District Plan Hauraki Gulf Islands Section - Proposed 2006
(Notified version 2006)
Street index |
Planning maps |
Text |
Appendices |
Annexures |
Section 32 material |
Plan modifications |
Help |
Notified - Home |
Decision - Home
Hearing reports index
Report on
submissions to the Auckland City District Plan: Hauraki Gulf Islands
Section - Proposed 2006
| Topic: |
Natural hazards
|
| Report to: |
The Hearing
Panel |
| Author: |
Colin Craig |
| Date: |
22 January 2008 |
| Group file: |
314/274011 |
1.0 Introduction
This report
considers submissions and further submissions ('submissions') that were
received by the council in relation to part 8 (natural hazards) of the
Auckland City District Plan: Hauraki Gulf Islands Section - Proposed 2006
('the Plan'). The Plan was publicly notified on 18 September 2006. The
closing date for lodging submissions was 11 December 2006. The submissions
were publicly notified for further submission on 29 April 2007. The closing
date for lodging further submissions was 28 May 2007.
This report
has been prepared under section 42A of the Resource Management Act 1991 ('the
RMA'), to assist the hearings panel to consider the submissions on natural
hazards. This report discusses the submissions (grouped by subject matter or
individually) and includes recommendations from the planner who prepared this
report. The recommendations identify whether each submission should be
accepted or rejected (in full or in part) and what amendments (if any) should
be made to the Plan to address matters raised in submissions. Further
submissions are dealt with in conjunction with the submissions to which they
relate.
The
recommendations contained in this report are not decisions of the council.
The council will issue its decisions following consideration of the
submissions, further submissions, any supporting evidence presented at the
hearing, and this report. The council's decisions will be released after all
the hearings to the Plan have been completed.
2.0 Statutory framework
2.1
General statutory framework
This
section of the report briefly sets out the statutory framework within which
the council must consider the submissions. In preparing this report the
submissions and, in particular, the decisions requested in the submissions,
have been considered in light of the relevant statutory matters. These were
summarised by the Environment Court in Eldamos Investments Limited v
Gisborne District Council W047/05 where the court set out the following
measures for evaluating objectives, policies, rules and other methods in
district plans:
-
The objectives of the Plan are to be evaluated by the extent to which they:
-
Are the most appropriate way to achieve the purpose of the RMA (s32(3)(a));
and
-
Assist the council to carry out its functions in order to achieve the purpose
of the RMA (s72); and
-
Are in accordance with the provisions of part 2 of the RMA (s74(1).
-
The policies, rules, or other methods in the Plan are to be evaluated by the
extent to which they:
-
Are the most appropriate way to achieve the objectives of the Plan
(s32(3)(b)); and
-
Assist the council to carry out its functions in order to achieve the purpose
of the RMA (s72); and
-
Are in accordance with the provisions of part 2 of the RMA (s74(1)); and
-
(If a rule) achieve the objectives and policies of the Plan (s76(1)(b)).
The purpose
of the RMA is "to promote the sustainable management of natural and physical
resources", and "sustainable management" is defined in section 5(2) as
meaning:
"...
managing the use, development, and protection of natural and physical
resources in a way, or at a rate, which enables people and communities to
provide for their social, economic, and cultural wellbeing and for their
health and safety while—
- Sustaining the potential of natural and physical resources (excluding
minerals) to meet the reasonably foreseeable needs of future generations; and
- Safeguarding the life-supporting capacity of air, water, soil, and
ecosystems; and
- Avoiding, remedying, or mitigating any adverse effects of activities
on the environment."
Along with
section 5, part 2 of the RMA includes sections 6 (matters of national
importance), 7 (other matters) and 8 (Treaty of Waitangi), which set out a
range of matters that the council needs to recognise and provide for in
achieving the purpose of the RMA. Those matters are also relevant when
considering submissions.
The Plan
must assist the council to carry out its functions under section 31 of the
RMA. These functions are:
"(a) The establishment, implementation, and review of objectives, policies,
and methods to achieve integrated management of the effects of the use,
development, or protection of land and associated natural and physical
resources of the district:
(b) the control of any actual or potential effects of the use,
development, or protection of land, including for the purpose of—
(i) the avoidance or mitigation of natural hazards; and
(ii) the prevention or mitigation of any adverse effects of the storage,
use, disposal, or transportation of hazardous substances; and
(iia) the prevention or mitigation of any adverse effects of the
development, subdivision, or use of contaminated land:
(iii) the maintenance of indigenous biological diversity:
(c) ...
(d) The control of the emission of noise and the mitigation of the effects
of noise:
(e) The control of any actual or potential effects of activities in
relation to the surface of water in rivers and lakes."
In addition
to the matters listed above from the Eldamos decision:
-
The Plan must "give effect to" any national policy statement and any New
Zealand coastal policy statement (s75(3)(a) and (b)).
-
The Plan must "give effect to" the regional policy statement (made operative
after 10 August 2005) (s75(3)(c)).
-
The Plan must be "not inconsistent with" any regional plan (s75(4)).
-
The council must ensure that that the Plan does not conflict with sections 7
and 8 of the Hauraki Gulf Marine Park Act 2000 ("the HGMPA"). Section 10 of
the HGMPA requires that sections 7 and 8 of that Act be treated as a New
Zealand coastal policy statement under the RMA.
2.2 Specific statutory requirements for natural hazards.
As noted
above, section 31 of the Resource Management Act (RMA) lists that one of the
functions of territorial authorities is:
the control of any actual or potential effects of the use, development, or
protection of land, including for the purpose of—
- the avoidance or mitigation of natural hazards
Section 7
of the RMA also requires territorial authorities and others exercising
functions and powers under the RMA to have particular regard to the effects of
climate change.
The RMA
deals with the sustainable management of natural and physical resources
including avoiding, remedying, or mitigating any adverse effects on the
environment, whilst the Building Act regulates building work, to ensure
buildings are safe and sanitary.
Section 71
of the Building Act 2004 requires building consent authorities (territorial
local authorities) to refuse to grant a building consent for the construction
of a building or major alterations to a building if :
- the land on
which the building work is to be carried out is subject to or is likely to be
subject to 1 or more natural hazards ; or
- the
building work is likely to accelerate, worsen, or result in a natural hazard
on that land or property.
Section 71
defines natural hazards as :
- erosion
(including coastal erosion, bank erosion and sheet erosion);
- falling
debris (including soil, rock, snow and ice);
- subsidence;
- inundation
(including flooding, overland flow, storm surge, tidal effects and ponding);
and
- slippage.
Section 72
of the Building Act 2004 requires a building consent authority to grant a
building consent on land subject to, or likely to be subject to 1 or more
natural hazards if the authority considers that the building work proposed
will not accelerate, worsen or result in a natural hazard on the land on which
the work will be carried out, or on any other property. The authority must
also consider it reasonable to grant a waiver or modification of the building
code in respect of the natural hazard concerned.
Section 73
requires that if a building consent is issued under section 72, the building
consent authority must notify the Registrar-General of Land identifying the
natural hazard concerned and provide a project information memorandum (PIM)
that relates to the building consent in question.
Section 35
of the Building Act addresses the content of PIMs which must include
information likely to be relevant to proposed building work including any
special feature of the land concerned. Special features are potential natural
hazards or the likely presence of hazardous contaminants that are likely to be
relevant to the design and construction or alteration of a building, that are
known to the territorial authority and are not apparent from the district
plan. In this case, Council has chosen to show the hazards known to it at the
time the plan was notified, on the district plan maps.
Clause
E1.3.2 of the First Schedule of the Building Regulations states that surface
water (flowing from a drain, river or stream) resulting from a storm having a
2 percent probability of occurring annually (a 1 in 50 year storm) shall not
enter housing, communal residential and communal non residential buildings.
Clause E1 does not however specifically protect commercial or industrial
buildings to the same extent but these buildings remain protected by section
71.
Natural
hazard identification is also an important function of the "open government"
of local authorities irrespective of the requirements of the RMA or the
Building Act and Regulations. Section 44A of the Local Government Official
Information and Meetings Act 1987 allows a person to apply to a local
authority for a land information memorandum (LIM) in relation to matters
affecting any land in the district of the authority. The matters to be
included in the memorandum include information identifying each special
feature or characteristic of the land including erosion, avulsion, falling
debris, subsidence, slippage, alluvion, or inundation. LIMs are typically
applied for by people wishing to purchase a property.
3.0 Background
This
section of the report sets out background information about the topic under
consideration. It identifies how the Plan deals with natural hazards.
Natural
hazards are any atmospheric or earth or water related occurrence (including
earthquake, tsunami, erosion, volcanic and geothermal activity, landslip,
subsidence, sedimentation, wind, drought, fire or flooding) the action of
which adversely affects or may adversely affect human life, property or other
aspects of the environment.
The issue
for Auckland City Council is how to manage and respond to irregular or
periodic exposure to such events. The frequency and magnitude of these events
will vary and their effects on the environment, including people, property and
infrastructure will vary as a result. Many natural hazards are difficult to
predict, in terms of their possible location, frequency, magnitude and
consequences.
Part 8 of
the proposed Plan deals with natural hazards. Reliable information on natural
hazard areas known to the Council when the plan was notified are identified on
the inner islands planning maps. These natural hazard areas are flood prone
areas (types A and B), soil warning areas and soil register areas (where
council holds a geotechnical report on the site), and erosion risk zones.
Because of a lack of reliable information for the outer islands there are no
natural hazard areas identified on the outer islands planning maps. In
developing the rules in part 8, a precautionary approach has been taken to
ensure that activities are not located in areas likely to be subject to
natural hazard events, in the absence of information known to Council and/or
shown on the planning maps.
The rules
in part 8 :
- prevent
activities such as vegetation removal or modification of areas where that
removal or modification may contribute to or accelerate erosion e.g. removal
of vegetation on steep slopes or near stream, the removal or modification of
sand dunes;
- prevent
activities in areas likely to affected by flooding or erosion including
coastal erosion and /or slippage;
- prevent the
use of materials or structures above mean high water springs that may serve as
a defence against coastal erosion.
4.0 Analysis of submissions
4.1
Introduction
This
section of the report discusses the decisions requested in submissions about
natural hazards and recommends how the panel could respond to the matters
raised and decisions requested in submissions. The submissions are addressed
under subject headings. While the relevant statutory matters (identified in
section 2.0 of this report) will not necessarily be referred to directly, the
discussion and recommendations have given appropriate consideration to these
and any other relevant matters.
