 'unformed legal road' requires resource consent assessment due the unmodified
nature of the legal road and that any modification can be assessed to consider whether
there are any significant environmental effects. The planning maps identify 'unformed
legal road'. In preparing the proposed rule, it was considered that the modifications
that occur through road formation are such that the additional effect of utilities
that would be permitted by this rule would be no more than minor. However, this
does not apply to areas of unformed road, which may be through sensitive environments
and landscapes. For this reason, maintaining the permitted status only in relation
to formed legal road is recommended.
The submission seeks the height of aboveground utility services be increased
from 1.6m (excluding plinth) to 1.8m (including plinth). The standard as it is currently
worded could be interpreted as having a greater overall height of 1.6m due to the
unspecified height of the plinth. The proposed amendment to the rule specifies a
maximum height of 1.8m including plinth so the combination of cabinet and plinth
could vary. This amendment is supported given the minor difference in height. In
addition, the size thresholds would also be consistent with the NES for telecommunications.
This amendment only applies to formed legal road adjacent to residential land. A
new activity is required to be added to the activity table in clause 5.5.1 of the
plan and be provided as a permitted activity:
Any aboveground electricity or wastewater network utility within formed legal
road reserve that has an area not exceeding 1.8m2 in plan view, does not exceed
1.8m in height (including plinth) and is located adjacent to residential land units
provided that this rule excludes masts and antennas.
The size thresholds for telecommunication facilities in the road reserve adjacent
to non-residential land are more permissive. This also needs to be reflected in
the activity table so that row 9 of the activity table in clause 5.5.1 of the plan
and any consequential amendments in the plan be amended to read:
Any aboveground telecommunication, electricity or wastewater network utility
within formed legal road reserve that has an area not exceeding of 2m2 in plan view,
does not exceed 1.6m 2.0m in height (exe inc luding plinth) and is
located adjacent to non-residential land units provided that this rule excludes
masts and antennas."
4.10.2.2 Submission
33/2
The submission seeks amendments to row 11,12 and 20 of the activity table in
clause 5.5.1 to replace 'cell site: and/or "cell phone antennas and masts" with
a more generic description of "radio-communication and telecommunication antennas".
This submission is supported. The rules as it currently reads would exclude other
forms of radio-telecommunication masts and antennas. A generic description is more
appropriate as telecommunication encompasses more than cell phone masts and antennas
and could include services such as antennas for digital microwave radio links, customer
multi access radio, broadcasting etc.
Consequential amendments to Part 14-definitions will be addressed as part of
the submissions to this section of the plan.
For the above reasons it is recommended that submission
33/2 be accepted and that row 11, 12 and 20 of the activity table in clause
5.5.1 be amended to read:
(underline indicates additions, strikethroughs indicate deletions)
Row 11- Cell site Radio-communication and telecommunication
antennas located on existing pole structures
Row 12- Cell phone Radio-communication and telecommunication
masts and attached antennas in commercial 5 and landform 3, 5 and 6
Row 20- Cell phone Radio-communication and telecommunication
masts and attached antennas in rural 1
4.10.2.3 Submission
33/5,
941/26(e)
Submission
33/5
The submission seeks that Row 17 of the activity table in clause 5.5.1 be amended
to include overhead lines adjacent to formed legal roads in the Rural 1 (rural amenity)
land unit as a permitted activity. This is supported in part.
The Rural 1 (rural amenity) is applied to pockets of small scale, rural land
located between the village areas of western Waiheke. Part 10a.19 states that Rural
amenity is characterised by:
- Small scale farming and horticulture activities
- Flat to rolling land
- A rural landscape with built elements but also the openness, features and
patterns created by productive activities.
- The contrast of its rural landscape with the intensity and nature of the surrounding
village development.
The plan also recognises the land unit adjoining Onetangi Road differs from the
other areas of rural amenity land in that it contains activities that may be considered
'non-rural' in character such as wineries and tourist complexes.
Overall, the land unit has a high visual amenity value, largely due to the contrast
of its landscape with the village style development that occurs throughout western
Waiheke.
The plan recognises that formed legal road is not classified with a land unit.
However, the key question is whether the roads adjacent to rural 1 is considered
'rural'. Currently, overhead lines exists along the legal road reserve adjacent
to the Rural 1 land unit. It is acknowledged that telephone lines are typically
deployed overhead in rural areas throughout New Zealand due to the high costs of
serving small numbers of customers over large distances.
However, it is considered that the current landholdings classified as Rural 1(rural
amenity) are not the typical 'rural' landscape given their close proximity to built
up urban areas and are more akin to a 'rural-amenity' landscape. The rural character
of this land unit is enjoyed by the neighbouring residential communities, and the
productive capacity of this rural land is of lesser importance than its amenity
function. The 'rural' landscape more typical of New Zealand is located at the eastern
end of Waiheke, and is classed as Landform 5 (Productive Land). The proposed rule
already allows for overhead lines as permitted activities in landform 1-7.
It is acknowledged however that rural 1 does exhibit a degree of rural amenity
character and given there are existing overhead lines for both telecommunications
and electricity, it is considered that overhead lines can be permitted to the extent
that it applies to existing formed legal road existing at the date of notification
of the plan.
Any provision for further overhead lines in formed legal road as a permitted
activity should be limited to the existing roads at the time of notification of
the proposed plan. Any services provided as a result of further subdivision and
development within rural 1 should be underground. This is consistent with the policy
of requiring underground services for subdivision (Part 12 of the plan) and new
development.
Submission
941/26(e)
The submission seeks that Row 17 of the activity table in clause 5.5.1 be amended
to include overhead lines adjacent to formed legal roads in the Rural 1 (rural amenity),
Rural 2 (Western Landscape) and Rural 3 (Rakino Amenity) land units as a permitted
activity. This is supported in part relating to Rural 1 but not supported in Rural
2 and 3.
The Rural 1 aspect of this submission is the same as per comment on submission
33/5 above.
The rural 2 land unit occupies land that is described as 'rural-residential'
landscape. It is interspersed with houses in Western Waiheke and Te Whau, which
have been formed as comprehensive developments amongst the rural farmland. To allow
the introduction of overhead lines into these areas, which have been developed with
such services being underground, would detract from the high visual amenity that
has been achieved through these developments to date.
The rural 3 land relates to Rakino, which does not have overhead lines at present.
To allow new overhead lines to be introduced as permitted activities across an island
that currently does not have overhead lines would detract from the amenity values
of the existing landscape.
For the above reasons it is recommended that Row 17 of the activity table in
clause 5.5.1 be amended to read:
( underline indicates additions)
New overhead telecommunication and/or electricity distribution lines in formed
legal road adjoining landform 1-7 and rural 1 provided that for rural 1 this
rule shall apply to formed legal roads existing at 18 September 2006.
It is also recommended that for the reasons above, submission
941/26(e) relating to rural 2 and 3 be rejected.
These submissions oppose the restriction of the number of antennas that are attached
to buildings. Submission
33/6 states that between six and nine antennas are typically mounted on buildings
especially in high density urban areas and therefore seeks that no limit be imposed
on the number of antennas attached to buildings.
Submission
1113/1 and
1113/2 states that telecommunication facilities require at least three panel
antennas to enable 3600 coverage (1200 per sector) plus two dish antennas. The gulf
islands have relatively large separation distances and therefore most cellular facilities
require both receiving and sending microwave dish antenna to link the facility with
other sites within the network. A total of five antennas is therefore a minimum
technical requirement.
The number of antennas located on existing buildings is limited to two antennas
as a greater number has the potential to be visually intrusive. It is acknowledged
that a greater number of antennas would provide greater coverage over the islands
for cellular telecommunication facilities. However, given the village nature of
the islands and the relatively small scale of the built up areas and villages (as
opposed to the isthmus or CBD), five or more antennas on a building has the potential
to be visually intrusive in areas such as Oneroa village, Ostend village and other
land units through out the islands. Additionally, due to the relatively low height
of most buildings, antennas can be more easily seen than they may be on tall buildings
such as are located in the CBD. Two antennas as a permitted activity in all
land units would allow a greater dispersion of antennas throughout the islands and
lessen the visual impact as opposed to a greater concentration of antennas in one
area which has a greater visual impact on that specific area.