A list of
the submissions which raise issues about part 8 (natural hazards) together
with the related further submissions is contained in appendix 1.
Appendix 2 contains copies of the summary of submissions. Any amendments
to the Plan recommended in response to submissions are identified in this
section of the report and are further detailed in appendix 3.
The list of
submissions contained in appendix 1 may include some submissions and further
submissions which were received 'late', ie they were received after the
closing date for lodging submissions (11 December 2006) or further submissions
(28 May 2007). All late submissions related to this part of the plan have
been accepted by the council as provided for under sections 37 and 37A of the
RMA.
4.2
Submissions about seawall remediation and other techniques.
Submissions
dealt with in this section:
86/2,
293/2, 360/2,
622/2,
623/2,
624/2,
625/2, 720/2,
755/2, 756/2,
757/2, 758/2,
759/2, 760/2,
761/2, 762/2,
763/2, 764/2,
765/2,
766/2, 767/2,
768/2, 769/2,
795/2, 838/2,
846/2, 847/2,
848/2, 860/2,
1124/2, 1188/2,
1189/2, 1212/2,
1213/2, 1222/2,
1246/2, 2051/2,
2052/2, 2059/2,
2090/2, 2548/2,
2565/2, 2590/2,
2627/2,
2629/2, 2698/2,
3027/2, 3555/2,
3606/2.
4.2.1
Decisions requested
The above submitters
request that Council should "provide a toolkit based on the RMA principles of
avoid, remedy and mitigate in relation to risk, which includes (without
limitation), regulation, good practice guides, stormwater management measures,
reference to and consistency with provisions of other statutes, enabling sea
wall remediation proposals and other appropriate techniques. The basis for
this toolkit is contained in the Tonkin and Taylor 2004 report relating to
coastal hazard assessment."
4.2.2 Planner's analysis and recommendations
Council is
providing a toolkit of objectives, policies and rules in part 8 so that the
effects of natural hazards are avoided, remedied or mitigated. The Building
Act 2004, PIMs issued under the Building Act, the Building Code (Building
Regulations) and LIMs issued under the Local Government Official Information
and Meetings Act 1987, also provide other regulatory means to prevent
buildings from being constructed in areas likely to be subject to natural
hazards.
With
reference to stormwater management techniques (for Kennedy Point where most
submitters have property interests) the Council has undertaken to give
particular attention to the proper management of the stormwater flow from the
roading system, will allow access to Council reserve land to undertake
remedial works to the cliff edge, and will share information on suggested
property management approaches.
With
regards to seawall remediation proposals for Kennedy Point properties, it is
likely that any seawall built will have to be placed below mean high water
springs and will require a resource consent from the Auckland Regional Council
(ARC) under the Regional Coastal Plan. Auckland City is not likely to oppose
any reasonable application by Kennedy Point residents to the ARC.
The Tonkin
and Taylor report is addressed more fully in section 4.3.2 below, but council
has provided a toolkit to address problems on Kennedy Point
Planner's
recommendations about submissions relating to seawall remediation and other
techniques:
| That
submissions
86/2, 293/2,
360/2, 622/2,
623/2,
624/2,
625/2, 720/2,
755/2, 756/2,
757/2,
758/2, 759/2,
760/2, 761/2,
762/2, 763/2,
764/2,
765/2,
766/2, 767/2,
768/2,
769/2, 795/2,
838/2, 846/2,
847/2,
848/2, 860/2,
1124/2, 1188/2,
1189/2,
1212/2, 1213/2,
1222/2, 1246/2,
2051/2, 2052/2,
2059/2, 2090/2,
2548/2,
2565/2, 2590/2,
2627/2, 2629/2,
2698/2, 3027/2,
3555/2,
3606/2
be accepted in part. |
4.3
Submissions about reducing the hazard notification on Kennedy Point to
a 50 year time frame.
Submissions dealt with in this section:
(1)
720/1, 755/3,
756/3, 757/3,
758/3, 760/3,
765/3,
767/3, 769/3,
846/3, 1124/3,
1188/3, 1212/3,
1213/3, 1222/3,
1246/3, 2059/3,
2590/3, 2627/3,
2629/3, 3555/3.
(2) 86/3, 293/3,
622/3, 623/3,
624/3,
625/3,
720/1,
720/3, 759/3,
761/3, 763/3,
764/3, 765/3,
766/3, 768/3,
795/3, 762/3,
838/3, 847/3,
848/3, 860/3,
1189/3
4.3.1
Decisions requested
- (1) Reduce the hazard notifications on Esslin Road, Donald Bruce Road and
Kennedy Point, so that they only affect private property where there is clear
evidence that the land will be adversely affected within a 50 year time frame.
- (2) Reduce the hazard
notifications on Kennedy Point, so that they only affect private property
where there is clear evidence that the land will be adversely affected within
a 50-year time frame.
4.3.2
Planner's analysis and recommendations
After a
number of residents raised concerns in November of 2002 about the erosion
occurring along the Huruhi Bay esplanade reserve, Auckland City Council and
Auckland Regional Council engaged Tonkin and Taylor to produce a hazard
assessment report. In April 2004, the Eastern Huruhi Bay Coastal Hazard
Assessment report was produced. The assessment by Tonkin and Taylor
identified that there is a significant erosion risk to both the esplanade
reserve around the peninsular and to the properties that back onto the
reserve. The assessment determined that the primary cause is the inherent
defects in the cliff geology, which means the cliff is generally weak in terms
of its material strength and therefore more susceptible to slips and on going
erosion.
The April
2004 report identified 3 different erosion risk classification zones and a
year 2100 erosion risk zone line, which affected most properties on the
western side of Kennedy Point. In zone 1 areas, the cliff material is
believed to be erosion resistant and located at headlands. The cliff material
in zones 2 and 3 is more weathered and has a higher erosion risk (see
figure H1 attached from Tonkin and Taylor report). The estimated rate of
change by Tonkin and Taylor was:
Zone 1:
Less than 1 metre / 100 years
Zone 2: 1 -
5 metres / 100 years
Zone 3: 5 -
10 metres / 100 years
A revised
version of the Tonkin and Taylor report produced in June 2004 included both a
year 2050 erosion risk line and a year 2100 erosion risk line. On most
properties on the western side of Kennedy Point, there is little significant
difference between the two lines.
In July
2004, it was agreed to extend the hazard assessment to include the shoreline
area between the southern end of Takirau Bay to the Kennedy Point boat ramp
Affected
property owners were written to in October 2004. In response, some residents
raised concerns that the 2050 and 2100 erosion risk zone lines shown on figure
7.2 of the Tonkin and Taylor report, which skirt the front of some properties
and bisect or run behind houses on other properties were not consistent with
the broad-brush assessment or precautionary estimate of the report. As a
consequence of these issues, and the potential uncertainty of erosion effects
on individual properties, it was decided to identify all properties at risk
within an erosion risk zone on the planning maps, without showing the detailed
risk to individual properties.
After a
meeting between Council officers and a residents group, an amended Tonkin and
Taylor report was produced dated November 2004. This deleted the 10 metre
safety margin from the line of influence they showed for the 2050 and 2100
erosion risk zone lines (see figure 7.1 from Tonkin and Taylor report
attached). Whilst the resulting 2050 line was moved seaward the line was
still within the front boundaries of most properties (especially those in the
southern half) of the Kennedy Point peninsular.
Later
correspondence with the Council by two members of the residents group
requested the removal of the erosion risk zone lines and a simple
identification of those properties which were touched by those lines. Hence
the identification of the erosion risk zone in the planning maps for Kennedy
Point is based on both the 2050 and 2100 erosion risk lines from the November
2004 Tonkin and Taylor report, but the planning maps do not show those lines,
and only identify those properties the Council believes could be affected by
coastal erosion in the next 50-100 years. As there is very little difference
between these two lines, and as some residents have noted, it is difficult to
determine the exact risk to individual properties over a 50-100 year time
frame, the hazard notifications for Kennedy Point should not be altered.
| Planner's
recommendations about submissions seeking a reduction of the hazard
notification on Kennedy Point to a 50 year time frame : That
submissions
720/1, 755/3,
756/3, 757/3,
758/3, 760/3,
765/3,
767/3, 769/3,
846/3, 1124/3,
1188/3, 1212/3,
1213/3, 1222/3,
1246/3, 2059/3,
2590/3, 2627/3,
2629/3,
3555/3 be rejected.
That
submissions
86/3, 293/3,
622/3, 623/3,
624/3,
625/3, 720/1,
720/3, 759/3,
761/3, 763/3,
764/3,
765/3,
766/3, 768/3,
795/3, 762/3,
838/3, 847/3,
848/3, 860/3,
1189/3 be rejected.
|
4.4 Submissions seeking the removal of the various hazard
notations relating to Kennedy Point.
Submissions
dealt with in this section:
(1) 86/1, 293/1,
325/1, 360/1, 622/1, 623/1, 624/1, 625/1, 759/1, 761/1, 762/1, 763/1, 764/1, 765/1, 766/1, 768/1, 795/1, 838/1, 847/1, 848/1, 860/1, 1189/1, 2051/1, 2052/1, 2090/1, 2548/1, 2565/1, 2698/1, 3027/1, 3606/1,
(2) 755/1, 756/1, 757/1, 758/1, 760/1, 767/1, 769/1, 846/1, 1124/1, 1188/1, 1212/1, 1213/1, 1222/1, 1246/1, 2059/1, 2590/1, 2627/1, 2629/1, 3555/1
4.4.1
Decisions requested
- Remove the
various hazard notations relating to Kennedy Point and in particular the
submitter's land.
- Remove the
various hazard notations relating to Esslin Road, Donald Bruce Road and
Kennedy Point and in particular the submitter's land.
4.4.2 Planner's analysis and recommendations
The
submissions seek either the removal of the various hazard notification
relating to Kennedy Point and in particular the submitters' land or the
decisions from council outlined in sections 4.2, 4.3, 4.6, 4.7, 4.8, 4.9 and
4.10 of this report. It would be inappropriate for council to remove the
hazard notifications for Kennedy Point or any other individual pieces of land,
if the council is reasonably confident that the land is hazard prone. To do
so would be contrary to Council's requirements under section 31 of the RMA and
section 44A of the Local Government Official Information and Meeting Act
1987.
| Planner's
recommendations about submissions seeking the removal of the various hazard
notations relating to Kennedy Point and in particular the submitter's land .
That
submissions 86/1, 293/1, 325/1, 360/1, 622/1, 623/1, 624/1, 625/1, 759/1,
761/1, 762/1, 763/1, 764/1, 765/1, 766/1, 768/1, 795/1, 838/1, 847/1, 848/1, 860/1, 1189/1, 2051/1, 2052/1, 2090/1, 2548/1, 2565/1, 2698/1, 3027/1, 3606/1
and 755/1, 756/1, 757/1, 758/1, 760/1, 767/1, 769/1, 846/1, 1124/1, 1188/1, 1212/1, 1213/1, 1222/1, 1246/1, 2059/1, 2590/1, 2627/1, 2629/1, 3555/1
be rejected.
|
4.5 Submissions seeking the removal of erosion risk zones
relating to Esslin Road, Donald Bruce
Road and Kennedy Point.
Submissions
dealt with in this section:
360/9, 2720/1, 2227/1
4.5.1
Decisions requested
That the Council
remove the Erosion Risk Zone relating to Esslin Road, Donald Bruce Road and
Kennedy Point or apply the Erosion Risk Zone designation to all properties
along the coastline of Waiheke, taking account not only of possible erosion
but also of predicted rising sea levels (2227/1).
That the shaded area
for 10 Kennedy Point Road (erosion risk area) be removed (360/9).
Expresses concern of
putting coastal erosion conditions onto 35 Kennedy Point Road, which is not
waterfront (2720/1).
4.5.2
Planner's analysis and recommendations
Because of
Council's obligations under section 31 of the RMA it would not be responsible
of Council to remove the erosion risk zone relating to Esslin Road, Donald
Bruce Rd or Kennedy Point. Even if the erosion risk zone was removed Council
will be obliged to include information on the risk of erosion for the same
properties within land information memorandums, and project information
memorandums issued with building consent applications.
Because of
previous work undertaken which identified that Onetangi Beach was the most at
risk beach on Waiheke Island, Onetangi Beach is also identified on the
planning maps as a erosion risk area, following the study of the beach in 2002
by Tonkin and Taylor. It is not however appropriate as suggested to apply a
erosion risk classification to all properties along the coastline of Waiheke
because many coastal areas will not be significantly affected by coastal
erosion or by predicted sea level rises due to topography, geology, location
etc. Because of budgetary constraints, it has not been possible to undertake
a comprehensive study of coastal erosion across the whole of the Waiheke or
Great Barrier Islands. The Council will however continue to investigate the
most at risk areas when money becomes available.
The rules
in part 8.6.1 take a precautionary approach and will provide protection to
coastal properties by keeping activities at distances and elevations where
they are not likely to be effected by a natural hazard event i.e. :
- within 20
metres of coastal cliffs with a slope angle steeper than 180,
- at an
elevation less than 3 metres above mean high water springs (MHWS) if the
activity is within 20m of mean high water springs, or
- at an
elevation less than 2 metres above MHWS if the activity is more than 20 metres
from mean high water springs.
With
regards to 10 Kennedy Point Rd, the November 2004 report by Tonkin and Taylor
on Kennedy Point shows that the 2050 and 2100 erosion risk line affects about
one-third of the property. In the case of 35 Kennedy Point Road, whilst the
planning maps, because of their scale appear to include the right of way from
the property to the coastal reserve, at a larger scale (on council's
geographical information service database) it can be seen that this right of
way is not included and 35 Kennedy Point Rd is not within the erosion risk
zone. The Tonkin and Taylor report confirms that the erosion risk lines are
close to, but do not affect, the right of way that 35 Kennedy Point Road has
to the coastal reserve.
| Planner's
recommendations about submissions seeking the removal of the erosion risk zone
from Esslin Road, Donald Bruce Road and Kennedy Point or the application of
the zone to all coastal properties on Waiheke:
That
submissions 360/9 and 2227/1
be rejected.
That
submission 2720/1
be accepted with no change to the text or maps because the erosion risk zone
notation does not affect 35 Kennedy Point Road
|
4.6 Submissions about amendments to the hazard notification
at Kennedy Point.
Submissions
dealt with in this section:
Group 1: 86/4, 293/4, 360/4, 622/4, 623/4, 624/4, 625/4, 759/4, 761/4, 762/4, 763/4,
764/4,
765/4, 766/4, 768/4, 795/4, 838/4, 847/4, 848/4, 860/4, 2051/4, 2052/4,
2090/4, 2548/4, 2565/4, 2698/4, 3027/4, 3606/4.
Group 2:
755/4,
756/4, 757/4, 758/4, 760/4, 767/4, 769/4, 846/4, 1124/4, 1188/4, 1212/4,
1213/4, 1222/4, 1246/4, 2059/4, 2590/4, 2627/4, 2629/4, 3555/4.
4.6.1 Decisions requested
Group 1:
Make consequential amendments to the proposal (with specific reference to the
hazard notifications at Kennedy Point), which better reflect the relationship
between the level of risk and range of RMA and other techniques necessary to
avoid , remedy and mitigate this risk.
Group 2: Make
consequential amendments to the proposal (with specific reference to the
hazard notifications at Esslin Road, Donald Bruce Road and Kennedy Point)
which better reflect the relationship between the level of risk and range of
RMA and other techniques necessary to avoid, remedy and mitigate this risk
4.6.2
Planner's analysis and recommendations
It is
unclear from these submissions what specific changes to the Plan that the
submitters request. The provisions of Part 8 seek to avoid the risk of a
natural hazard adversely affecting properties and activities on Esslin Road,
Donald Bruce Road and on Kennedy Point. It would be helpful if submitters
attend the hearing and provide specific examples to the panel to support their
submissions.
| Planner's
recommendations about submissions seeking amendments to the hazard
notifications at Kennedy Point. That
submissions 86/4, 293/4, 360/4, 622/4, 623/4, 624/4, 625/4, 759/4, 761/4, 762/4, 763/4,
764/4, 765/4, 766/4, 768/4, 795/4, 838/4, 847/4, 848/4, 860/4, 2051/4, 2052/4,
2090/4, 2548/4, 2565/4, 2698/4, 3027/4, 3606/4
be rejected.
That
submissions
755/4, 756/4, 757/4, 758/4, 760/4, 767/4, 769/4, 846/4, 1124/4, 1188/4,
1212/4, 1213/4, 1222/4, 1246/4, 2059/4, 2590/4, 2627/4, 2629/4, 3555/4
be rejected.
|
4.7 Submissions about reconciling competing Council policy
decisions on the role of seawalls
Submissions
dealt with in this section:
86/5, 293/5, 360/5,
606/5, 622/5, 623/5, 624/5, 625/5, 755/5, 756/5, 757/5, 758/5, 759/5, 760/5,
761/5, 762/5, 763/5, 764/5, 765/5, 766/5, 767/5, 768/5, 769/5, 795/5, 838/5,
846/5, 847/5, 848/5, 860/5, 1124/5, 1188/5,
1189/5, 1212/5, 1213/5, 1222/5,
1246/5, 2051/5, 2052/5, 2059/5, 2090/5, 2548/5, 2565/5, 2590/5, 2627/5,
2629/5, 2698/5, 3027/5, 3555/5
4.7.1 Decisions requested
Reconcile the
competing council policy positions on the role of seawalls by adopting the
recommendations of the Tonkin and Taylor report 2004 (relating to coastal
hazard assessment), noting that these have been successfully put in place
elsewhere by the council both historically and recently e.g. at Kohimarama
Beach
4.7.2 Planner's analysis and recommendations
It is
unclear what the competing council policy positions are with regards to
seawalls. The Tonkin and Taylor (T&T) report notes that "due to the cliff
structure and the erosion mechanisms, the range of hard engineering solutions
is practically limited to seawalls and revetments (facing of stone,
concrete) to protect against long-term shoreline retreat. Seawalls or
revetments can provide protection by reducing the toe erosion of the cliff
line. However, increasing hard structures in the coastal environment needs to
be carefully considered with any policy contained in the RMA, PRP:C (proposed
Regional Plan : Coastal) and NZCPS (New Zealand Coastal Policy Statement)."
It states in a later paragraph that "should private individuals wish to
undertake coastal protection on the esplanade reserve, landowner approval
would have to be sought from the ACC and the necessary resource consents
obtained. Similarly, any works below MHWS will require consent approval from
the ARC."
The T&T
report also suggests that beach replenishment could be considered in embayed
shorelines as well as replanting of the cliff area.
Seawalls
may be the only appropriate protection for many properties on Kennedy Point
due to the nature of the cliff face, where they are likely to have only minor
effects on public access and landscape values, but seawalls or other hard
structures will generally not be an appropriate means of protection in
unmodified coastal environments . Hard structures in other areas may limit
public access to beaches, cause a loss of the dry sand area and lead to
inappropriate development in the coastal area. Their failure can cause
ongoing problems and a greater armouring of the coastal area. The objective
and policies in clause 8.3.3 seek to protect existing natural coastal defences
and prevent the use of new hard engineered structures where they are likely to
have an adverse effects on the coastal environment.