The assessment criteria for a restricted discretionary activity for three or
more antennas attached to a building is limited to:
- Design, external appearance and visual effects
- Site layout and placement
- Height and proportion
- Other environmental effects including noise, vibration, odour, dust, discharges
to air and water, lighting and spill lighting, hazardous substances and vehicle
movements
- Removal of redundant services
- Co-location
- Cumulative visual effects
- Heritage
- Radio frequency fields
The above matters may be treated on a non-notified basis or without the need
to obtain written approval of or serve notice on affected persons.
With a greater number of telecommunication companies being established in New
Zealand it is important that the council exercises a degree of control on the visual
effect of antennas located on buildings. Given that new technology is constantly
evolving in the telecommunications industry (e.g 3G etc), there is likely to be
an increase in the demand for cellular sites throughout the island.
It is important that such sites be assessed for appropriateness in terms of the
visual effects of antennas and other criteria as stated above. Given the unique
village nature and relatively low density of population on the islands it is considered
that there is the potential for adverse visual effects and that two antennas per
building as a permitted activity is considered appropriate. Any number greater than
two should be assessed to determine the appropriateness of the site/building.
In addition, the government has recently confirmed the National Environmental
Standards (NES) for telecommunications. One of the regulations will allow the installation
of masts and antennas on existing structures in the road reserve as a permitted
activity, subject to specified limitations to height and size. The combination of
two antennas on buildings (or three or more as a Restricted Discretionary activity)
and the permitted activity status afforded to mast and antennas in the road reserve
by the NES should be sufficient to provide coverage of the islands to meet the cellular
telecommunication needs.
Pending further information at the hearing from the telecommunication companies
explaining the technical requirements for cellular sites, it is recommended that
submissions
33/6,
1113/1 and
1113/2 be rejected for the above reasons.
4.10.2.5 Submissions
33/7,
941/26(f)
The submissions oppose the discretionary activity status for permitted activities
that do not meet the one or more of the development controls. The submissions argue
that it is more appropriate to make such activities restricted discretionary, with
only the particular aspect that is infringed being assessed.
The submissions are not supported. This would not be consistent with the other
development control modifications in all land units and settlement areas where the
plan requires discretionary activity assessment. Any infringement would include
assessment of the following as stated in clause 10c.3.1-Development control modification
assessment of the plan:
- Whether allowing the infringement is consistent with the objectives in clause
10c.2.
- Whether the infringement(s) will result in any adverse effects on amenity
values of neighbouring properties, the character of the surrounding environment
or the natural environment which cannot be avoided, remedied or mitigated.
- Whether the development remains consistent with the intention of the development
control(s) it infringes having regard to explanation given in the plan for the
particular control(s).
- The extent to which there will be adverse cumulative effects where a development
infringes two or more development controls.
Furthermore, any infringement(s) to the identified development controls may be
difficult to internalise within a site and the council would need to assess the
overall effects of proposals with respect to the particular circumstances of a site.
Development control modifications may also be assessed on a non-notified basis,
but this needs to be assessed on a case by case basis.
For the above reasons it is recommended that submissions
33/7 and
941/26(f) be rejected.
4.10.2.6 Submissions
33/8,
941/26(g)
These submissions oppose the non-complying activity status being applied to aboveground
and overhead utilities within the coastal and water protection yards and landforms
1,2,4 and 7. The submissions state that there maybe some technical reasons requiring
installation of these services in these areas and that such services should be assessed
on their merits on a case by case basis as a discretionary activity and that a non-complying
activity status is considered unreasonable.
This is not supported. The classification of aboveground and overhead services
as non-complying activities is to ensure that these services are assessed against
the tests as outlined in section104 of the RMA. It is considered that these land
units and protection yards are the most sensitive areas of the gulf islands and
should be afforded a higher level of protection. This is reinforced by section 6
of the RMA:
Section 6 - Matters of national importance of the RMA states:
(a) The preservation of the natural character of the coastal environment
(including the coastal marine area), wetlands and lakes and rivers and their margins,
and the protection of them from inappropriate subdivision, use and development:
(b) The protection of outstanding natural features and landscapes from
inappropriate subdivision, use and development:
(c) The protection of areas of significant indigenous vegetation and significant
habitats of indigenous fauna...
Furthermore, the classification does not mean that utility services cannot establish
in the stated areas provided that it can be shown that:
- The adverse effects of the activity on the environment will be minor; or
- The application will not be contrary to the objectives and policies of the
plan
(Section 104D RMA).
Therefore the construction of utility services within the coastal and water body
protection yards or in landform 1,2,4 and 7 classified as a non-complying activity
is considered appropriate.
For the above reasons, it is recommended that submission
33/8 and
941/26(g) be rejected.
4.10.2.7 Submissions
519/5
The submission seeks the addition of vents in Row 9 of the activity table.
The submission states that vents are required for wastewater infrastructure and
are similar in nature to a mast or antenna and that a vent would generate similar
visual effects to these. This submission is supported to the effect that the submitter
provide evidence at the hearing depicting the types of vents currently used. In
this respect, it is considered that vents should be of a slim nature with as narrow
a profile as possible.
For the above reason, it is recommended that submission
519/5
be accepted and that row 9 of the activity table in clause 5.5.1 be amended to read:
( underline indicates additions)
Any aboveground telecommunication, electricity or wastewater network utility
that has an area not exceeding 2m2 in plan view and does not exceed 1.6m in height
(excluding plinth) provided that this rule excludes masts, vents and antennas.
4.10.2.8 Submissions
519/6
The submission seeks the addition of "upgrading of underground infrastructure"
in row two of the activity table to allow for efficient and necessary increased
service demand for the community. This submission is not supported.
Row three makes provision for underground services as a permitted activity and
it is considered that any upgrading of underground infrastructure could be considered
under this rule.
For the above reason, it is recommended that submission
519/6
be rejected.
4.10.2.9 Submissions
537/1
The submission seeks the inclusion of underground water utility services to ensure
the future ability to provide for reticulated water supplies in communities to assist
in operation requirements for the New Zealand Fire Service.
This submission is supported. The environmental effects are minor with respect
to visual effects and there is no difference between underground telecommunication,
electricity and wastewater utilities. The most likely visual effects will come from
the earthworks associated with trenching and tunnelling. Earthworks associated with
utility services are required to comply with the earthwork controls in clause 10c.5.6.1.
For the above reason, it is recommended that
537/1 be accepted and that row 3 of the activity table in clause 5.5.1 be amended
to read:
( underline indicates additions)
Underground telecommunication, electricity, water and wastewater network
utilities
Refer to clause 4.8.2.1 of this report for the analyses of these submissions.
For the reasons outlined in clause 4.8.2.1 of this report, it is recommended
that the above submissions be rejected.
4.10.2.11 Submissions
941/26 (b)(c)(d)(e)
This submission seeks several changes to the activity table in clause 5.5.1.
These will be dealt with in turn:
(b) Row 4 of the activity table relates to the bundling of existing overhead
telecommunication and electricity lines, provided that the new line does not exceed
40mm in diameter.
The submission states that for practical and operational reasons the permitted
diameter be increased to 50mm, and that bundled lines to be comprised of 40mm is
not always possible and some flexibility should be provided for.
This submission is not supported. The rationale for bundling of existing lines
is supported to the extent that less overhead lines will be visible. However, a
result of the bundling will be a "fatter" cable. It is considered that 40mm will
be sufficient diameter to minimise any adverse visual effects and is of a sufficient
width to accommodate most operational and practical needs. Any additional increase
in diameter should be assessed for any visual effects. Furthermore, the diameter
is also consistent with the diameter proposed for the activity in Row 14 of the
activity table.
The submitter may wish to expand on the rationale for the requested 50mm diameter
cable at the hearing.
(c) Row 9 of the activity table relates to aboveground telecommunication, electricity
and wastewater network utilities not exceeding 2m2 (plan view) in area and a maximum
height of 1.6m.
The submission opposes the standards as the dimensions are too restrictive and
unreasonable because the submitter's aboveground equipment would not be able to
comply with the dimensions. The submission proposes a maximum area of 6m2 in area
(plan view) and a maximum height of 1.75m.