The work
undertaken by Council at Kohimarama and St Heliers was in a highly modified
coastal environment where beach sand replenishment occurred and artificial
reefs were built in order to retain the sand on these beaches.
| Planner's
recommendations about submissions seeking a reconciliation of the competing
Council policy decisions on the role of seawalls That
submissions
86/5, 293/5, 360/5, 606/5, 622/5, 623/5, 624/5, 625/5, 755/5, 756/5, 757/5,
758/5, 759/5, 760/5, 761/5, 762/5, 763/5, 764/5, 765/5, 766/5, 767/5, 768/5,
769/5, 795/5, 838/5,
846/5, 847/5, 848/5, 860/5, 1124/5, 1188/5,
1189/5,
1212/5, 1213/5, 1222/5, 1246/5, 2051/5, 2052/5, 2059/5, 2090/5, 2548/5,
2565/5, 2590/5, 2627/5, 2629/5, 2698/5, 3027/5, 3555/5 be rejected
.
|
4.8 Submissions about providing for sea walls
which do not impede public access as a controlled activity
Submissions
dealt with in this section:
86/6, 293/6, 360/6,
622/6, 623/6, 624/6, 625/6,
720/6, 755/6, 756/6, 757/6, 758/6, 759/6, 760/6,
761/6, 762/6, 763/6, 764/6, 765/6, 766/6, 767/6, 768/6, 769/6, 795/6, 838/6,
846/6, 847/6, 848/6, 860/6, 1124/6, 1188/6,
1189/6, 1212/6, 1213/6, 1222/6,
1246/6, 2051/6, 2052/6, 2059/6, 2090/6, 2548/6, 2565/6, 2590/6, 2627/6,
2629/6, 2698/6, 3027/6, 3555/6, 3606/6
4.8.1 Decisions requested
Provide
for sea walls which protect land from coastal erosion and which do not impede
public access as a controlled activity
4.8.2
Planner's analysis and recommendations
Sea walls,
groynes and other methods of shoreline armouring may protect private property,
but in the case of sandy beaches, may cause the loss of the dry sand beach
area available to the public or have adverse effects on the local
environment. Hard structures can also adversely affect the natural appearance
of coastal areas and replace natural processes that may protect the coast from
coastal erosion. In some areas the presence of armouring structures may also
encourage inappropriate intensification or development in coastal hazard
areas. Failure of sea walls and groynes may lead to further inappropriate
modification of the coastal environment. Sea walls in one area may affect the
accretion or movement of sand in other areas. Seawalls paid for by Council
may enable beachfront interests to enjoy the benefit of a near-shore location
while externalising the costs onto a wider community. Because of these issues
and the general comments in section 4.9.2 below about controlled activities it
is not considered appropriate to provide for sea walls as a controlled
activity.
| Planner's
recommendations about submissions about providing for sea walls, which do not
impede public access as a controlled activity: That
submissions:
86/6, 293/6, 360/6, 622/6, 623/6, 624/6, 625/6,
720/6, 755/6, 756/6, 757/6,
758/6, 759/6, 760/6, 761/6, 762/6, 763/6, 764/6,
765/6, 766/6, 767/6, 768/6,
769/6, 795/6, 838/6, 846/6, 847/6, 848/6, 860/6, 1124/6, 1188/6,
1189/6,
1212/6, 1213/6, 1222/6, 1246/6, 2051/6, 2052/6, 2059/6, 2090/6, 2548/6,
2565/6, 2590/6, 2627/6, 2629/6, 2698/6, 3027/6, 3555/6, 3606/6
be rejected.
|
4.9 Submissions about development being a controlled
activity where a geotechnical report exists for a site.
Submissions
dealt with in this section:
86/7, 293/7, 360/7,
622/7, 623/7, 624/7, 625/7,
720/7, 755/7, 7557, 757/7, 758/7, 759/7, 760/7,
761/7, 762/7, 763/7, 764/7, 765/7, 766/7, 767/7, 768/7, 769/7, 795/7, 838/7,
846/7, 847/7, 848/7, 860/7, 1124/7, 1188/7,
1189/7, 1212/7, 1213/7, 1222/7,
1246/7, 2051/7, 2052/7, 2059/7, 2090/7, 2548/7, 2565/7, 2590/7, 2627/7,
2629/7, 2698/7, 3027/7, 3555/7, 3606/7.
4.9.1
Decisions requested
Acknowledge on an individual site basis that where a geotechnical report
exists from a registered geotechnical engineer, development will become a
controlled rather than a discretionary activity
4.9.2
Planner's analysis and recommendations
The council has intentionally
omitted the controlled activity status from the Plan. In the past, the
council has used the controlled activity status in the Isthmus Plan, the
Central Area Plan and in the operative Hauraki Gulf Islands Plan.
Considerable experience has led the council to the view that, in the main, the
use of the controlled activity status does not provide the council with
sufficient discretion to address the adverse effects associated with
particular proposals. This is because the council is not able to decline an
application for a controlled activity but can only impose conditions relating
to matters over which it has reserved control. Council cannot impose
conditions which require such significant modification as to fundamentally
alter the proposal. To do so would effectively negate the consent granted and
prevent the activity from taking place. Not all proposals which warrant
assessment through the resource consent process can be adequately mitigated by
the use of conditions. Some proposals need to be declined or substantially
modified.
There will be other submissions
that seek a controlled activity status for specific activities. These
submissions will be considered in other hearing reports. If, as a result of
these submissions, the council does decide to introduce a controlled activity
status, then it will be appropriate at that time to reconsider whether some or
all development on sites with a geotechnical reports should be a controlled
activity. However, at this time, it is recommended that the submissions
seeking a controlled activity status, be rejected.
It is noted that clause 8.6.1
states that where an appropriately qualified engineer confirms that the land
will not be subject to flooding, erosion or instability, no consent will be
required under part 8.
| Planner's
recommendations about submissions seeking that development be a controlled
activity where a geotechnical report exists for a site: That
submissions
86/7, 293/7, 360/7, 622/7, 623/7, 624/7, 625/7,
720/7, 755/7,
756/7, 757/7,
758/7, 759/7, 760/7, 761/7, 762/7, 763/7, 764/7, 765/7, 766/7, 767/7, 768/7,
769/7, 795/7, 838/7, 846/7, 847/7, 848/7, 860/7, 1124/7, 1188/7,
1189/7,
1212/7, 1213/7, 1222/7, 1246/7, 2051/7, 2052/7, 2059/7, 2090/7, 2548/7,
2565/7, 2590/7, 2627/7, 2629/7, 2698/7, 3027/7, 3555/7, 3606/7
be rejected
|
4.10 Submissions about Council working with residents and
property owners to develop an appropriate policy response to issues of erosion
and stability.
Submissions
dealt with in this section:
86/8, 293/8, 360/8,
622/8, 623/8, 624/8, 625/8, 755/8, 756/8, 757/8, 758/8, 759/8, 760/8, 761/8,
762/8, 763/8, 764/8, 765/8, 766/8, 767/8, 768/8, 769/8, 795/8, 838/8, 846/8,
847/8, 848/8, 860/8, 1124/8, 1188/8,
1189/8, 1212/8, 1213/8, 1222/8,
1232/1,
1246/8, 2051/8, 2052/8, 2059/8, 2090/8,
2227/5, 2565/8, 2590/8, 2629/8,
2698/8, 30278, 3555/8, 3606/8
4.10.1
Decisions requested
That the
council dedicate sufficient specialist resources to work with the residents
and property owners as well as the Auckland Regional Council to develop an
appropriate policy response to issues of erosion and stability in those areas
that suffer from them
4.10.2
Planner's analysis and recommendations
The
objectives, policies and rules in Part 8 of the proposed Plan are believed to
be an appropriate policy response to the issues of erosion and instability in
areas that suffer from them.
As noted
previously the council has undertaken to give particular attention to the
proper management of the stormwater flow from the roading system servicing
Kennedy Point, it will allow access to Council reserve land around Kennedy
Point to undertake the necessary remedial works to the cliff edge, and will
share information on suggested property management approaches to minimise the
rate of erosion. The Council is unlikely to oppose any reasonable
application to the ARC by residents wishing to construct seawalls in
appropriate locations below Kennedy Point.
The work
undertaken by the Auckland City Council and Auckland Regional Council in
relation to Kennedy Point is and example of Council working with property
owners. As described in 4.3.2 of this report, Council commissioned Tonkin and
Taylor to investigate erosion issues in conjunction with specialist council
officers and property owners. Council will continue to deal with specific
issues as funding and priorities allow.
| Planner's
recommendations about submissions seeking that council work with residents and
property owners to develop an appropriate policy response to issues of erosion
and stability: That
submissions:
86/8, 293/8, 360/8, 622/8, 623/8, 624/8, 625/8, 755/8, 756/8, 757/8, 758/8,
759/8, 760/8, 761/8,
762/8, 763/8, 764/8, 765/8, 766/8, 767/8, 768/8, 769/8,
795/8, 838/8, 846/8, 847/8, 848/8, 860/8, 1124/8, 1188/8,
1189/8, 1212/8,
1213/8, 1222/8,
1232/1, 1246/8, 2051/8, 2052/8, 2059/8, 2090/8,
2227/5,
2565/8, 2590/8, 2629/8, 2698/8, 3027/8, 3555/8, 3606/8 be accepted
without changes to the text.
|
4.11 A submission seeking the alignment of any proposals on
natural hazards with the principles of the RMA so as to avoid, remedy or
mitigate.
Submissions
dealt with in this section: 325/2
4.11.1 Decisions requested
To align
any proposal on natural hazards with the principles of the RMA 1991 so as to
"avoid, remedy or mitigate".
4.11.2 Planner's analysis and recommendations
It is
believed that the natural hazard objectives, policies and rules are consistent
with and align with the principles of the RMA 1991. The submitter is
encouraged to attend the hearing and provide specific examples for the panel
to support their submission. Overall it is considered that this submission
can be accepted without changes to the plan.
| Planner's
recommendations about submissions seeking the alignment of any proposals on
natural hazards with the principles of the RMA, so as to avoid, remedy or
mitigate. That
submission
325/2 be accepted
without changes to the text or maps.
|
4.12 A submission supporting the recognition of flood plains,
at risk soil and erosion areas in the planning maps.
Submissions
dealt with in this section:
3061/165, 3061/166,
3061/167.
4.12.1
Decisions requested
The recognition of
flood plains, at risk soil and erosion areas in the planning maps is
supported.
4.12.2 Planner's analysis and recommendations
That the
submissions be accepted.
| Planner's
recommendation about a submission supporting the recognition of flood plains,
at risk soil and erosion areas in the planning maps.
That
submissions
3061/165,
3061/166 and
3061/167 be accepted
without changes to the text or maps.
|
4.13 Submissions relating to climate change.
Submissions
dealt with in this section:
536/1,
1166/7 and
3106/4
4.13.1 Decisions requested
- That
the council, in accordance with the Ministry of Environment's request, express
clearly the fact of climate change and how to mitigate and adapt to the
climate change. Request that council state: "The partnership between Auckland
City Council and the Ministry for the Environment aims to improve awareness,
understanding of the effects of climate change and ways of mitigating this
change within the local government sector, leading to increased long-term
sustainable behaviour in relation to mitigating and adapting to climate change
(536/1).
- 2.
That "at risk areas" from effects of climate change
are identified and the district plan ensures those areas are managed so that
new development and infrastructure are not built on those areas and
initiatives are undertaken to reduce risks to existing development (1166/7)
Strengthen the plan in
its treatment of climate change (3106/4).
4.13.2 Planner's analysis and recommendations
Whilst Part
8 only mentions climate change in passing with reference to section 7 of the
RMA, it was difficult at the time of the notification of the Plan for Council
to quantify the effects of climate change, specifically on the Hauraki Gulf
Islands. Council is commissioning further work on possible changes to
rainfall, wind, sea level and storm surge frequency for the Auckland area as a
result of climate change. If, as a result of this work, the plan provisions
are likely to be insufficient then a plan change will be undertaken. On
average though, it is expected that average temperatures in New Zealand will
increase by about 10C by the 2030s and 2-30C by the 2080s and using moderate
projections it is possible that sea level rise will be between 30-50cm by
2100, exacerbating coastal erosion, sea inundation during storms, salinisation
of fresh water and drainage of low lying lands. More episodes of heavy
rainfall are likely and a greater risk of severe winds and storms. The number
of hot days is expected to increase in the northern North Island.
What
policies and rules of Part 8 seek to do is to avoid development in areas that
are likely to be affected by climate change - areas prone to flooding, coastal
erosion, slippage, subsidence. The rules also seek to prevent the modification
of hazard prone areas or natural defences such as sand dune areas, so that
they will maintain their resilience to natural hazard events arising from
climate change.
The
development controls in part 10c including indigenous vegetation protection
and exotic tree protection also contribute to reducing greenhouse gases in the
atmosphere.
The writer
is unaware of any formal partnership between Auckland City Council and the
Ministry of the Environment and the inclusion of the statement requested by
the submitter in the district plan may be misleading.
Natural
hazard areas (which may be at risk from the effects of climate change) known
to the Council when the plan was notified, are identified on the inner islands
planning maps. These natural hazard areas are flood prone areas (types A and
B), soil warning areas and soil register areas, and erosion risk zones.
Because of a lack of reliable information for the outer islands there are no
natural hazard areas identified on the outer islands planning maps. The
policies and rules in part 8 will take a precautionary approach and will
ensure that activities are not located in areas likely to be subject to
natural hazard events, in the absence of information known to Council and/ or
shown on the planning maps. These policies and rules also seek to prevent the
modification of hazard prone areas so that they maintain their resilience to
natural hazard events arising from climate change and to ensure changes to
hazard prone areas will not increase the risk to existing development.
It is
therefore considered that the plan provisions do identify many areas that are
at risk from the effects of climate change. Once further research and
analysis is undertaken there may be additional at risk areas identified.
| Planner's
recommendations about submissions relating to climate change:
That
submissions 1166/7 and
3106/4 be accepted
without any change to the text or maps
That
submission
536/1 be rejected
|
4.14 A submission requesting that works authorised by statute
or regulations be a permitted activity.
Submissions
dealt with in this section: 941/44
4.14.1 Decisions requested
Clause 8 be amended to include the following activity (or words to like
effect) as a permitted activity:
"The actions of any
person in carrying out work which is authorised by statute or regulations
(including the Electricity Act 1992 and the Electricity (Hazards from Trees)
Regulations 2003)".
4.14.2 Planner's analysis and recommendations
There are
some situations where work authorised by statute or regulation might legally
override rules within the proposed plan and could be considered as a permitted
activity. The matter raised by the submitter in connection with the
Electricity Act 1992 and the Electricity (Hazards from Trees) Regulations 2003
is also addressed in part 5- network utility services, specifically clause
5.6.7. This is a more appropriate place for the proposed rule such as the
submitter proposes, which could apply to many parts of the proposed plan.
| Planner's
recommendations about a submission requesting that works authorised by statute
or regulation be a permitted activity .
That
submission
941/44 be
be accepted in part
|
4.15 A submission requesting that part 8 be amended to include
measures to manage and avoid erosion including stormwater management and
revegetation programmes.
Submissions
dealt with in this section: 2227/2
4.15.1 Decisions requested
Amend
Part 8 of the Proposed District Plan to include measures to manage and avoid
erosion including stormwater management and revegetation programmes
4.15.2 Planner's analysis and recommendations
The
impervious surface area rules in part 10c.4.9 recognise that stormwater must
be disposed of on site and seek to control the amount of impervious surfaces
on small sites, so that the adverse effects of stormwater when concentrated by
impervious surfaces are minimised. Because in nearly all areas stormwater
and wastewater is not reticulated, sufficient permeable surfaces must be
available on every site to dispose of both the stormwater generated from
impervious surfaces on the site and for the wastewater generated on that
site. The amount of vegetation cover, the slope of the land, the soil types
and the saturation of the soil moderate the absorption of stormwater.
Stormwater that is not absorbed on site will travel across other land until it
finds its way to a water body.
The inner
islands planning maps identify flood prone land areas in western Waiheke and
the rules in part 8 prevent development or activities (without a resource
consent) in identified flood prone areas. In the absence of identified flood
prone areas, the rules in part 8 require a resource consent for any
building, structure or earthworks activity at an elevation less than 1 metre
above the edge of adjacent permanent stream, river, wetland or lake (see rule
8.5.1).
The rules
in part 8 require a resource consent for the removal of any vegetation:
- on land
where the slope is steeper than 1 in 3;
- within 5
metres of the centreline of any stream, or river, or the edge of any lake or
wetland;
and the
removal of indigenous vegetation greater than 2 metres in height within 10
metres of the centreline of any stream or river or the edge of any wetland to
prevent erosion of streams, rivers and wetlands. The protection of this
vegetation helps to prevent erosion. Vegetation is also protected by other
rules e.g. 10c.5.1, 10c.5.2 and 12.11.13
The
proposed rules will also protect vegetation by requiring a resource consent
for any building, structure or earthworks activity:
- within 20m
of a coastal cliff with a angle steeper than 1 in 3;
- on any
slope with an angle greater than 1 in 2; and
- the removal
of vegetation from sand dunes that are within 40 metres of mean high water
springs (see rule 8.5.1).
The issue
of revegetation is addressed as part of the assessment criteria for
discretionary activities, and is intended to be used as a means of mitigating
the effects of some activities.
No further
amendments are considered necessary to Part 8 to
manage and avoid erosion including stormwater management and revegetation
programmes as various other controls throughout the plan achieve this.
| Planner's
recommendations about a submission requesting that part 8 of the proposed plan
include measures to avoid erosion including stormwater management and
revegetation programmes.
That
submission
2227/2 be accepted
without changes to Part 8.
|
4.16 A submission requesting that part 8 be
reviewed, integrated, mandated and upgraded.
Submissions
dealt with in this section:
3061/52
4.16.1 Decisions requested
Part 8.0 Natural
hazards is opposed in it present form until it is reviewed, integrated,
mandated by the community and upgraded to:
- Take
account of climate change issues e.g. sea level rise
- Take
account of development in coastal amenity areas
- Take
account of radical / extreme weather events
- Apply
the HGMPA to this part of the Plan
- Ensure a
complete coverage in relation to coastal erosion and slippage, specific to the
effectiveness of the building controls in particular.
- Recognise the role of on-site stormwater runoff in coastal erosion
- Integrated comprehensive waters management system
4.16.2 Planner's analysis and recommendations
With
regards to climate change, sea level rise and radical/extreme weather events
this is addressed in section 4.13 of this report. Part 8 controls development
in all coastal areas, including coastal amenity areas, through restriction on
development and activities within 20m from a coastal cliff with a angle
steeper than 1 in 3 and with restrictions on the removal of vegetation from
sand dunes that are within 40 metres of mean high water springs.
The rules
within part 8 take a precautionary approach in the absence of this information
by setting limitations on activities in areas that have a high probability of
coastal erosion and slippage. Thus the rules (8.6.1) propose to limit
development and activities
- within 20m
from a coastal cliff with a angle steeper than 1 in 3;
- on any
slope with an angle greater than 1 in 2; and
- at an
elevation less than 3 metres above mean high water spring if the activity/
development is within 20m of mean high water springs;
- at an
elevation less than 2 metres above mean high water spring if the activity/
development is more than 20m of mean high water springs.
and prevent
the modification and removal of sand dunes and vegetation from sand dunes that
are within 40 metres of mean high water springs. The use and effectiveness of
controls in the Building Act for land subject to natural hazards is
complementary to what the rules are proposing. The requirements of the
Building Act in natural hazard areas are outlined in the explanation to part
8.3.1 of the proposed plan.
On-site stormwater runoff may be a contribution in
some cases to coastal erosion and it is addressed to some extent in policy 2
of objective 8.3.2. The impervious surface area rules in part 10c.4.9 also
recognise that stormwater must be disposed of on site and seeks to control the
amount of impervious surfaces on small sites, so that the adverse effects of
stormwater when concentrated by impervious surfaces are minimised. This
matter is also dealt with by building regulations. Clause E1 (Surface Water)
of the New Zealand Building Regulations 1992 requires buildings and site works
to be constructed in a way that protects people and other property from
the adverse effects of surface water. Specifically clause E1 requires that
surface water resulting from an event having a 10% probability of occurring
annually (a 1 in 10 year rainfall event) and which is collected or
concentrated by buildings or site works, to be disposed of in a way that
avoids the likelihood or damage to other property. Thus, clause E1 can be
used to prevent stormwater runoff affecting coastal erosion on esplanade
reserves or properties not owned by the person discharging the stormwater.
Whilst the
Hauraki Gulf Islands Marine Park Act 2000 is not specifically mentioned in
part 8, the provisions in part 8 do not conflict with sections 7 and 8 of the
Act.
As noted in
section 4.15.2 of this report, rules are proposed in part 10c.4.9 to limit the
amount of impervious surfaces on small sites, to limit the adverse effects of
stormwater, whilst part 4.8 of the proposed plan deals with wastewater, and
the Building Act deals with the requirements for drinking water.
|
Planner's recommendations about a submission requesting that part 8 be
reviewed, integrated, mandated and upgraded.
That
submission
3061/52 be
rejected.
|
4.17 A submission requesting that clause 8.3.3 be retained but
that the policies in clause 8.3.2 be amended to specifically refer to the
control of stormwater runoff along coastal areas and the restriction of
pedestrian access to dunes.
Submissions
dealt with in this section: 1250/17
4.17.1 Decisions requested
Retain clause 8.3.3
but amend the policies in clause 8.3.2, to specifically refer to the control
of stormwater runoff along coastal areas and the restriction of pedestrian
access to dunes.
4.17.2
Planner's analysis and recommendations
As noted in
section 4.15 above the control of stormwater runoff is adequately dealt with
by the Building Regulations.