The dimensions as notified in the plan reflect the council's desire to standardise
all above ground equipment in relation to size. This is to minimise adverse visual
amenity effects due to the utilitarian nature of utility equipment. It is acknowledged
that the function of equipment often dictates the size and appearance and as a result,
the standard is seen as too restrictive. The submission does not specifically mention
the number and exact types of equipment that maybe required and there maybe a case
whereby some equipment could be permitted.
Any thresholds for permitted activity status should be investigated as there
needs to be a balance between providing for equipment that have little effect on
visual amenity and the need to provide a functional standard that meets the majority
of equipment needs of the utility providers. Any threshold standard should not always
mean that all equipment should have permitted activity status. Rather, the 2m2 proposed
standard for permitted activities is considered an appropriate maximum size for
all specified situations, beyond which size the activity would be assessed on its
effects. To raise the permitted standard to 6m2 may better meet the functional requirements
of the utility operator, but would add to their visual dominance and provide the
ability for their construction irrespective of the sensitivity of the receiving
environment.
It is noted that as per analysis in clause 4.10.2.1 (submission
1112/1) of this report height of equipment could be permitted to 1.8m (including
plinth) but that the area size of 2m2 remain.
The submitter may also designate sites if the equipment is of a sufficient size
and importance to the network. This could help mitigate any visual effects by conditions
such as landscaping being imposed on the designation.
The proposed standard as submitted is also of a substantial size that can adversely
affect the road reserve with respect to visual amenity and traffic and roading considerations.
In addition, the proposed increase in standard size as a permitted activity, would
also apply to telecommunications and wastewater aboveground services.
For the above reasons, it is recommended that submission
941/26(c) be accepted in part.
(d) Row 14 of the activity table relates to the provision of an additional
overhead broadband internet distribution line on existing support poles provided
that the additional line does not exceed 40mm in diameter as a permitted activity.
The submission supports this activity. This submission is supported as the addition
of one line would have minimal visual amenity effects where existing lines overhead
lines exist. It is also considered that the provision of broadband internet is consistent
with the New Zealand Government's strategic direction for providing ease of access
to broadband. In addition, the low density (population and built form) nature of
the islands would make undergrounding of a new line cost prohibitive.
It should also be acknowledged that this activity applies to existing lines and
support poles. Where there are underground lines and no existing overhead lines
and support poles, undergrounding of the additional broadband internet line is required.
Alternatively a resource consent will be required for the overhead line.
In this case, it is considered that the provision of an additional overhead line
would have minimal visual effect and, on balance, would provide for the communities'
economic, social and cultural well being.
(e) Row 17 of the activity table provides for new overhead telecommunication
and electric distribution lines in formed legal road adjoining landform 1-7 as a
permitted activity. The submission seeks that it would also be appropriate to extend
this to Rural 1,2 and 3 as it is considered the cost of undergrounding these rural
areas is cost prohibitive and that rural roads usually do not have formed sidewalks
in which to install cables.
This submission has been addressed under clause 4.10.2.3 of this report. For
the reasons set out in clause 4.10.2.3 of this report, it is recommended that submission
941/26(e) be accepted in part.
4.10.2.12 Submissions
1110/1
The submission supports the provision of metrolight poles as a permitted activity
within land units and settlement areas. This submission is supported.
4.10.2.13 Submission
1112/2
This submission is similar to submission
33/1 in that utility services which comply with the relevant development controls
for the land unit in which it is located is a permitted activity. Submission
33/1 differs in that it related to compliance with the relevant controls in
clause 5.6 of the plan rather than the development controls of the relevant land
unit.
This submission is not supported. A separate network utility chapter has been
specifically developed to take into account the unique nature of utility services
where compliance with the land unit's relevant development controls is not always
appropriate. The activity table in clause 5.5.1 establishes thresholds for the sizes
of cabinets and equipment proposing to establish within the relevant land unit.
It is considered that these thresholds as notified in the plan are appropriate for
managing the visual effects as a permitted activity.
Specific development controls (clause 5.6) have also been customised for utility
services to mitigate the effects of these services. Furthermore, some equipment
(streetlight poles, metrolight poles, telecommunication/electricity distribution
poles) are exempt from some development controls which would be relevant to all
land units (e.g height, building in relation to boundary, yards) thereby recognising
the unique nature of these utility services.
In addition, the use of a site specifically for utility purposes can have adverse
effects that are not normally associated with the relevant land units use. As stated
earlier in this report, utility services by their very nature are utilitarian and
have the potential to detract from the visual amenity of the area in which they
are located and generate effects beyond the immediate site (e.g residential areas).
It is considered that beyond these thresholds, matters can be assessed as a discretionary
activity.
Alternatively, there is the option of designation. This process would allow for
the assessment of the site and purpose and nature of the work. Appropriate conditions
could also be imposed on the designation to address effects of the work to ensure
that any adverse effects are avoided, remedied or mitigated.
For the above reasons, it is recommended that
1112/2 be rejected.
4.10.2.14 Submission
1112/3
This submission also relates to submission
1112/1 and
1112/2. The submission states that activities in rows 9 and 18 of the activity
table provide no distinction between the location of aboveground network facilities,
that is either in the road reserve or on private land. The submitter considers the
provisions of rows 9 and 18 should only relate to structures in the legal road reserve.
In other areas (i.e not legal road reserve), it is considered that aboveground facilities
should be subject to the relevant bulk and location standards of the underlying
zone.
The submission states that the size of equipment cabinets are primarily dictated
by function, and the need to contain certain components and that it is not a case
of making equipment cabinets smaller to meet smaller dimension controls. It is for
these reasons that there are supply and operational problems with meeting the permitted
sizes for aboveground structures in the plan.
This submission is not supported. This has been discussed in clause
1112/1 (clause 4.10.2.1). The thresholds of aboveground utility services have
been developed to take into account the sizes of aboveground equipment. It is considered
that the thresholds would cater for the majority of the cabinets/equipment used
by the utility companies. There will be some instances where the cabinets/equipment
are of such a size that a resource consent should be required for assessment regardless
of whether it is located within the road reserve or private land. One of the primary
reasons being that the use of the site specifically for utility purpose may detract
from the amenities of the area and can have adverse effects (particularly visual
amenity) that are not normally associated with the relevant land units use.
Furthermore, the recently confirmed National Environmental Standards (NES) should
provide for telecommunication facilities within the road reserve.
For the above reasons, it is recommended that
1112/3 be rejected.
Rural 1(rural amenity) is not the typical 'rural' landscape given its close proximity
to built up urban areas and is more akin to a 'rural-amenity landscape. The rural
character of this land unit is enjoyed by the neighbouring residential communities,
and the productive capacity of this rural land is of lesser importance than its
amenity function. The 'rural' landscape more typical of New Zealand is located at
the eastern end of Waiheke, and is classed as Landform 5 (Productive Land).
To allow cell phone masts and antennas in Rural 1 as permitted activities would
not be in keeping with the amenity values of this land unit.
For the above reason, it is recommended that these submissions be rejected.
4.10.2.16 Submission
1179/1
This submission opposes wastewater reticulation provided for as a permitted activity.
The submission states that wastewater should be dealt with 'on-site'. Reticulation
of wastewater will concentrate the problem in one area and necessitate the need
for water to reticulate the wastewater. This may require the need for aquifer water
which should be used for productive land uses. Possible rate increases would also
result from a wastewater reticulation.
The submission is not supported. The provision of wastewater in the activity
table in clause 5.5.1 (Row 3) recognises the existing Oneroa wastewater system.
There maybe instances where upgrading of existing infrastructure is required. The
wastewater provision in the activity table facilitates this process. Notwithstanding
this, it is recognised that any future policy direction in terms of wastewater reticulation
on Waiheke will need appropriate council committee approval and funding. The provision
of wastewater network utilities in the activity table does not imply further reticulation
on Waiheke.
For the above reasons, it is recommended that submission
1179/1
be rejected.
4.10.2.17 Submission
1596/8
This submission seeks the inclusion of bus stops/shelters as a permitted or restricted
discretionary activity. The submission is accepted in part to the extent that provision
exists in the plan for bus stops/shelters as a permitted activity. This is included
in row 8 of the activity table under the definition of 'road network' and in Part
14 of the plan.