The
restriction of pedestrian access to sand dunes is not best controlled under a
district plan. If the Council is the owner of land on which there are sand
dunes, it can as land owner reasonably control access to those dunes if it is
necessary to prevent their damage or prevent the loss of vegetation. Beach
care programs typically fence of regenerating areas and control access to
prevent damage. Council's Public Places Bylaw makes it an offence to cause
damage to a public place or to remove sand from a public place, and requires
persons wishing to gain access to a public to use a designated access where
this is available. As Council's bylaws apply down to mean low water mark it
can restrict access to dune areas if it provides designated access areas.
| Planner's
recommendations about a submission requesting that clause 8.3.3 be retained
but that the policies in clause 8.3.2 be amended to specifically refer to the
control of stormwater runoff along coastal areas and the restriction of
pedestrian access to dunes.
That
submission
1250/17
be rejected.
|
4.18 A submission relating to drought conditions.
Submissions
dealt with in this section: 3521/69
4.18.1 Decisions requested
Amend clause 8.3.2 to
include a policy that recognises the relationship between the nature of
non-reticulated water use on the islands creating a higher risk to residents
and businesses from drought conditions
4.18.2 Planner's analysis and recommendations
Whilst
drought is a natural hazard the writer believes that the residents of the
Hauraki Gulf Islands are well aware of the risks of drought and the need to
conserve water in summer or during drought conditions and the addition of a
policy as suggested would be of little practical value. Council would not
generally include any rules to give effect to such a policy - such as rules on
the size of water tanks or the requirement to use water saving devices. It
is noted that section 18 of the Building Act 2004 states that any person who
carries out building work is not required by the Act to achieve performance
standards that are additional to, or more restrictive than the performance
criteria prescribed in the building code in relation to that building work.
Severe drought conditions are also likely to be a region wide issue and would
affect the water supply dams that serve reticulated water supplies in the
region.
| Planner's
recommendation about a submission relating to drought conditions That
submission
3521/69 be
rejected.
|
4.19 A submission requesting that clause 8.3.2 be amended by
adding a policy that seeks to avoid development in hazard prone areas.
Submissions
dealt with in this section: 3521/70
4.19.1 Decisions requested
Amend clause 8.3.2 by
adding a policy that seeks to avoid development in hazard prone areas
4.19.2 Planner's analysis and recommendations
The
additional policy proposed by the submitter is similar to the second policy in
part 8.3.1 which states: "By preventing new development and activities in
high risk areas where the effects of the natural hazard cannot be adequately
avoided or mitigated". There are many types of hazard prone areas but it
is only reasonable to exclude activities from areas where the risk of a hazard
event occurring is high and/or where the consequences of natural hazard event
are serious. No additional policy as suggested by the submission is
recommended.
Planner's
recommendation about a submission requesting that clause 8.3.2 be amended to
include a policy that seeks to avoid development in hazard prone areas.
That
submission
3521/70 be
rejected.
4.20 A submission requesting that clause 8.3.2 be amended to
recognise that integrated management is required for many coastal hazard
mitigations proposals.
Submissions
dealt with in this section: 3521/71
4.20.1 Decisions requested
Amend clause 8.3.2 to
recognise that integrated management is required for many coastal hazard
mitigations proposals. It should be noted that resource consents may be
required by both the ARC and ACC
4.20.2 Planner's analysis and recommendations
The issue
of integrated management for coastal hazard mitigations is already addressed
in the second paragraph of part 8.6.3 where it notes that "the placement of
any structure in, on, under or over the bed of any lake or river or stream or
below mean high water springs is controlled by the Auckland Regional
Council." No change to clause 8.3.2 is recommended.
| Planner's
recommendation about a submission requesting that clause 8.3.2 be amended to
recognise that integrated management is required for many coastal hazard
mitigations proposals.
That
submission
3521/71 be
rejected.
|
4.21 A submission requesting that clause 8.3.1(2) recognises
that farming activity, particularly grazing, is normally appropriate for areas
that are at risk of natural hazards.
Submissions
dealt with in this section:
1243/65
4.21.1 Decisions requested
With respect to clause
8.3.1(2) provide that farming activity, particularly grazing, is normally
appropriate for areas that are at risk of natural hazards.
4.21.2 Planner's analysis and recommendations
Policy
8.3.1(2) seeks to prevent new development and activities in high risk areas
where the effects of the natural hazard cannot be avoided or mitigated. Rule
8.6.1(1) outlines the type of development and activities that the rule applies
to. The rule as proposed did not intend to apply to the existing use of land
for horticulture or pastoral farming, but it would include the modification of
land that is hazard prone for horticulture or pastoral farming including the
removal of vegetation from hazard prone land. It would also apply to the
construction of new buildings or structures for horticulture or pastoral
farming. It is appropriate that the term 'land use development activity' be
removed from clause 8.6.1.1(a) because there are sufficient controls on all
such activities in rule 8.6.1 as to render the term unnecessary. However a
control on the removal of vegetation from soil warning areas, soil register
areas or erosion risk zones would be required to prevent removal of vegetation
where it could increase erosion and slips or slumps. Activities such as
grazing should not have an adverse effect on hazard prone land and should not
be caught by rule 8.6.1. The removal of the term 'land use development
activity' would avoid confusion with this rule and clarify policy 8.3.1(2).
| Planner's
recommendations about a submission requesting that clause 8.3.1(2) recognises
that farming activity, particularly grazing, is normally appropriate for areas
that are at risk of natural hazards.
That
submission
1243/65 be accepted
in part and
-
the term "land use development activity" be removed from rule 8.6.1;
-
that a new rule be added after rule 8.5.1(3)which reads: the removal of any
vegetation more than 2m high from any area identified as a soil warning area,
soil register area or in an erosion risk zone.
|
4.22 A submission requesting that clause 8.5.1 should not
apply to activities undertaken by the Department of Conservation in accordance
with the functions under the Conservation Act 1987.
Submissions
dealt with in this section:
2517/5
4.22.1 Decisions requested
That clause 8.5.1 be
amended to include a fourth rule that states:
"This rule does not
apply to activities within the Conservation Land Unit undertaken by DOC for
structures, facilities and operations in accordance with its functions under
the Conservation Act 1987".
4.22.2 Planner's analysis and recommendations
The
Department of Conservation like other land owners are required to obtain
building consents where applicable for structures and buildings and are thus
subject to the requirements of section 71 of the Building Act. The writer
believes that other activities undertaken by DOC on the conservation land unit
in accordance with its functions under the Conservation Act 1987, such as
vegetation removal, land use activities, earthworks and the storage of
hazardous substances are likely to be at a small scale. This is also
consistent with the rules for conservation land units in rule 10a.25.6.1.
| Planner's
recommendations about a submission requesting that clause 8.5.1 should not
apply to activities within the conservation land unit undertaken by the
Department of Conservation in accordance with its functions under the
Conservation Act 1987.
That
submission
2517/5 be accepted
and a new exception be added to clause 8.5.1 which reads : "Rules
1-5 above do not apply to activities within the conservation land unit
undertaken by the Department of Conservation for structures, facilities and
operations in accordance with its functions under the Conservation Act 1987".
|
4.23 Submissions relating to accessory structures and
buildings
Submissions
dealt with in this section: 2631/14,
2631/15 and
3098/2&3
4.23.1 Decisions requested
Amend clause 8.5
(2631/14) and 8.6 (2631/15) to provide for construction of minor structures
and additions and alterations to existing buildings, as a Controlled Activity,
subject to appropriate Matters for Control and without the need for public
notification, to the satisfaction of the submitters).
Provide exemptions for
small scale accessory structures (3098/2) and provide for all building work as
a restricted discretionary activity (3098/3).
4.23.2 Planner's analysis and recommendations
It is
difficult to determine what the submitters consider to be minor structures,
additions and alterations to existing buildings or small-scale accessory
buildings that could be located on hazard prone land. Despite the size of an
accessory building or a minor structure, it could be placed in area subject to
natural hazards, and could increase the severity of natural hazards both on
the land it was placed or on other land. If, for example, an accessory
building or minor structure was placed in a flood prone area, it might
increase the risk of flooding of adjacent land by creating an obstruction to
the storm flow. If it was constructed in a slip prone area, any earthworks
required for its construction might increase the potential for slippage on
that land. In addition, the Council cannot in the case of an accessory
building, minor structure or major alterations to existing buildings, exempt
itself from the requirements of section 71 of the Building Act. Section 71
prevents a building consent from being granted for a building or for major
additions or alterations to a building if the land on which the building work
is to be carried out is subject or likely to be subject to one or more natural
hazards. The comments in section 4.9.2 of this report regarding controlled
activities are also relevant to these submissions.
There is however merit in submission
3098/3 in providing for additions or alterations to exisiting buildings or
small accessory structures as a restricted discretionary activity. It is also
appropriate that most building work in natural hazard areas, such as building
work covered in rule 8.6.1.(1) be a restricted discretionary activity as the
matters of discretion can easily be defined. In this case it is whether the
building work avoid, remedy or
mitigate the potential impacts of the natural hazard; or accelerate or
exacerbate the probability of a natural hazard occurring and/or the potential
impacts of the natural hazard.
| Planner's
recommendations about submissions relating to accessory structures and
buildings.
That submissions 2631/ 14,
2631/15 and 3098/2 be rejected. That
submission 3098/3 be accepted as shown in
Appendix 3.
|
4.24 Submissions relating to vegetation removal (8.5 and 8.6)
Submissions
dealt with in this section:
526/15,
527/15,
528/15,
529/15,
539/15,
1243/66,
3098/1,
2631/14 and
3098/3
4.24.1 Decisions requested
Amend clause 8.5.1 to
ensure that vegetation removal from slopes greater than 18 degrees as part of
an approved rural management plan for vineyard or pastoral productive purposes
is provided for (526/15,
527/15,
528/15,
529/15,
539/15).
Provide in clause
8.5.1 for the removal of riparian vegetation as a permitted activity
(1243/66).
Provide for limited
vegetation removal as a permitted activity and change the status of all
vegetation removal to a restricted discretionary activity (3098/1&3).
Amend clause 8.5 and
8.6 to provide for minor vegetation removal, as a Controlled Activity, subject
to appropriate Matters for Control and without the need for public
notification, to the satisfaction of the submitters (2631/14 & 15).
4.24.2 Planner's analysis and recommendations
Whilst
vegetation removal on slopes greater than 1 in 3 could be included in a rural
management plan, it is not clear to the writer how this should be "provided
for". If it is meant that this removal should be able to be incorporated as a
matter within a rural management plan requiring a resource consent then the
writer would agree. If however the submitters mean that vegetation removal on
slopes greater than 1 in 3 should be a permitted activity just because the
activity is mentioned in a rural management plan, then this would be opposed
by the writer.
Technical
publication (TP)71 from the Auckland Regional Council "Slope Instability
Hazards in the Auckland Region: A Preliminary Assessment" identifies (at a
regional scale) that most of the Hauraki Gulf Islands have either a moderate
or a high slope instability hazard partly due to moderate to steep inland
slopes. TP 71 categorises steep slopes as being 16-200.
The degree
of vegetation cover and the slope of the land can affect slope stability and
erosion. Technical Publication 90 "Erosion and Sediment Control" by the ARC
notes that vegetation is, without question, the most effective long-term form
of erosion control. It notes that vegetation shields the surface from the
impacts of falling rain, slows the velocity of runoff, holds soil particles in
place and maintains the soil's capacity to absorb water. Data from the United
States suggests that there may be 1000 times the sediment yield from disturbed
sites during construction compared with permanent forest cover.
The
proposed plan seeks to protect riparian vegetation, to minimise streamside
erosion, and to protect the health of streams from sedimentation. Riparian
vegetation also moderates the effects of flooding by slowing the entry of
water into steams and by reducing the velocity of water in-stream, which
limits erosion during flooding events. Riparian vegetation has also been
shown to reduce the total suspended solids from overland flow. The erosion of
streams may have adverse effects on structures and activities located near
those streams.
Rules in
8.5.1 are restricted discretionary activities for the removal of vegetation on
steep slopes, and near streams, rivers, lakes and wetlands. Rule 8.5.1(2) and
8.5.1(3) does however allow the removal of plant pest species near any
streams, rivers, lakes or wetlands as a permitted activity to prevent these
from blocking waterways and causing flooding. Erosion from the removal of
vegetation on one site can have significant off-site effects such as siltation
of watercourses, which may modify or destroy in-stream values and in serious
cases may also modify estuaries and coastal habitats, thus it is appropriate
that the removal of vegetation on steep slopes remains a restricted
discretionary activity.
Rule
8.6.1.1 (discretionary activities) requires a resource consent for any "land
use development activity". This would include the removal of vegetation in a
natural hazard area as part of an activity such as earthworks creating a
building site and so on. As noted in part 4.17.2 of this report, it may be
more appropriate that most of these activities are classified as restricted
discretionary activity. Part 8.6.1.2 requires a consent for the removal of
vegetation on sand dunes - because the removal of vegetation from sand dunes
can have severe effects on those dunes and their ability to withstand storm
events it is recommended that this activity remain a discretionary activity.
Submission
3098/1 seeks that part 8 should allow for limited vegetation removal as a
permitted activity and 3098/3 seeks that the status of all vegetation removal
should be a restricted discretionary activity. Submission
2631/14 and 15
seeks that the plan provide for minor vegetation removal as a controlled
activity. Neither submitter indicates what they consider "limited vegetation
removal" or "minor vegetation removal" would be for vegetation removal on
hazard prone land. The difficulty for Council is that the retention of some
areas of vegetation may be more important than the retention of other areas
even on the same site, because of the degree to which that vegetation may
prevent erosion or slippage. Submissions
2631/14 and 15 do not provide
information as to what matters of control would be of satisfaction to the
submitter.
As previously noted in section
4.9.2 of this report, the council has intentionally omitted the controlled
activity status from the Plan. Considerable experience has led the council to
the view that, in the main, the use of the controlled activity status does not
provide the council with sufficient discretion to address the adverse effects
associated with particular proposals. The council is not able to decline an
application for a controlled activity but can only impose conditions relating
to matters over which it has reserved control. Not all proposals for the
removal of vegetation can be adequately mitigated by the use of conditions to
prevent erosion or slippage. Some proposals for vegetation removal might need
to be declined or substantially modified.
The
requests of submissions
1243/66,
2631/14 and
2631/15 are thus opposed. The
request of submission 3098/1 is also opposed. In the case of
3098/3 some
vegetation removal is already provided for as a restricted discretionary.
4.25 Submissions requesting activities in clause 8.6.1 become
restricted discretionary activates
Submissions
dealt with in this section:
1285/9 and
3847/1
4.25.1 Decisions requested
If the soil warning
and soil register on sheet 7, map 2 (with particular reference to 28 Dolphin
Lane, Church Bay) is to remain, the rules contained in part 8 should be
amended so that any of the activities listed in clause 8.6.1 become restricted
discretionary activities (1285/9).
Activities in clause
8.6.1 should be restricted discretionary activities, and not discretionary
(3847/1)
4.25.2 Planner's analysis and recommendations
As
previously discussed, it is appropriate that many of the rules in part 8.6
would be more appropriate as restricted discretionary activities so that the
assessment of any application is confined to the extent to which the proposed
development or activity avoids, remedies or mitigates the natural hazard
present or the creation of a natural hazard. It is however recommended that
the soil warning and soil registers on all of the maps remain, to be
consistent with Council's responsibilities under section 31 of the RMA.
| Planner's
recommendations about submissions requesting that the rules in part 8 should
be amended so that any of the activities listed in clause 8.6.1 become
restricted discretionary activities.
That
submission
1285/9 and
3847/1 be accepted
in part and the necessary changes be made to part 8.6.1.
|
4.26 A submission relating to assessment criteria
Submissions
dealt with in this section:
3098/4
4.26.1 Decisions requested
In part 8, focus assessment criteria and matters to be considered for
practical application of rules
4.26.2 Planner's analysis and recommendations
The writer
believes that the assessment criteria and matters to be considered are focused
on practical outcomes to avoid development in hazard prone areas.
| Planner's
recommendation about a submission requesting the focusing of assessment
criteria and matters to be considered for the practical application of rules
(for all vegetation removal and building work as a restricted discretionary
activity).
That
submission
3098/4
be accepted in part with no changes to the text.
|
4.27 A submission supporting the recognition of flood plains
in the planning maps.
Submissions
dealt with in this section:
3061/165
4.27.1
Decisions requested
The recognition of
flood plains in the planning maps is supported
4.27.2 Planner's analysis and recommendations
The
submission is supported.
| Planner's
recommendation about a submission supporting the recognition of flood plains
in the planning maps .
That submission
3061/165 be accepted
|
4.28 Submissions regarding soil warning areas and soil
register areas.
Submissions
dealt with in this section:
359/1,
538/3,
1096/1,
1199/14,
1285/8, 2064/1,
3061/166
4.28.1 Decisions requested
- The soil
warning area on 18 Causeway Road (Lots 1 and 2, DP 68000) be removed (1199/14,
2064/1).
- The Soil
Warning and Soil Register notation on sheet 7, map 2 should be removed (with
particular reference to 28 Dolphin Lane, Church Bay) (1285/8).
- To remove
the "soil register area" designation from 21 Fairview Crescent, Rocky Bay
(359/1).
- To remove the
designation of "soil register area" from the planning map, as it applies to
the property at 21 Fairview Crescent, Rocky Bay (1096/1).
- That the soil
overlays imposed on 25 Ocean View Rd under the Plan, (specifically the "soil
warning area" and "soil register area"), be removed (538/3)
- The
recognition of at risk soil areas in the planning maps is supported
(3061/166).
4.28.2 Planner's analysis and recommendations
Soil
warning areas are areas where the soil is suspected or known to be unstable or
weak, because of its inherent nature, or because it has been an area of fill,
or possibly a refuse tip. Soil register areas are most commonly areas where
soil reports have been provided to council as part of a building consent
application. These reports are usually prepared because of concerns regarding
the site such as slope instability or weak ground, which may affect the
construction of buildings. Some soil reports may show only minor problems for
the site. If a soil report identifies an area of instability or weakness, the
site may be identified as unstable or weak on the Council's records.
The sites
above are identified on Council's Geographical Information Service as:
18 Causeway
Road - filled/weak ground and soil register area;
28 Dolphin
Lane - unstable/ suspected ground and soil register area;
21 Fairview
Crescent - soil register area;
25 Ocean
View Rd - filled weak ground and soil register area.
This
information would be included in LIMs (if it was not apparent from the
district plan) and PIMs, but it is appropriate that the planning maps have
this information because of Council's responsibilities under section 31 of the
RMA as well as its responsibilities under the Building Act 2004.
| Planner's
recommendations about submissions seeking the removal of soil warning areas
and soil register areas from the planning maps.
That
submissions
359/1,
538/3,
1096/1,
1199/14,
1285/8,
2064/1
be rejected
That
submission
3061/166
be supported.
|
4.29 A submission requesting the reinstallation of the flood
hazard designation (FH) on the planning maps.
Submissions
dealt with in this section:
2547/2
4.29.1 Decisions requested
Reinstall the flood
hazard designation (FH) on the planning maps
4.29.2 Planner's analysis and recommendations
The FH
flood hazard areas on the planning foils for Great Barrier Island in the
operative plan were not based on the real risk of flooding but simply on low
lying areas of land in land units 3 (alluvial flats) and land unit 4 (wetland
systems). Thus, the FH areas were not necessarily a real representation of
risk of flooding. Until more detailed studies are undertaken, the rules
within rule 8.6.1 which cover all areas of the Hauraki Gulf Islands that are
not identified as hazard prone on the planning maps, will adequately prevent
development in flood hazard areas that are not identified on those maps.
| Planner's
recommendations about a submission requesting the reinstallation of the flood
hazard designation (FH) on the planning maps.
That
submissions
2547/2
be rejected.
|
5.0 Conclusion
This report
has considered the decisions requested in submissions lodged regarding Part 8
- Natural Hazards of the Proposed Auckland City District Plan: Hauraki Gulf
Islands Section 2006.
The report
recommends whether submissions should be accepted or rejected and how
associated further submissions should be dealt with, and how the Plan should
be modified as a result. These recommendations are made prior to the hearing
of submissions and therefore without the benefit of evidence which may be
presented at that time. At this stage before the hearing, it is recommended
that this part of the Plan be approved, with amendments (as outlined in appendix 3), for the reasons outlined in this report.
| |
Name
and title of signatories |
Signature |
| Author |
Colin
Craig: Senior Planner |
|
| Reviewer |
Megan
Tyler, Manager: Islands |
|
| Approver |
Penny
Pirrit, Manager: City Planning |
|
Appendix 1
List of submissions and
further submissions (125kb PDF)
Summaries of submissions
Appendix 2
Summaries of submissions
Appendix 3
Recommended changes to
the Plan
Recommended changes to
parts 8.5 and 8.6 are included below:
8.5
Rules - restricted discretionary activities
8.5.1 Activities
The following are
restricted discretionary activities:
- The
removal of any vegetation (except for any species listed in
appendix 14 - List of plant pest species)
on any piece of land where the slope is steeper than 1 in 3 (18o).