The "Road network' definition as defined: 'means a system of roads to allow
the movement of pedestrian, cycles and vehicles. It includes any of the following:
1. Underground infrastructure located at or below the existing ground surface.
This includes any of the following...
f. Transport shelters...
2. Aboveground infrastructure located above the existing ground surface. This
includes any of the following...
h. Transport shelters...'
The road opening notice (RON) procedures under the Local Government Act addresses
the issue of traffic safety, location and placement of structures and reinstatement
of the road.
For the above reasons, it is recommended that submission
1596/8
be accepted in part to the extent that provision for bus stops/shelters already
exist in the activity table in clause 5.5.1 of the plan and Part 14-definitions.
These submissions seek amendments to distinguish the activity of 'antennas attached
to a building' (rows 10 and 19) from the separate listed activity of cell site antennas
located on 'existing pole structure' (row 11) as this could create ambiguity between
the two activities.
The submission is supported for the reasons outline above and that Rows 10 and
19 be amended respectively:
( underline indicates additions)
Up to two antennas attached to a building (excluding existing pole structures)
Three or more antennas attached to a building (excluding existing pole
structures)
These submissions seek the upgrading of overhead lines to be a discretionary
activity with undergrounding the priority and that any new overhead lines should
be classified as a notified application. These submissions are not supported.
The submissions do not differentiate between 'existing overhead lines' and 'new
overhead lines'. The council's policy is to require new lines to be underground
with respect to subdivision and development. This is stated in the objectives and
policies (clause 5.3.3) and the activity table which permits undergrounding of utilities
and the reference to the Hauraki Gulf Islands Development Code.
Upgrading of overhead lines is provided for as a permitted activity in Row 4
of the activity table in clause 5.5.1 where 'Bundling of existing overhead telecommunication
and electricity lines provided that the new line does not exceed 40mm in diameter'
. In addition, the construction of an additional broadband internet overhead
distribution line is a permitted activity (row 14 of the activity table).
It is considered that the effect on visual amenity of these activities will be
minor and that the activities be retained as a permitted activity. The rationalisation
of existing lines is considered a logical progression of utilising an existing resource
which would enable the community to further provide for their social and economic
wellbeing.
New overhead lines in some rural land units and adjoining formed legal roads
(rows 5, 16, 17) are also permitted activities. Given the large distances that lines
have to cover in a rural context, undergrounding may not be practical on economic
grounds.
For the above reasons, it is recommended that submissions
2928/2
and 2929/2
be rejected.
4.10.2.20 Submission
2935/1
This submission seeks to provide objectives, policies, rules and assessment criteria
that recognise and provide for dedicated cycleways along the main roads between
the villages and to the wharf at Matiatia and Kennedy Point. The submission supports
the existing provision for cycling and walking but would like the provision of a
network of interlinked separated cycleway along the main routes of the island. This
would separate the motor vehicle from the cycle.
This submission is supported in part. The network utility services section of
the plan provides the framework in which to provide the road network (row 8 of activity
table in clause 5.5.1) on the islands. It is not the role of the district plan to
provide the detail of delivering cycleways in the islands. This is done through
the Long Term Council Community Plan (LTCCP) and annual plan process. Part 13-Connectivity
and Linkages provides more detailed objectives, policies, rules and assessment criteria
with respect to cycleways as highlighted in clauses 13.2.6, 13.3.5, 13.4.6, 13.6.2
and 13.7.5 of the plan.
It is considered that the provisions of Part 5 and Part 13 allow for the provision
of cycleways and that other documents will be used to deliver that in the islands.
One minor amendment to part 14-definitions of the plan would be to add 'cycleways'
within the definition of 'road network' to make the definition more explicit.
4.10.2.21 Submission
3406/1
This submission raises the issue of reticulation. The submission considers that
reticulation will change the character of the island and it must not be a permitted
activity.
The activity table in clause 5.5.1 provides for a range of activities. Underground
wastewater utilites is provided as a permitted activity in Row 3 of the activity
table. This is to recognise the existing wastewater system which serves the Oneroa
commercial area . In terms of visual and amenity effects, there is no differentiation
between electricity, telecommunication and wastewater facilities. However the decision
to reticulate would be a decision which would need to made by the community and
with appropriate council committee funding and approval. This district plan does
not represent a change to reticulation for the islands as it recognises the existing
Owhanake plant.
For the above reasons, it is recommended that submissions
3406/1
be rejected.
4.10.2.22 Submission
3621/1
The submission seeks the removal of the unformed legal road notation from the
planning maps because if the council wishes to form the road, it would be caught
by the land unit restrictions. This is not supported.
The activity table in clause 5.5.1 differentiates between formed and unformed
legal road. The rationale is to provide for the construction, operation and maintenance
of the road network where the road is existing as the environment in which it is
situated has been modified to an extent that further upgrading of the road will
have minimal environmental effect.
The gulf islands also have many unformed legal roads and the landscape is such
that new roads may have to be constructed through bush, forest areas or on land
with a topography which would require substantial earthworks. It is therefore appropriate
that formation of any unformed road would require consent to manage the environmental
effect associated with constructing a new road. Therefore it is considered that
the need to differentiate between unformed road and formed road is justified.
For the above reasons, it is recommended that submissions
3621/1
be rejected.
4.10.2.23 Submission
3701/2
This submission seeks the formulation of objectives, rules and policies that
prevent roading on peninsulas and promontories around Waiheke island as these are
very significant natural and landscape features that must be protected and retained
in their 'natural' state.
The construction of roads can occur three ways:
- Widening or upgrading an existing formed road
- Constructing unformed legal road
- Vesting and construction of road through subdivision
The widening or upgrading of existing formed roads occurs when the capacity of
the road is in need of upgrading due to increased traffic. Roads already exist on
the peninsulas and promontories of the islands and the council maintains these roads
as part of its assets. It is not considered appropriate to develop objectives, policies
and rules to prevent the construction, maintenance and operation of existing roads
already located on peninsulas and promontories.
The construction of unformed legal roads on the islands is a complex issue. It
is often determined by the need or demand for such roads and also the cost/benefit
of constructing such a road. The council also has to consider the topographical
constraints (especially on Great Barrier Island) and route of the road which may
involve road legalisation. The council would generally not construct new roads unless
there is a demonstrable need. Part 13 of the plan addresses the issue of unformed
roads on the islands (clauses 13.2.4, 13.3.3, 13.4.4). Part 5 of the plan also addresses
the formation of unformed road which requires discretionary activity consent and
the need to consider all effects.
The vesting and construction of roads can also be associated with subdivision.
All new allotments must have legal access to a road. The route of a new road is
often determined by the need to provide access to new allotments which may be located
on peninsulas and promontories. This is assessed as part of the subdivision consent.
Part 12 has objectives and policies relating to access (clause 12.3.4) and assessment
criteria (clause 12.11.6). Whilst not specifically addressing roads located on peninsulas
and promontories, the objective is to ensure that access provided as part of subdivision
is designed and located to avoid adverse effects on natural character, landscape
values and amenity values:
12.3.4 Objective - access roads and tracks
To ensure that access provided as part of subdivision is designed and located
to avoid adverse effects on natural character, landscape values and amenity values.
Policies
- 1. By requiring access arrangements to integrate with the natural landform
wherever possible and minimise adverse ecological and visual effects.
- 2. By requiring the design and location of access to be defined at the
time of subdivision to preserve natural character and landscape values.
- 3. By restricting vehicle access to buildings to address potential adverse
effects of vehicle access on natural character and landscape values.
It is considered that together the objectives, policies, rules and assessment
criteria in these various parts of the plan can avoid adverse effects on the natural
character, landscape and amenity values in relation to peninsulas and promontories.