- The
removal of any vegetation (except for any species listed in appendix 14 - List of plant pest species)
within 5m of the centreline of any stream or river or the edge of any lake or
wetland.
- The
removal of any indigenous vegetation greater than 2m in height within 10m of the
centreline of any stream or river or the edge of any wetland.
- 4. The removal of any vegetation more than 2m high from any area
identified as a soil warning area, soil register area or in an erosion risk
zone.
- 5. Any of the following:
- a. The location of any, building, permanent structure, fence or wall;
- b. Exterior additions or alterations to, or change of use of, any building
or structure;
- c. The placement of any septic tank, wastewater treatment and disposal
system, effluent disposal field, underground storage tank, water tank or
stormwater pipe or soakage field;
- d. Any earthworks;
- e. The storage of any hazardous substance in volumes that exceed the
permitted activity rules in part 9 - Hazardous facilities and contaminated
land;
When
located as follows:
- i. In any natural hazard area identified on the planning maps; or
- ii. In any of the following locations, subject to any more accurate
natural hazard information identified in the planning maps to the contrary:
- at an
elevation less than 1m above the edge of any adjacent permanent stream, river,
wetland or lake;
- within
a horizontal distance of 20m from the top of any coastal cliff with a slope
angle steeper than 1 in 3 (18o);
- on any
slope with an angle greater than or equal to 1 in 2 (26o);
- at an
elevation less than 3m above mean high water springs if the activity is within
20m of mean high water springs;
- at an
elevation less than 2m above mean high water springs if the activity is located
more than 20m from mean high water springs.
Exception
Provided that activities 4(a) to 4(e) above do not apply to any land located
within (i) or (ii) where a report from an appropriately qualified engineer
establishes that the land is not subject to, and will not be subject after any
proposed activity, building or other structure is completed, to any of the
following:
- flooding, in a 1 in 100 year storm
- coastal erosion over a 50 year time frame
- instability or erosion.
Rules 1-5 above do not apply to activities within the conservation land unit
undertaken by the Department of Conservation for structures, facilities and
operations in accordance with its functions under the Conservation Act 1987.
8.5.2 Notification
requirements
Except as provided
for by section 94C(2) of the RMA, applications for a resource consent for the
above activities will be considered without public notification or the need to
obtain the written approval of or serve notice on affected persons (in
accordance with section 94D(2) and (3) of the RMA).
8.5.3 Matters of discretion
The council has
restricted its discretion to considering the following matters:
- 1. The likelihood of a natural hazard event occurring, and the likely
extent of damage occurring as the result of that event. In considering this,
regard will be had to the extent to which site specific analysis of the hazard
(such as engineering stability or flooding reports) and its effects have been
undertaken and any other information the council may have on the site and
surrounding land.
- 2. The extent to which the proposal affects the potential impacts of the
natural hazard present, or has the potential to create a new natural hazard on
the subject land and any adjacent land. In considering this, regard will be had
as to whether the proposal is likely to:
- avoid,
remedy or mitigate the potential impacts of the natural hazard; or
- accelerate or exacerbate the probability of a natural hazard occurring and/or
the potential impacts of the natural hazard.
- 3. The extent of vegetation removal from areas such as steep slopes, near
streams, rivers, lakes or wetlands,
- 4. The extent to which the proposal ensures the replacement of any
vegetation which is damaged or removed from areas such as steep slopes, near
streams, rivers, lakes or wetlands. This will include the type of vegetation to
be used, it height, location and phasing of the planting
- 5. Methods to avoid or mitigate erosion or slippage of the land as the
result of the removal of vegetation.
- 6. The extent to which the proposal ensures that any storage tanks (above
ground or underground) installed in hazard prone areas are protected from
damage, flooding, spilling, dislocation and leakage in the event of a natural
hazard event.
- 7. The extent to which the proposal ensures that hazardous substances
stored in hazard prone areas are protected from flooding, spillage and leakage
in the event of a natural hazard event.
- 8. The extent to which the proposal includes non-structural solutions such
as planting to avoid, remedy or mitigate the hazard rather than hard engineering
solutions.
- 9. The extent to which landscape values, and public access are affected by
any structure used to avoid, remedy or mitigate any natural hazard.
- 10. The extent to which any building or structure listed in clause 8.6.1
located in a natural hazard area near the coast, can be relocated in the event
of severe coastal erosion and shoreline retreat.
8.6
Rules - discretionary activities
8.6.1 Activities
The activities
listed below are discretionary activities.
- Any of the following:
- The location of any land use development activity, building, permanent
structure, fence or wall.
- Exterior additions or alterations to, or change of use of, any building
or structure.
- The placement of any septic tank, wastewater treatment and disposal
system, effluent disposal field, underground storage tank, water tank or
stormwater pipe or soakage field.
- Any earthworks.
- The storage of any hazardous substance in volumes that exceed the
permitted activity rules in part 9 - Hazardous facilities and contaminated
land.
When
located as follows:
- i. In any natural hazard area identified on the planning maps; or
- ii. In any of the following locations, subject to any more accurate
natural hazard information identified in the planning maps to the contrary:
- at an
elevation less than 1m above the edge of any adjacent permanent stream, river,
wetland or lake
- within
a horizontal distance of 20m from the top of any coastal cliff with a slope
angle steeper than 1 in 3 (18o)
- on any
slope with an angle greater than or equal to 1 in 2 (26o)
- at an
elevation less than 3m above mean high water springs if the activity is within
20m of mean high water springs
- at an
elevation less than 2m above mean high water springs if the activity is located
more than 20m from mean high water springs.
Exception
Provided that (a) to (e) above do not apply to any land located within (i) or
(ii) where a report from an appropriately qualified engineer establishes that
the land is not subject to, and will not be subject after any proposed activity,
building or other structure is completed, to any of the following:
- flooding, in a 1 in 100 year storm
- coastal erosion over a 50 year time frame
- instability or erosion.
- 1.
The placement of any material, objects or structures, in or on any beach above
mean high water springs in a manner that may serve as a defence against coastal
erosion.
- 2.
The modification, alteration or removal of sand dunes and vegetation (except for
any species listed in appendix 14 - List of plant pest species)
on sand dunes within 40m of mean high water springs.
8.6.2 Explanation
Natural hazard
areas as identified on the planning maps include flood prone areas, areas
identified as filled, unstable or weak ground, including areas of suspected
slope instability or where soils reports are held; refuse tip sites with weak
ground, and coastal erosion risk areas. It does not include any wind zone
identified for the purposes of the Building Act 2004.
Flood prone areas
include type A flood plains, type B flood risk areas and secondary or overland
flow paths taken by stormwater on its way to a flood plain in a storm that is
more severe than a 1 in 10 year storm. Type A flood plains shown on the
council's planning maps and geographic information system ('GIS') are considered
by the council to be a reasonably accurate assessment of flooding in a 1 in 100
year storm. Type B flood risk areas shown on the planning maps or GIS are not as
accurate as type A areas and may be based on incomplete information.
8.6.3 Additional
requirements
There may be
instances where the requirements of section 71 of the Building Act 2004 will
prevent a building consent being issued, even though the activity is authorised
under the RMA by virtue of the above rules, if the council believes the land on
which the building work is to be carried out is subject to or likely to be
subject to one or more natural hazards. The council is likely to refer to any
information it has, including information stored on its GIS when making this
determination.
The placement of
any structure in, on, under or over the bed of a lake or any river or stream or
below mean high water springs is controlled by the Auckland Regional Council.
8.6.4 Assessment criteria
for discretionary activities
The council's
assessment of an application for a discretionary activity will include
consideration of the following matters:
-
The likelihood of a natural hazard event occurring, and the likely extent of
damage occurring as the result of that event. In considering this, regard will
be had to the extent to which site specific analysis of the hazard (such as
engineering stability or flooding reports) and its effects have been undertaken
and any other information the council may have on the site and surrounding land.
- The extent to which the proposal affects the potential impacts of the
natural hazard present, or has the potential to create a new natural hazard on
the subject land and any adjacent land. In considering this, regard will be had
as to whether the proposal is likely to:
- avoid,
remedy or mitigate the potential impacts of the natural hazard; or
- accelerate or exacerbate the probability of a natural hazard occurring and/or
the potential impacts of the natural hazard.
- The extent to which the proposal ensures that any storage tanks (above
ground or underground) installed in hazard prone areas are protected from
damage, flooding, spilling, dislocation and leakage in the event of a natural
hazard event.
- The extent to which the proposal ensures the replacement of any
vegetation which is removed or damaged.
- The extent to which the proposal ensures that hazardous substances
stored in hazard prone areas are protected from flooding, spillage and leakage
in the event of a natural hazard event.
- The extent to which the proposal includes non-structural solutions such
as planting to avoid, remedy or mitigate the hazard rather than hard engineering
solutions.
- The extent to which landscape values, and public access are affected by
any structure used to avoid, remedy or mitigate any natural hazard.
- The extent to which any existing natural features (e.g sand dunes in
coastal hazard areas) will provide protection from the natural hazard present.
- The extent to which any building, structure or activity listed in
clause 8.6.1 located in a natural hazard area near the coast, can be relocated
in the event of severe coastal erosion and shoreline retreat.
- The extent to which matters 1, 2, 8, 9 and 10 in clause 8.5.3 are
addressed.
- The extent to
which any proposed coastal protection works by the
placement of any material, objects or structures, in or on any area
located outside of the coastal marine area will be located and designed so as to
avoid adverse environmental effects including:
- long
term visual effects on the coastal landscape and amenity values
- any
likely increase in the coastal hazard posed to the coastline in question,
including increased rates of erosion, accretion, subsidence or slippage
- undermining of the foundations at the base of the structure
- erosion in front of, behind or around the ends of the structure
- settlement or loss of foundation material
- movement or dislodgement of individual structural elements
- off
shore or long shore loss of sediment from the immediate vicinity.
- The extent to which any existing natural features (e.g. sand dunes in coastal
hazard areas) will provide protection from the natural hazard present.
- Methods to avoid or mitigate erosion of sandunes as the result of their
modification, alteration or the removal of vegetation from the dune.