For the above reasons, it is recommended that submissions
3701/2
be rejected as it relates to changes to Part 5.
| Planner's recommendations about submissions
33/1,
33/2,
33/5,
33/6,
33/7,
33/8,
519/5,
519/6,
537/1,
306/5,
372/5,
564/5,
578/5,
581/5,
635/5,
640/5,
645/5,
654/5,
676/5,
704/5,
708/5,
728/5,
743/5,
870/5,
882/5,
907/5,
934/5,
941/26,
956/5,
1024/5,
1110/1,
1112/1,
1112/2,
1112/3,
1113/1,
1113/2,
1114/1,
1114/2,
1141/5,
1179/1,
1237/5,
1322/5,
1596/8,
1778/5,
1779/5,
1780/5,
1781/5,
1782/5,
1783/5,
1784/5,
1785/5,
1786/5,
1787/5,
1788/5,
1789/5,
1790/5,
1791/5,
1792/5,
2106/5,
2106/6,
2282/5,
2294/2,
2636/5,
2674/5,
2685/5,
2781/5,
2835/5,
2928/2,
2929/2,
2935/1,
2993/5,
3061/159,
3207/5,
3226/5,
3240/5,
3251/5,
3273/5,
3275/5,
3287/5,
3303/5,
3312/5,
3319/5,
3334/5,
3342/5,
3348/5,
3364/5,
3369/5,
3406/1,
3535/5,
3576/5,
3621/1,
3701/2,
3821/5,
That submission
33/2 be accepted and that rows 11, 12 and 20 of the activity table in clause
5.5.1 be amended to read:
(underline indicates additions, strikethroughs indicate deletions)
Row 11- Cell site Radio-communication and telecommunication
antennas located on existing pole structures
Row 12- Cell phone Radio-communication and telecommunication
(and broadcasting?) masts and attached antennas in commercial 5 and landform
3, 5 and 6
Row 20- Cell phone Radio-communication and telecommunication
(and broadcasting?) masts and attached antennas in rural 1
That submission
519/5
be accepted and that row 9 of the activity table in clause 5.5.1 be amended
to read:
( underline indicates additions)
Any aboveground telecommunication, electricity or wastewater network utility
that has an area not exceeding 2m2 in plan view and does not exceed 1.8m
1.6m
in height (exincluding plinth) provided that this rule excludes masts, vents
and antennas.
That submission
537/1 be accepted and that row 3 of the activity table in clause 5.5.1 be
amended to read:
( underline indicates additions)
Underground telecommunication, electricity, water and wastewater
network utilities
That submission
941/26(d) be accepted with no changes to the text
That submission
1110/1 be accepted with no changes to the text
That submissions
2106/5,
2106/6 be accepted and that rows 10 and 19 of the activity table in clause
5.5.1 be amended to read:
( underline indicates additions)
Up to two antennas attached to a building (excluding existing pole
structures)
Three or more antennas attached to a building (excluding existing pole
structures)
That submission
33/1 be accepted in part and that the following rules be provided for as
a permitted activity in the activity table in clause 5.5.1:
Aboveground telecommunication, electricity or wastewater network utility
in Island Residential 1 (traditional residential-except coastal amenity area)
and Settlement Area sub area-(Residential amenity area) that meets the following:
Maximum height: 1.8m
Maximum footprint of any single cabinet or structure: 1.4m2
Maximum footprint occupied by all cabinet or structure: 1.8m2
and
Aboveground telecommunication, electricity or wastewater network utility
in Landform 3 (alluvial flats), Landform 5 (productive land), Commercial 3 (local
shops), Commercial 6 (Quarry), Commercial 7 (Wharf), Settlement Area sub area-(Visitor
accommodation area, Claris light industry area, Mulberry Grove School and Okiwi
School and Domain areas) that meets the following:
Maximum height: 2m
Maximum footprint of any single cabinet or structure: 2.0m2
That submissions
33/5 and
941/26(e) relating to rural 1 be accepted in part and that row 17 of the
activity table in clause 5.5.1 be amended to read:
( underline indicates additions)
New overhead telecommunication and/or electricity distribution lines in
formed legal road adjoining landform 1-7 and rural 1 provided that for rural
1 this rule shall apply to formed legal roads existing at 18 September 2006.
That submission
1112/1 be accepted and
941/26(c) be accepted in part and that Row 9 of the activity table in clause
5.5.1 and any consequential amendments of the plan be amended to read:
Any aboveground telecommunication, electricity or wastewater network utility
within formed legal road reserve that has an area not exceeding of 2m2
in plan view, and does not exceed 1.6m 2.0m in height (exe inc
luding plinth) and is located adjacent to non-residential land units
provided that this rule excludes masts, vents and antennas."
And
a new activity be added to the activity table in clause 5.5.1 of the
plan and be provided as a permitted activity:
Any aboveground electricity or wastewater network utility within formed
legal road reserve that has an area not exceeding 1.8m2 in plan view, does not
exceed 1.8m in height (including plinth) and is located adjacent to residential
land units provided that this rule excludes masts and antennas.
That submission
1596/8
be accepted in a part with no changes to the text.
That submission
2935/1
be accepted in part and that the definition of 'road network' be amended to
include 'cycleways' as follows:
(underline indicates additions)
"1. Underground infrastructure located at or below the existing ground
surface. This includes any of the following:
a. The construction (including earthworks), operation and maintenance
of roads including associated footways, cycleways , foot bridges..."
"2. aboveground infrastructure located above the existing ground surface.
This includes any of the following:
a. The construction (including earthworks), operation and maintenance
of roads including associated footways, cycleways , foot bridges..."
|
4.11 Submissions about clause 5.6
4.11.1 Decisions requested
Submission
1156/1
requests:
The removal of clauses 5.6.2 to 5.6.4 and their replacement with community
mandated policies and rules.
Submission
2295/1
requests:
That objectives, policies and rules be developed in clause 5.6 for the enhancement
of public open space.
4.11.2 Planner's analysis and recommendations
4.11.2.1 Submission
1156/1
Clauses 5.6.2-5.6.4 are part of the development controls for network utility
services and relate to height, building in relation to boundary and yards.
The submission states that the sections do not promote sustainable management.
It is not clear what alternative methods the submitter would suggest to deal
with the provision of network utility services. It is considered that the controls
allow for a reasonable level of provision while recognising the amenity and characteristics
of the land unit in which they are located.
For the above reasons, it is recommended that submissions
1156/1
be rejected.
4.11.2.2 Submission
2295/1
This submission supports the intent of public open space and that objectives,
policies and rules in clause 5.6 be developed and included in the plan.
This submission is not supported. Public open space is not classified as a 'network
utility service' as defined in Part 14 of the plan. Part 5-Network utility services
is not the appropriate section of the plan to develop objective, policies and rules
for public open space. It is considered that the objectives and policies for Recreation
1 and 2 are a more appropriate place for managing public open space. Furthermore
submission
2295/3 addresses the issue of public open space.
For the above reasons, it is recommended that submission
2295/1
be rejected.
4.12 Submissions about clauses 5.6.2, 5.6.3 and 5.6.4
4.12.1 Decisions requested
Submission
33/9 requests:
Amend clause 5.6.2(2)(a) to allow for a zone height exceedence of 5m
in rural and business land units.
Submission
33/10 requests:
Amend clause 5.6.2.(2)(b) by removing reference to the "lowest
point of the roof line of the building".
Submission
33/11 requests:
Amend clause 5.6.2.(2) (height) to replace "cell site" and "cell phone"
masts and antennas with the more generic description of "radio-communication and
telecommunication" masts and antennas (or relief of similar effect).
Submission
941/28 requests:
Above ground telecommunication network infrastructure and aboveground electricity
network infrastructure be added to the list of exempt activities in clause 5.6.2(1).
Submission
941/29 requests:
Above ground telecommunication network infrastructure and aboveground electricity
network infrastructure be added to the list of exempt activities in clause 5.6.3(1).
Submission
941/30 requests:
Aboveground telecommunication network infrastructure and aboveground electricity
network infrastructure be added to the list of exempt activities in clause 5.6.4(1).
Submission
1110/2 requests:
Supports clause 5.6.2 (1) (b).
Submission
1110/3 requests:
Supports clause 5.6.3 (1) (b).
Submission
1110/4 requests:
Supports clause 5.6.4 (1) (b)
Submission
1115/1 requests:
Amend clause 5.6.2(2)(a) as follows (additions underlined and deletions in
strikethrough):
"A cell phone mast and attached antennas may exceed the height limit in commercial
5, landform3, 5 and 6; and rural 1 by a maximum of 3 5m."
Submission
1115/2 requests:
Amend clause 5.6.2(2)(b) as follows (additions underlined and deletions in
strikethrough):
"A cell site antenna attached to an existing building may exceed either the
maximum height for the land unit or settlement area or the lowest point of the roofline
of the building by a maximum of 2m, whichever is the lesser may be attached to
an existing building, provided it does not exceed the existing building height by
more than 3m at its point of attachment."
4.12.2 Planner's analysis and recommendations
4.12.2.1 Submission
33/9,
1115/1
Submission
33/9 seeks amendment as the proposed rules would allow a height limit for masts
and antennas to be 11m (8m+3m). The submitter considers this too restrictive. The
submitter accepts that this height limit would be acceptable in high amenity areas,
but considers a minimum height of 15m be allowed in rural and business land units.
The additional height is required to achieve technical objectives. The line of sight
principle is important so that sufficient height is allowed for to avoid blocking
by buildings, trees and topography.
In addition, submission
1115/1 also seeks the requirement of exceeding the land unit height limit by
5m for the above mentioned reasons.
Furthermore submission
1115/1 also seeks the addition of the rural 1 land unit in clause 5.6.2(2)(a).
This is linked with submission
1114/1 which has been addressed in clause 4.10.2.15 of this report.
Considering the scale of the landscape and buildings, a mast of 11m is likely
to not be dominant feature, with building height limits of typically 8m. However,
to raise the permitted height limit to 15m has the potential to allow for masts
that are of a scale that could be dominant features in any of the land units. Similarly,
to allow the height limit to be exceeded by 5m may need to a similar result. Finally,
the Rural 1 landscape is also known as 'rural amenity'. This name conveys the visual
sensitivity of this landscape, and any change that makes masts permitted in this
area will potentially result in adverse effects on the visual amenity values of
this land unit. For these reasons, these submissions are not supported.
Both submissions relate to clause 5.6.2(2)(b) of the plan. The district plan
controls relates to cell site antennas attached to existing buildings (excluding
masts). The rule allows that where a cell antenna is to be attached to an
existing building, it may exceed the maximum height for the land unit or settlement
area, or the lowest point of the roof line of the building by a maximum of 2m, whichever
is the lesser.
Submission
33/10 states that if the rule was in force then antennas would be limited to
below 8m as most buildings on the islands would be below 8m in height. This would
mean that a potential maximum height of 10m for all building mounted antennas (8m+2m).
Most of the maximum land unit heights in the plan are limited to 8m. The submitter
also states that the antennas should be mounted a sufficient height to meet the
radio frequency emission standards in Part 28 of the consolidated bylaw.
Submission
1115/2 also states that the antennas and support structures need to be higher
than the permissible height of buildings of the land unit in which they are located.
This is needed to ensure an effective transmission signal (due to building obstacles,
vegetation, topography) and health and safety issues associated with radio frequency
standards.
The submission is supported, due to the practical need for antennas to be higher
than the buildings to ensure an effective transmission signal. The dominance of
antennas on buildings would be controlled by the rule (see submission
33/6 above) limiting the number of antenna that can be attached to a building.
It is recommended that submissions
33/10 and
1115/2 be accepted in part and the rule be amended to allow the antenna to exceed
the highest point of the roof line by a maximum of 2m, rather than the lowest point
as originally proposed. The new rule would read:
A cell site antenna attached to an existing building may exceed either the
maximum height for the land unit or settlement area or the lowest highest
point of the roof line of the building by a maximum of 2m, whichever is the lesser.
4.12.2.3 Submission
33/11
The submission seeks the more generic description of 'radio-communication and
telecommunication' in lieu of 'cell site' and 'cell phone'. The submitter states
that other type of radiocommunication and telecommunication antennas are used and
are similar in scale and size e.g digital microwave radio links, customer multi
access radio. The submitter also states that a more generic reference to radio-communication
facilities is more appropriate.
This submission is supported. A generic term would cover more radio and telecommunication
antennas than simply 'cell site' and 'cell phone antennas'. The visual effects would
be similar for the antennas stated above. Radio frequency emissions would be controlled
by Part 28 of the bylaw.
That submission
33/11 be accepted and that clause 5.6.2(2) be amended to read
(underline indicates additions, strikethroughs indicate deletions)
a. A cell phone radio-communication and telecommunication mast and
attached antennas may exceed the height limit in commercial 5 and landforms 3, 5
and 6, by a maximum of 3m.
b. A cell site radio-communication and telecommunication antenna attached
to an existing building may exceed either the maximum height for the land unit or
settlement area or the lowest point of the roof line of the building by a maximum
of 2m, whichever is the lesser.
The comment below also addresses submissions
941/29 and
941/30 which addresses clause 5.6.3(1) and 5.6.4(1).
These submissions seeks that aboveground telecommunication and electricity infrastructure
be exempt from maximum height (clause 5.6.2(1)), building in relation to boundary
(clause 5.6.3(1)) and yards (clause 5.6.4(1)). The submitter supports the intent
of the development controls, particularly those which recognise the operational
requirements. However, the submitter also wishes that other aboveground telecommunication
and electricity infrastructure such as cabinets, transformers and substations should
also be exempt from the development control of the relevant land unit or settlement
area in which they are located.
These submissions are not supported. Clauses 5.6.2(1), 5.6.3(1) and 5.6.4(1)
lists streetlight poles, metrolight poles, telecommunication and electricity distribution
lines and poles as the infrastructure which is exempt from maximum height, building
in relation to boundary and yard controls. This is in recognition of the slimline
and linear nature of these types of infrastructure and the inappropriateness of
height, building in relation to boundary and yards applying to these types of infrastructure.
Conversely, cabinets, transformers, substations and the like infrastructure have
more 'bulk' and are more akin to a building. Therefore, the abovementioned development
controls would be appropriate in controlling the location and associated effects
of physical dominance, shadowing, admission of light to adjoining properties.
For the above reasons, it is recommended that submissions
941/28,
941/29,
941/30 be rejected.
The comment below also addresses submissions
1110/3 and
1110/4 which addresses clause 5.6.3(1)(b) and 5.6.4(1)(b).
These submissions support the provisions relating to metrolight poles in clauses
5.6.2(1)(b), 5.6.3(1)(b) and 5.6.4(1)(b).
Metrolight poles are seen as a means of installing the masts associated with
a cellular network in a manner that has acceptable effects on amenity values. The
metrolight poles have a similar appearance to street lights and for this reason,
they fit in well in the built environment. The height of the metrolight pole should
be in keeping with the height of the street lights in the immediate area.
The recently passed National Environmental Standards (NES) requires that the antennas
do not extend more than 30% or 3 metres, which ever is the lesser, above the highest
point of the existing structure prior to the addition of any equipment for telecommunications.
As streetlights and metrolight poles are often located near boundaries, they
will have difficulty complying with yard and recession plane requirements, which
are designed for structures that are of a greater bulk than a tall thin pole.
For these reasons, these submissions are supported.
| Planner's recommendations about submissions
33/9,
33/10,
33/11,
941/28,
941/29,
941/30,
1110/2,
1110/3,
1110/4,
1115/1,
1115/2
That submission
33/11 be accepted and that clause 5.6.2(2) be amended to read
(underline indicates additions, strikethroughs indicate deletions)
c. A cell phone radio-communication and telecommunication
mast and attached antennas may exceed the height limit in commercial 5 and landforms
3, 5 and 6, by a maximum of 3m.
d. A cell site radio-communication and telecommunication antenna
attached to an existing building may exceed either the maximum height for the
land unit or settlement area or the lowest point of the roof line of the building
by a maximum of 2m, whichever is the lesser.
That submissions
33/10,
1115/2 be accepted in part and that clause 5.6.2(2)(b) of the plan be amended
to read:
(underline indicates additions, strikethroughs indicate deletions)
A cell site radio-communication and telecommunication antenna attached
to an existing building may exceed either the maximum height for the land unit
or settlement area or the lowest highest point of the roof line of the
building by a maximum of 2m, whichever is the lesser.
That submissions
1110/2,
1110/3 and
1110/4 be accepted with no changes to the text.
That submissions
33/9,
1115/1,
941/28,
941/29,
941/30 be rejected.
|
4.13 Submissions about clauses 5.6.6
4.13.1 Decisions requested
Submission
941/31 requests:
Clause 5.6.6 be amended to read (or words to similar effect):
"Any building associated with network utility services must comply with the
ridgeline control applying in the land unit or settlement area in which it is located".
4.13.2 Planner's analysis and recommendations
4.13.2.1 Submission
941/31
This submission does not identify any changes to clause 5.6.6. At paragraph 2.44
of the submission, the submitter states that "Vector considers that Rule 5.6.6
does not adequately recognise the operational requirements of network utility operators,
and geographical constraints, which may, at times, require ridgelines to be traversed
."
It is expected that the submitter wanted some changes made to this rule but it
was not included in the relief requested. No doubt the submitter will rectify this
at the hearing. At this point, it is recommended that that the submission be rejected.
| Planner's recommendations about submission
941/31
That submission
941/31 be rejected.
|
4.14 Submissions about clauses 5.6.7
4.14.1 Decisions requested
Submission
941/32 requests:
Clause 5.6.7 be amended to read (or words to similar effect):
"Tree and vegetation removal
Any network utility service must comply with the indigenous vegetation controls
and any exotic tree protection controls applying in the land unit or settlement
area in which they are located , except that the actions of any person in carrying
out work which is authorised by statute or regulations (including the Electricity
Act 1992 and the Electricity (Hazards from Trees) Regulations 2003) are exempt from
this rule and such activities are permitted. In such circumstances, the person concerned
shall notify the Council in writing no later than 7 days prior to the work commencing
as to the reasons for the work. Refer to clause 10c.5.3 for rules about exotic
tree and indigenous vegetation protection on legal roads.
Notes:
1. Trimming of vegetation for network utility services is also controlled
by the Telecommunication Act 2001 and Electricity Regulations 2004".
4.14.2 Planner's analysis and recommendations
4.14.2.1 Submission
941/32
This submission is not supported. The submitter considers that it is unnecessarily
onerous and unreasonable to require network utility services to comply at all times
with the general tree protection controls and that operational requirements should
be taken into account.
The Council under the "Greening of the City Policy" seeks to protect the trees
that are currently growing throughout the city and encourage the planting of more
trees. Evidence of this is seen particularly in the streetscape where trees are
being planted in areas when footpaths are being upgraded and in streetscape of new
subdivisions.
The District Plan provides for general tree protection for indigenous trees above
3 metres in height or on Great Barrier greater than 6m in height for Kanuka. Protection
is also provided for exotic trees greater than 8m in height or with a girth greater
than 800mm. Prior to any work to be carried out on general protected trees a restricted
discretionary activity resource consent is required.
The above controls also apply to trees in legal road. However, some exclusion
is provided for the pruning of trees and vegetation located within the legal road
so that the management of these assets can be adequately provided for. The controls
are outlined in clause 10c.5.1-10c.5.3 of the plan.
The Electricity (Hazards from Trees) Regulations 2003 came into existence as
a response to a number of accidents occurring from people climbing trees and coming
in contact with live electricity lines.
The purpose of these regulations is to protect the security of the supply of
electricity, and the safety of the public, by
- prescribing distances from electrical conductors within which trees
must not encroach; and
- setting rules about who has responsibility for cutting or trimming
trees that encroach on electrical conductors; and
- assigning liability if those rules are breached; and
- providing an arbitration system to resolve disputes between works owners
and tree owners about the operation of these regulations.
Council has been advised that District Plan rules take legal precedence over
the Electricity(Hazards from Trees) Regulations 2003, and as a result resource consents
will be required before any trimming is undertaken of "scheduled" or "protected"trees
Section 330 RMA provides for emergency powers to be used given specific conditions
and the regulations provide for arbitration between the tree owner and the electricity
distribution utility where conflict is likely to emerge. However similar emergency
powers are accorded to the electricity utility company under the Electricity (Hazards
from Trees) Regulations 2003 section 14, and telecommunications utility under Section
132 Telecommunications Act 2001.
On balance it is considered that a resource consent should be required to trim
general protected trees in the gulf islands and that the general tree protection
rules should take precedence over the electricity and hazard regulations. This to
ensure that general protected trees contribute to the natural character and landscape,
ecological and amenity values of the islands and that a degree of control is maintained
by the council to ensure a good environmental outcome.
As previously stated, in the event of an emergency and within strict parameters,
emergency powers are afforded to utility companies under Section 330 of the RMA,
Electricity (Hazards from Trees) Regulations 2003 section 14,and section 132 of
the Telecommunications Act.
| Planner's recommendations about submission
941/32
That submission
941/32 be rejected.
|
4.15 Submissions about clauses 5.7.2, 5.7.5, and 5.8.1(p) with respect
to radio frequency emissions
4.15.1 Decisions requested
Submission
1108/1 requests:
Amend clause 5.7.2 to remove the reference to radio frequency fields from
the heading and to delete the third bullet point.
Submission
1108/2 requests:
Insert a new subsection 5.7.5 as follows
" Radio frequency emissions
All network utility services shall comply with NZS 2772.1:1999".
Submission
1108/3 requests:
Amend clause 5.8.1 to replace the reference to council's bylaw in criterion
P with reference to NZS2772.1:1999.
4.15.2 Planner's analysis and recommendations
These submissions relate to the council's reference to Part 28 of the consolidated
bylaw on radio frequency fields. The submitter contends that New Zealand Standard
2772.1:1999 is the appropriate standard when referring to standards for radio frequency
emissions and that the Ministry of Health and Ministry for the Environment have
prepared national guidelines.
The submitter further contends that the standard in the bylaw is arbitary and
not subject to scientific scrutiny or the public process under the RMA.
The standard is a conservative approach taken by the council and acknowledges
that it is more restrictive than the New Zealand standard proposed by the submitter.
However, the bylaw has provided no significant practical barriers to the industry
within Auckland City, suggesting that there is no reason the telecommunication industry
could not meet this requirement in all urban areas in New Zealand. The bylaw also
allows exemptions and exemptions have been sought and been granted in the past.
The standard is based upon scientific evidence and the above mentioned New Zealand
Standard and as previously stated above, the council adopted a conservative approach
as part of the bylaw review in 2002 thereby allowing a greater margin of safety.
In terms of public process, the radio frequency bylaw was reviewed in 2002 which
allowed participation by the public and their views to be considered. Section 684
of the Local Government Act 1974 and section 145 of the subsequent 2003 Local Government
Act permits the council to establish bylaws with respect to public health and safety.
The bylaws are currently being reviewed. It is intended to 'roll over' the existing
radio frequency bylaws and when the NES comes into force, the radio frequency bylaw
will be withdrawn.
As a result of the National Environmental Standards (NES) for radio frequency
fields it is recommended that submissions
941/28,
941/29,
941/30 be accepted.
| Planner's recommendations about submissions
1108/1,
1108/2,
1108/3
That submissions
1108/1,
1108/2,
1108/3 be accepted and that clause 5.7.2 be amended to read (underline indicates
additions, strikethroughs indicate deletions):
5.7.2 Signs, spill lighting and radio frequency fields
The Council's bylaws control the following:
- Signs located on network utility structures
- Spill lighting associated with network utility services on private property
Radio frequency fields emitted from commercial and amateur radios, television
transmitters and microwave links and cell phone repeaters sites.
And that a new subsection 5.7.5 be inserted as follows:
5.7.5 Radio Frequency Fields
An activity that generates radio frequency fields shall comply with the
National Environmental Standards (NES): New Zealand Standard (NZS2772.1:1999 Radio-frequency
Fields Part 1: Maximum Exposure Levels 3kHz-300GHz).
That clause 5.8.1 be amended to read:
P. Radio frequency fields
The extent to which the proposal complies with the National Environmental
Standard (NES): New Zealand Standard (NZS2772.1:1999 Radio-frequency fields Part
1: Maximum Exposure Levels 3kHz-300GHz) council's bylaw which controls radio
frequency emissions. |
4.16 Submissions about clauses 5.8.1
4.16.1 Decisions requested
Submission
941/33 requests:
The first restricted discretionary activity in the table at clause 5.8.1 be
amended to read:
"Any aboveground telecommunication, electricity or wastewater network utility
that has an area not exceeding of 2m2 6m² in plan view and does not
exceed 1.6m 1.75m in height (excluding plinth) provided that this rule excludes
masts and antennas".
Submission
941/34 requests:
Matter for discretion c. (clause 5.8.1) be amended as follows (or words to
similar effect):
"Whether landscaping and/or screening is practicable, and would effectively
mitigate visual and amenity effects so that the effects of the work are internalised
on the site and do not adversely affect adjacent properties, particularly residential
and open space uses".
Submission
941/35 requests:
Matter for discretion g.(clause 5.8.1) be amended to read (or words to similar
effect):
"Whether trees and other vegetation need to be removed for the construction
of the utility service. In particular, tree and vegetation removal should be kept
to a minimum and, where appropriate and practicable , screening and landscaping
should be undertaken to mitigate the effects of such removal".
Submission
941/36 requests:
Matter for discretion j. (clause 5.8.1) be amended to read (or words to similar
effect):
"Whether conditions are required to address the removal of redundant above
ground utility equipment or structures in the event that it is on the same alignment
or locality as the proposal. With respect to utility services in legal road, reference
should be made to the Code of Practice for Working in the Road".
Submission
941/37 requests:
Matter for discretion r. (clause 5.8.1) be amended as follows (or words to
similar effect):
"Whether it is necessary to locate services overhead, having regard to any
technical , practical, operational or financial constraints or ground conditions
that make placement underground unfeasible.
Whether the placement of overhead services would have any additional adverse
effects on the visual environment, amenity values or health and safety, having regard
to the level of adverse effects caused by existing network utility services in the
vicinity".
Submission
1109/1 requests:
Amend clause 5.8.1 by adding "where possible" at the start of assessment criterion
b.
Submission
1112/4 requests:
Amend row 1 in table 5.8.1 as follows (additions underlined and deletions
in strikethrough):
"Aboveground telecommunication, electricity or wastewater network utility
located within the legal road reserve that has an area exceeding 2m2 in plan
view and exceeds 1.6 1.8m in height (exe inc luding plinth) provided that
this rule excludes masts and antennas."
Submission
1113/3 requests:
Amend row 2 of table 5.8.1 as follows (additions underlined and deletions
in strikethrough):
" Three Six or more antennas attached to a building."
Submission
1114/3 requests:
Delete row 3 in table 5.8.1.
Submission
2294/1
requests:
Add the requirement at clause 5.8.1 That when works are carried out on a road
in the area of waterways or streams or culvert pipes that pass under the road, a
functional and ecologically suitable fish bypass is constructed and maintained at
the same time.
4.16.2 Planner's analysis and recommendations
4.16.2.1 Submission
941/33
This submission is a consequential amendment from submission
941/26(c) as discussed in clause 4.10.2.11 of this report. For the reasons outlined
in the aforementioned submission, this submission is not supported.
These submissions oppose assessment criteria c and g. Both assessment criteria
refer to the use of landscaping and/or screening. The submitter states that if trees
are used for screening and landscaping, there is a risk that the roots will grow
into underground cables and cause damage. This may cause health and safety issues
and be inconsistent with the requirements of the Electricity Regulations 2003. The
submitter also questions whether it is practicable for landscaping to be provided.
These submissions are not supported. Landscaping and screening are an effective
means of mitigation for large utility equipment, and can mitigate visual and amenity
effects. Trees do not necessarily have to be used for mitigation. Small shrubs and
fencing can be an alternative so there would be little risk of roots growing
into power cables. Furthermore, there are examples on the islands where landscaping
has been utilised effectively to screen large utility structures and equipment.
It is also considered that the assessment criteria would only apply to structures
and activities above the determined threshold (restricted discretionary/discretionary)
in the activity table in clause 5.5.1 and these structures/equipment will be assessed
on its merits. The use of the words "practicable," "where appropriate and practicable"
does not create certainty in what the council is trying to achieve.
In addition the islands' nature and character where there are substantial existing
trees, bush and shrubs can also help "screen" utility structures/equipment.
For the above reasons, it is recommended that submissions
941/34 and
941/35 be rejected.
4.16.2.3 Submission
941/36
The submission states that there are often considerable practical issues when
removing belowground structures and associated disturbance to the community. The
submitter further states that underground cables are only removed if a utility operator
requires space and that cables are removed at the same time as new equipment is
installed. Therefore the submitter does not consider that assessment criteria j-removal
of redundant services should apply to minor utility structures which are located
below ground.
This submission is not supported. The assessment criteria as currently worded
refers to all redundant services whether aboveground or underground and does not
just specifically refer to underground cables.
The assessment criteria is based on the occupation of road reserve space, where
space can be at a premium. It is acknowledged that such matters may not be so relevant
on the islands where there may be more road space available to convey utility services.
It has generally been agreed that whenever an area has been opened and services
have been identified as obsolete then they should be removed at that time. It should
also be acknowledged that some redundant services may be able to be reused by other
service providers.
4.16.2.4 Submission
941/37
The submission states that assessment criteria does not recognise that network
utilities can face practical, operational and financial (as well as technical) constraints.
This submission is not supported. It is acknowledged that network utilities can
face the constraints as outlined in the submission. However, many other projects
outside of network utility infrastructure also face these constraints. "Practical"
constraints can encompass any situation and it is recognised that operational and
financial constraints are not matters considered within the RMA context in terms
of addressing the need to place underground cables and its effect on the visual
environment, amenity values, and health and safety.
4.16.2.5 Submission
1109/1
This submission states that the plan should recognise that it is not always possible
to locate antennas away from the primary building façade and located in such a way
so as to visually integrate with the building. This is due to the variable design
of buildings and the need to comply with radio frequency standards.
The submission is supported in part. The assessment criteria is to ensure that
utility equipment do not dominate the building or site in which they are located
or are placed in a manner that is subservient to other built elements on the site.
With particular reference to antennas it is recognised that it is important for
antennas to receive and transmit signals. However, they should be placed in a manner
which does not dominate and is subservient to the building façade where they can
be highly visible from the street. Therefore, if antennas are placed above the roofline
they should be located away from the primary building façade thereby minimising
visual effects.
4.16.2.6 Submission
1112/4
This submission is a consequential amendment from submission
1112/3 as discussed in clause 4.10.2.14 of this report. For the reasons outlined
in the aforementioned submission, this submission is not supported.
4.16.2.7 Submission
1113/3
This submission is a consequential amendment from submission
1113/2 as discussed in clause 4.10.2.4 of this report. For the reasons outlined
in the aforementioned submission, this submission is not supported.
4.16.2.8 Submission
1114/3
This submission is a consequential amendment from submission
1114/2 as discussed in clause 4.10.2.15 of this report. For the reasons outlined
in the aforementioned submission, this submission is not supported.
4.16.2.9 Submission
2294/1
This submission is a consequential amendment from submission
2294/2
as discussed in clause 4.2.2.5 of this report. For the reasons outlined in the aforementioned
submission, this submission is not supported.
| Planner's recommendations about submissions
941/33,
941/34,
941/35,
941/36,
941/37,
1109/1,
1112/4,
1113/3,
1114/3,
2294/1
That submissions
1109/1 be accepted in part and that clause 5.8.1 b. Site layout and placement,
be amended to read:
(underline indicates additions, strikethroughs indicate deletions)
" Where antennas are located above the roofline they
Antennas on
buildings should be located away from the primary building façade..."
That submissions
941/33,
941/34,
941/35,
941/36,
941/37,
1112/4,
1113/3,
1114/3,
2294/1
be rejected.
|
5.0 Conclusion
This report has considered the decisions requested in submissions lodged regarding
network utility services of the Proposed Auckland City District Plan: Hauraki Gulf
Islands Section 2006.
The report recommends whether submissions should be accepted or rejected and
how associated further submissions should be dealt with, and how the Plan should
be modified as a result. These recommendations are made prior to the hearing of
submissions and therefore without the benefit of evidence which may be presented
at that time. At this stage before the hearing, it is recommended that this part
of the Plan be approved, with amendments (as outlined in appendix 3), for
the reasons outlined in this report.
| |
Name and title of signatories |
Signature |
| Author |
Bruce Young, Senior Planner |
|
| Reviewer |
Megan Tyler, Manager: Islands |
|
| Approver |
Penny Pirrit, Manager: City Planning |
|
Appendix 1
List of submissions and further submissions
Appendix 2
Summary of submissions
Appendix 3
Recommended changes to the Plan
Appendix 4
Landscape report